Connectivity Status
Hisar Industrial Smart City: Connectivity Status as of November 2026
Hisar Industrial Smart City, also searched as Hisar IMC, is a 2,988-acre industrial cluster planned beside Maharaja Agrasen Airport in Hisar district, Haryana, developed by NICDC under the Amritsar–Kolkata Industrial Corridor. Air access and direct national highway access are in place or under way, while the expressway, rail freight and internal road network were at tender or planning stage as of November 2026.

| Cluster land | 2,988 acres of government land, transferred to NICDC; stamp duty waiver approved on 18 May 2026 |
|---|---|
| Road access | Independent, direct access from NH-9 and NH-52 (operational) |
| Nearest airport | Maharaja Agrasen Airport, planned adjacent to the cluster. Domestic terminal and expanded runway completed by August 2025; international terminal under construction (35% complete as of April 2026) |
| Rail freight | Hisar lies between the Rewari (Western DFC) and Ambala (Eastern DFC) stations. Planned phases: 2027, 2032 and 2037 (proposed) |
| Key expressway | Hisar–Rewari Expressway, 160 km four-lane greenfield road; DPR completed in 2024; pre-construction as of the latest reports (early 2026) |
| Trunk infrastructure tender | ₹707 crore EPC tender (excluding O&M and GST) floated June 2026; bids under evaluation as of August 2026 |
| Power at full build-out | 232 MW, with a 220-kV substation planned within the cluster |
Air connectivity at Maharaja Agrasen Airport
The cluster is planned immediately next to Maharaja Agrasen Airport, which sits about 5 km north-east of Hisar city centre on NH-9. Status as of mid-2026:
- Operational: The domestic terminal (Phase I) and expanded runway (Phase II) were completed by August 2025. Alliance Air runs direct flights from Hisar to several cities.
- Under construction: The Phase III-A international terminal has a target construction completion date of 17 April 2027. It was 35% complete as of April 2026.
- Existing facilities: A 3-hangar MRO terminal, a domestic and regional terminal with 7 bays for UDAN flights, and a 2-bay cargo terminal with cold storage and an integrated logistics hub.
The wider airport upgrade covers 7,200 acres, of which 4,212 acres is for the airport and 2,988 acres for the cluster. It is being built in three phases at a cost of ₹5,200 crore, with the aim of an international airport by 2030. The plan includes an MRO hub, an aerospace university, an aerospace and defence manufacturing zone, a logistics hub and food parks.
Roads and expressways
The cluster has independent and direct access from NH-9 and NH-52, so this part of the connectivity is already in place.
- NH-9, Delhi to Rohtak (operational): Upgraded to six lanes, with a 30 km Rohtak City Bypass so that traffic between New Delhi and Hisar does not enter Rohtak city.
- NH-9, Rohtak to Hisar and towards Punjab (under construction): Being widened to a four-lane highway.
- Hisar–Rewari Expressway (proposed, pre-construction): A 160 km four-lane, access-controlled greenfield road linking Hisar with Rewari in southern Haryana. It is expected to cut Hisar–Rewari travel from 4–5 hours to about 2 hours. The DPR was completed in 2024. NHAI was preparing tenders, with construction expected to begin in 2026 and take 3–4 years. The Hisar end includes a 4-lane greenfield southern bypass for Hisar city.
The expressway depends on NHAI's tendering and award. Its opening date should be checked against the latest NHAI announcements.
Rail links and dedicated freight corridors
Hisar sits between the Rewari station on the Western Dedicated Freight Corridor and the Ambala station on the Eastern Dedicated Freight Corridor. The plan includes feeder rail links to both. These are planned, not built.
- Phase 1, by 2027 (proposed): Multi-modal connectivity through Hisar City Junction.
- By 2032 (proposed): A rail freight terminal at the airport, connected to the Eastern Dedicated Freight Corridor.
- By 2037 (proposed): The final phase of the rail plan.
Separately, a Detailed Project Report has been submitted by HRIDC for dedicated rail connectivity to the Integrated Aviation Hub at Hisar Airport and for raising rail speeds to 130–160 kmph. The state government is examining it. It has not yet moved to construction.
Internal roads, utilities and trunk infrastructure
The main internal work is a ₹707 crore EPC tender, floated in June 2026 and covering design, construction, testing, commissioning and operation and maintenance of the cluster's trunk infrastructure. The scope covers roads, water supply, sewerage and stormwater drainage, plus a 220-kV substation with five 33-kV substations. The build period is 30 months, followed by 5 years of maintenance.
- As of August 2026, bids had been received and were under evaluation. The contract has not yet been awarded.
- Work to build a boundary wall around the Phase I land was reported under way in August 2026.
- Water supply for the airport is part of the infrastructure plan.
- Power requirement at full capacity is 232 MW.
- A consultant has been appointed for the detailed master plan and preliminary engineering. The state set 31 August 2026 as the deadline for master plan notification.
The state government's Civil Aviation Department transferred the 2,988 acres to NICDC. In May 2026 the Haryana Cabinet approved a waiver of about ₹132.41 crore in stamp duty and registration charges on the transfer. In September 2026 the Chief Minister directed officials to speed up construction through the State Pragati Portal review.
What is complete and what is still ahead
As of 11 November 2026, the position is as follows.
- Completed: Airport domestic terminal and runway expansion (by August 2025); land transfer and stamp duty waiver (May 2026); EPC tender floated (June 2026).
- Under way: Airport international terminal (target 17 April 2027); boundary wall work; EPC bid evaluation.
- Still ahead: Rail freight Phase 1 (2027); international airport (2030); airport rail freight terminal (2032); final rail phase (2037); Hisar–Rewari Expressway construction; the cluster's trunk roads and utilities, 30 months after contract award.
Development phases
Frequently asked questions
Is the Hisar Industrial Smart City next to an airport?
Yes, the cluster is planned immediately adjacent to Maharaja Agrasen Airport in Hisar.
Are flights running from Hisar Airport now?
Yes, the domestic terminal and expanded runway were completed by August 2025, and Alliance Air operates direct flights to several cities.
When will the Hisar airport international terminal open?
The international terminal has a target construction completion date of 17 April 2027, and was 35% complete as of April 2026.
When will the Hisar–Rewari Expressway be built?
The 160 km four-lane expressway is planned, with its DPR completed in 2024 and construction expected to begin in 2026 and take 3–4 years, according to the latest reports.
Does the Hisar cluster have direct highway access?
Yes, the 2,988-acre site has independent and direct access from NH-9 and NH-52.
When will rail freight reach the Hisar cluster?
Rail freight is planned in phases: a link through Hisar City Junction by 2027, an airport freight terminal by 2032, and a final phase by 2037.
Sources
- IMC Hisar Haryana – NICDC Official
- Hisar Integrated Manufacturing Cluster (IMC), Haryana – NICDC
- Activities & Achievements – Civil Aviation Department, Government of Haryana
- National Industrial Corridor Development Corporation (NICDC) will support the Government of Haryana – PIB Press Release
- Major push for Hisar IMC: Rs 707-crore EPC tender issued for Trunk Infrastructure – The Tribune
- IMC-Hisar yet to move beyond planning – The Tribune
- What is the IMC project and when is it likely to take shape – The Tribune
- Transportation – Municipal Corporation Rohtak