INFRASTRUCTURE REVIEW
CM Saini Reviews Hisar IMC Infrastructure Progress at State Pragati Portal Meeting
Haryana Chief Minister Nayab Singh Saini on Wednesday 12 August directed officers while chairing the fourth meeting to review the State Pragati Portal, and briefed attendees on extensive infrastructure development underway at the Integrated Manufacturing Cluster (IMC) in Hisar. The cluster will have facilities including water supply for the airport and a 220-kV power substation, with work underway to construct the boundary wall around 1,578 acres of land in the first phase of the airport project.

| Total IMC land area | 2,988 acres |
|---|---|
| Phase I area | 1,605 acres |
| Project cost | Rs 4,680 crore |
| Investment potential | Rs 32,417 crore |
| Expected employment | 1.25 lakh jobs |
| EPC tender for Phase-I infrastructure | Rs 707 crore (bids received and under evaluation) |
| Power requirement at full capacity | 232 MW of electricity |
| Master plan notification deadline | 31 August 2026 |
What the CM Announced
During the fourth State Pragati Portal review meeting, CM Saini said extensive infrastructure is being developed at the Integrated Manufacturing Cluster (IMC) in Hisar, which will house a Skill Development Centre, Convention Centre and Exhibition Hall, Logistics Park and Multi-Speciality Hospital, besides facilities for defence and aerospace, agro-food processing, garment and textile industries.
He informed that facilities, including water supply for the airport and a 220-kV power substation, are being developed at the IMC, and that work is also underway to construct the boundary wall around 1,578 acres of land in the first phase of the airport project.
Development Authority and Governance
The IMC will be developed jointly by the Haryana government and the National Industrial Corridor Development Corporation (NICDC), as announced in a statement following a meeting chaired by Chief Minister Nayab Singh Saini. The State Support Agreement (SSA) and Shareholder Agreement (SHA) pave the way for the development of the Integrated Manufacturing Cluster (IMC) at Hisar, through which NICDC will assist Haryana in shaping one of its most ambitious industrial hubs.
The State Pragati Portal is a web-based monitoring dashboard launched in January 2022 to track infrastructure projects costing over Rs 75 crore.
Project Scale and Investment
Spread across 2,988 acres, the Hisar cluster is expected to become a cornerstone of Haryana's economic future. The project carries an estimated investment potential of Rs 32,417 crore, with a project cost of Rs 4,680 crore. Once operational, it is projected to create 1.25 lakh jobs and attract a mix of domestic and global investors, reinforcing the Make in India mission.
Infrastructure Procurement and Timeline
Bids have been received for the EPC project worth approximately Rs 707 crore for the Phase-I infrastructure, and the bids are currently being evaluated. The EPC agency will be appointed shortly. The successful bidder will have to complete the construction work within 30 months and maintain the infrastructure for five years.
The process for notification of the master plan has also been initiated, with a target to notify it by August 31, 2026. Construction work for canal diversion in Phase-I has already been awarded.
Utilities and Infrastructure Details
The trunk infrastructure will include internal roads, water supply, sewerage, stormwater drainage, power distribution and other essential utilities required for industrial development. When completed, the IMC is expected to require around 232 MW of electricity. To meet this demand, the Haryana Vidyut Prasaran Nigam (HVPN) will establish a 220-kV grid substation for the project, with power distribution within different sectors of the IMC handled by the Dakshin Haryana Bijli Vitran Nigam (DHBVN).
Strategic Location and Corridor Status
Hisar Integrated Manufacturing Cluster (IMC), located in Haryana is one of the most ambitious industrial infrastructure projects under the Amritsar–Kolkata Industrial Corridor (AKIC) in India, proposed to be a large size, multi-sector industrial platform where the idea is to make Hisar a next generation industrial hub for MSMEs, exports, logistics and advanced manufacturing. Planned over approximately 2,988 acres, including 1,605 acres in Phase I, the project is strategically located along NH-52 and NH-09 and lies close to the upcoming Hisar Aviation Hub.
Development phases
Land use
Frequently asked questions
What is the Hisar Integrated Manufacturing Cluster?
It is proposed to be a large size, multi-sector industrial platform where the idea is to make Hisar a next generation industrial hub for MSMEs, exports, logistics and advanced manufacturing.
When was the Pragati Portal review meeting held and what was reviewed?
On 12 August, Haryana Chief Minister Nayab Singh Saini directed officers while chairing the fourth meeting to review the State Pragati Portal. The meeting reviewed extensive infrastructure being developed at the Hisar IMC including skill centres, convention facilities, logistics parks, hospitals, and advanced manufacturing hubs.
How much has been invested and what is the expected return?
The project carries an estimated investment potential of Rs 32,417 crore, with a project cost of Rs 4,680 crore. Once operational, it is projected to create 1.25 lakh jobs and attract a mix of domestic and global investors.
What is the status of Phase 1 infrastructure development?
Bids worth approximately Rs 707 crore for Phase-I infrastructure have been received and are being evaluated. The EPC agency will be appointed shortly. The master plan notification is targeted by August 31, 2026.
What sectors will the IMC support?
The IMC will house facilities for defence and aerospace, agro-food processing, garment and textile industries and other industrial units, along with a Skill Development Centre, Convention Centre and Exhibition Hall, Logistics Park and Multi-Speciality Hospital.
Who is developing the IMC?
The IMC will be developed jointly by the Haryana government and the National Industrial Corridor Development Corporation (NICDC).
Sources
- CM Saini sets three-month target for electricity, water supply at Gurugram Global City
- Complete basic infrastructure in Global City within three months: Haryana CM
- Major push for Hisar IMC: Rs 707-crore EPC tender issued for Trunk Infrastructure
- Hisar Integrated Manufacturing Cluster Gains Momentum As Haryana Signs Key Agreements Under AKIC
- Hisar IMC Industrial Cluster: ₹4,680 Cr Manufacturing Hub Hisar Airport
- National Industrial Corridor Development Corporation (NICDC) will support Haryana in developing IMC at Hisar
- Haryana Waives Rs 132 Crore Stamp Duty For Hisar Airport Industrial Corridor Project
- Hisar Integrated Manufacturing Cluster (IMC), Haryana – NICDC Official