HARERA Registers M3M Gurgaon International City (GIC) Manesar Phase 1 — RERA No. HARERA/GGM/991/723/2025/94

On 16 October 2025, the Haryana Real Estate Regulatory Authority (HARERA), Gurugram, registered the first phase of M3M India Infrastructures' Gurgaon International City (GIC) township in Manesar under RERA No. RC/REP/HARERA/GGM/991/723/2025/94. The registration is the statutory clearance that allows the developer to legally market and sell plots/units in this phase.

Gurgaon International City (GIC) Manesar — HARERA Registers M3M Gurgaon International City (GIC) Manesar Phase 1 — RERA No. HARERA/GGM/991/723/2025/94
RERA registration numberRC/REP/HARERA/GGM/991/723/2025/94
Registration date16 October 2025
Registering authorityHARERA, Gurugram
Developer / PromoterM3M India Infrastructures (P) Ltd.
Licensed land area (this registration)56.57252 hectares / 139.79375 acres
Underlying DTCP licenceLicence No. 168 of 2025, dated 08.09.2025
LocationSectors M9, M10 & M11, Manesar (villages Bas Haria & Jhund Sarai Abad), Gurugram, Haryana
Project classificationIndustrial plotted colony with residential & commercial pockets
Phase 1 market-facing scope~50 acres, ~300 plots
Wider township vision (unregistered beyond Phase 1)150 acres, expandable to 200 acres

What was decided

HARERA Gurugram formally registered a real estate project named "Gurgaon International City", promoted by M3M India Infrastructures (P) Ltd., under the Real Estate (Regulation and Development) Act. The project is duly registered with the Haryana Real Estate Regulatory Authority vide registration number RC/REP/HARERA/GGM/991/723/2025/94, dated 16.10.2025. This registration is the operative regulatory record for the project as filed by the promoter; buyers are directed to verify it independently, since all details of the said registered project are available on www.haryanarera.gov.in and may be verified before by the viewer/recipients at their own independent discretion.

Legal basis: DTCP licence behind the registration

The RERA registration sits on top of a Directorate of Town and Country Planning (DTCP), Haryana, licence issued a few weeks earlier. "Gurgaon International City" is an industrial plotted colony, developed and promoted by M/s M3M India Infrastructure Private Limited, on licensed land admeasuring 56.57252 hectares (139.79375 acres) situated in the revenue estate of villages Bas Haria and Jhund Sarai, Abad, Sector-M9, M10 & M11, Manesar, Gurugram, Haryana, with DTCP approval granted vide Memo No. LC-5390/JE(SK)2025/35500 dated 09.09.2025 and Licence No. 168 of 2025 dated 08.09.2025.

So the sequence of approvals was: DTCP land-use licence (8–9 September 2025) → HARERA project registration (16 October 2025). The RERA number covers the licensed 139.79-acre parcel; it is on this parcel that the developer is bringing an initial tranche of plots to market.

Operative details: area, boundaries and land use

The registered project area is 56.57252 hectares (139.79375 acres), located in the revenue estates of Bas Haria and Jhund Sarai Abad, across Sectors M9, M10 and M11, Manesar, Gurugram district, Haryana. It is described in official project material as an industrial plotted colony rather than a purely residential scheme, meaning the land use mix leans toward plotted industrial/commercial development with residential pockets folded in.

Third-party project trackers, citing the HARERA filing, list the township as conceptualized as an Industrial Plotted Colony with integrated residential and commercial pockets, offering 286 industrial plots, dedicated residential land parcels (including group housing and affordable housing plots), and commercial pockets. These figures are reported by aggregator sites rather than confirmed directly from the HARERA portal in this research, so they should be treated as indicative pending independent verification on haryanarera.gov.in.

Phase 1: what is actually being sold now

Multiple project listings and the developer's own township announcement describe the RERA-registered stage as "Phase 1" of a much larger master plan. As reported by Business Standard: the first phase of the project, spread across 50 acres and already RERA-approved, will include 300 plots. Property-marketing pages elaborate that the first phase, already RERA-approved (HARERA/GGM/991/723/2025/94), covers 50 acres with around 300 plots for data centers, innovation hubs, EV facilities, retail spaces, and residential zones.

In other words, the 139.79-acre licensed/registered parcel is not being sold in one go — the developer has opened roughly 50 acres and ~300 plots to the market as the initial saleable tranche, with the remainder of the licensed land and the wider township vision to follow in later stages.

The wider township context

GIC is marketed as part of a considerably larger ambition than the registered 139.79-acre parcel. Per Business Standard's report on the launch: M3M India will invest Rs 7,200 crore to develop a 150-acre integrated township in Gurugram... While the project currently spans 150 acres, planned expansions can push the total area to 200 acres, according to the developer. The same report notes the company has launched its Gurgaon International City (GIC) township project, which is expected to generate a topline of around ₹12,000 crore.

This means the figures commonly quoted for GIC — 150 acres, ₹7,200 crore investment, ₹12,000 crore topline — describe the developer's overall township ambition, distinct from the 139.79-acre area actually covered by RERA No. 94/2025 and DTCP Licence No. 168/2025 as of this registration. Any land beyond the licensed 139.79 acres would require its own DTCP licensing and RERA registration before it can be legally sold.

Practical effect of the registration

What this registration is not

GIC Manesar is a private developer township, not a government-notified planned city or investment region — the "development authority" here is the promoter itself (M3M India Infrastructures (P) Ltd.), operating under DTCP licensing and HARERA oversight rather than any statutory new-town authority. Readers should not conflate this RERA registration with a government master-plan notification: it authorises the sale of specific plots within a privately licensed colony, nothing more and nothing less.

As of this record, only the 139.79-acre licensed parcel (with a ~50-acre/~300-plot first saleable tranche) carries a confirmed RERA number. The broader 150–200 acre vision, high-rise residential towers, and additional commercial/retail components described in marketing material remain future phases pending their own approvals.

Development phases

Phase 1 (RERA-registered)Registered 16 Oct 2025~50 acres, ~300 plots (industrial/innovation, EV,retail, residential) within the 139.79-acre licensedparcelLicensed parcel (full RERA/DTCP scope)DTCP licence 08–09 Sept 2025; RERA 16 Oct 202556.57 hectares / 139.79 acres, Sectors M9, M10, M11,ManesarWider township vision (not yet separatelyregistered)Announced Nov 2025150 acres, expandable to 200 acres; ₹7,200 croreinvestment target

Frequently asked questions

What exactly did HARERA approve on 16 October 2025?

HARERA Gurugram registered the project "Gurgaon International City," promoted by M3M India Infrastructures (P) Ltd., under RERA No. RC/REP/HARERA/GGM/991/723/2025/94, dated 16.10.2025 — the registration required before the developer can legally market and sell units/plots.

How much land does this RERA registration cover?

The registered/licensed land measures 56.57252 hectares (139.79375 acres) in Sectors M9, M10 and M11, Manesar, on the revenue estate of villages Bas Haria and Jhund Sarai Abad, per the developer's own legal disclosure.

Is the entire 150-acre GIC township covered by this single RERA number?

No. The 150-acre (expandable to 200-acre) township is the developer's overall stated ambition. The RERA number confirmed here covers the 139.79-acre licensed parcel, and market listings describe an initial ~50-acre, ~300-plot 'Phase 1' as the tranche actually being sold under this registration.

What DTCP approval sits behind this RERA registration?

DTCP Licence No. 168 of 2025, dated 08.09.2025 (approval memo dated 09.09.2025), which licensed the land for development as an industrial plotted colony ahead of the HARERA registration.

Is GIC Manesar a government-notified new town?

No. It is a private developer township — the 'development authority' is the promoter, M3M India Infrastructures (P) Ltd., operating under HARERA and DTCP oversight rather than a statutory new-town or investment-region authority.

What does this registration allow M3M to do that it couldn't do before?

It allows the promoter to legally advertise, book and sell plots/units in the registered project, subject to RERA disclosure and escrow obligations, and gives buyers a regulatory reference and grievance forum via HARERA.

Sources