Land & Licensing
Gurgaon International City (GIC) Manesar — Land Acquisition & Licensing Status
Gurgaon International City (GIC) Manesar is not a government land-pooling township — it is a privately licensed colony built by M3M India Infrastructures (P) Ltd. on land it purchased directly, then got approved by Haryana's Town & Country Planning Department (DTCP) and registered with HARERA.

| Licensed land area | 56.57252 hectares (139.79375 acres) |
|---|---|
| Villages / revenue estates | Bas Haria & Jhund Sarai (Abad), Sectors M9, M10, M11, Manesar |
| District | Gurugram, Haryana |
| DTCP licence no. | 168 of 2025, dated 08.09.2025 |
| HARERA registration | RC/REP/HARERA/GGM/991/723/2025/94, dated 16.10.2025 |
| Declared project investment | ₹7,200 crore (developer-stated) |
| RERA-filed estimated project cost | ₹39,981.76 lakh (within project area) |
| Project window (per HARERA filing) | Start 01.10.2025 — completion 30.09.2034 |
How the land was acquired: licensing, not government acquisition
Unlike government-led planned cities that use land pooling or the Right to Fair Compensation Act (2013) with notified per-acre rates, GIC Manesar sits on land that the developer says it privately purchased and then licensed for development under Haryana's town-planning regime. The project's own disclosures describe it as "an industrial plotted colony, developed and promoted by M/s M3M India Infrastructure Private Limited...on a licenced land."
"Gurgaon International City" is an industrial plotted colony, developed and promoted by M/s M3M India Infrastructure Private Limited ("Promoter"), on a licenced land with area admeasuring 56.57252 Hectares (139.79375 Acres) situated in the revenue estate village of Bas Haria & Jhund Sarai, Abad, Sector-M9, M10 & M11, Manesar, Gurugram, Haryana. Approval for which was granted by DTCP vide Memo No. LC-5390/JE(SK)2025/35500 dated 09.09.2025 with Licence no. 168 of 2025 dated 08.09.2025.
A separate zoning-plan approval preceded the licence: the Department of Town & Country Planning, Haryana has granted the Zoning Plan vide Memo No. DTCP 11473 dated 29.09.2025. The project was then registered with the regulator: The Project is duly registered with Haryana Real Estate Regulatory Authority vide Regn. No. RC/REP/HARERA/GGM/991/723/2025/94 dated 16.10.2025.
This means the standard consent-award/negotiated-settlement mechanism used in government acquisition — where a Land Acquisition Collector issues an award and farmers can seek enhanced compensation through references or courts — does not apply here. The developer assembled the land parcel itself before seeking statutory approvals.
Villages and district covered
Public filings name only two revenue estates for the licensed parcel, both within Gurugram district:
- Bas Haria — Sector M9/M10/M11, Manesar
- Jhund Sarai (Abad) — Sector M9/M10/M11, Manesar
The project is located across the Revenue Estate of Village Bas Haria & Village Jhund Sarai Abad in Sectors M9, M10 & M11, Manesar, Gurugram. No other district or additional villages are named in the developer's HARERA/DTCP disclosures found for this project. If a wider land bank beyond the current 139.79-acre licence is assembled for the developer's stated future expansion, the villages involved have not been disclosed as of July 2026.
Compensation rates — not applicable/not disclosed
No per-acre or per-square-yard compensation rate for farmers or land-owners has been published for GIC Manesar, and none should be expected in the government-acquisition sense. Because this is a licensed private colony rather than a state land-pooling scheme, the developer's dealings with the original land-owning families are private commercial transactions and are not required to be, and have not been, publicly disclosed with per-unit rates, unlike acquisition-award notifications issued by government authorities elsewhere.
What is publicly filed is the resulting project cost, not a land-cost breakdown: Declared Total Estimated Cost (Within Project Area): ₹39,981.76 Lakhs (as per RERA filing). This RERA-filed figure covers construction and development costs disclosed to the regulator — it is not a land-acquisition compensation budget.
Investment and budget figures reported
The developer has publicised an overall investment figure for the township, separate from the RERA-filed project-cost disclosure above: The project represents an investment of about ₹7,200 crore and is projected to generate a topline of ₹12,000 crore. This ₹7,200 crore is the company's own stated development outlay across the full township vision (residential, commercial and industrial), not a government-sanctioned land-acquisition budget.
Coverage from November 2025 corroborates the same figures: As reported by Business Standard (Nov 5, 2025) and Mint Hindi (Nov 6, 2025), M3M India has committed an investment of ₹7,200 crore in this township, aiming to generate an estimated ₹12,000 crore in topline revenue.
Disputes or farmer negotiations
No land dispute, farmer protest or compensation grievance specific to the GIC Manesar licensed parcel (Bas Haria/Jhund Sarai) has surfaced in current reporting as of July 2026. This is consistent with the project's private-purchase acquisition route, where disputes — if any — would typically be resolved through private sale-deed negotiations rather than public compensation-award proceedings.
For context, IMT Manesar as a broader industrial estate has a history of land-acquisition friction unrelated to GIC: a separate, long-running conflict concerns land conflict in Gurugru, Haryana over farmers' protest and compensation disputes tied to land acquired in 2007 for Industrial Model Township expansion. That case involves different acquisition proceedings and predates GIC's 2025 licence by nearly two decades; it should not be read as describing GIC Manesar's own land history.
Current stage (as of July 2026)
GIC Manesar has moved from licensing to early construction/registration stage but remains far from completion:
- Zoning plan approved: 29 September 2025 (DTCP Memo No. 11473).
- DTCP development licence granted: Licence No. 168 of 2025, dated 8 September 2025.
- HARERA registration: RC/REP/HARERA/GGM/991/723/2025/94, dated 16 October 2025.
- Project timeline filed with HARERA: the project start date is 01 October 2025 and expected completion date is 30 September 2034; the RERA registration is valid from 16-10-2025 to 30-09-2034.
- Phase 1 status: Its first phase, already RERA-approved (HARERA/GGM/991/723/2025/94), covers 50 acres with around 300 plots for data centers, innovation hubs, EV facilities, retail spaces, and residential zones.
- Occupancy readiness: A recent independent assessment notes RERA approval covers the first 50 acres, not the whole 150 to 200 acre vision...Only the 50-acre first phase is RERA-approved so far, and it currently consists of plots rather than finished residential units.
Development phases
Frequently asked questions
Did the Haryana government acquire land for GIC Manesar under the Land Acquisition Act?
No. GIC Manesar is a privately licensed colony. The developer, M3M India Infrastructures (P) Ltd., holds a DTCP development licence (No. 168 of 2025) over land it describes as its own licensed holding — this is a different route from government-led land pooling or acquisition-award schemes.
Which villages does the GIC Manesar land fall in?
The licensed 139.79-acre parcel is described in HARERA/DTCP filings as lying in the revenue estates of Bas Haria and Jhund Sarai (Abad), within Sectors M9, M10 and M11 of Manesar, Gurugram district, Haryana.
What compensation rate did farmers get for this land?
No per-acre or per-unit compensation rate has been publicly disclosed. Because the land was privately purchased/licensed rather than acquired by a government authority under a notified award, there is no public compensation schedule to cite.
How much is M3M investing in GIC Manesar?
The developer has stated an investment of about ₹7,200 crore for the township, with a projected topline (sales) value of about ₹12,000 crore. Separately, the RERA filing declares an estimated project cost of ₹39,981.76 lakh within the registered project area — a different, narrower figure covering the current registered phase.
Are there any land disputes reported for GIC Manesar specifically?
As of July 2026, no dispute or farmer grievance tied specifically to the Bas Haria/Jhund Sarai parcel used for GIC has been found in current reporting. Older land-acquisition conflicts exist in the wider IMT Manesar area from a 2007 acquisition, but these are unrelated to GIC's 2025 DTCP licence.
What stage is the project at right now?
The DTCP licence was granted in September 2025, the zoning plan approved the same month, and HARERA registration followed on 16 October 2025. Only the first 50-acre phase is RERA-approved and it currently comprises plots, not built or delivered units; the filed project completion date is 30 September 2034.
Sources
- GIC Township — M3M India (official disclosure page)
- Gurgaon International City | Premium Residential Project — M3M India
- Gurgaon International City Manesar Detailed Breakdown
- M3M Launches ₹7200 Cr GIC Township in 150-Acre Manesar
- M3M Gurgaon International City – Township in Sector M9–M11 Manesar (RERA/DTCP disclosures)
- HARERA Public Notice — Zoning Plan, Gurgaon International City
- HARERA Public Notice — Joint Development & Marketing Rights
- Land acquisition, farmers' protest, and compensation disputes in Industrial Model Township project in Manesar, Haryana — Land Conflict Watch
- M3M's Rs 7200 Crore Gurgaon International City
- M3M GIC Global International City Manesar Gurgaon