New Cities India

Land Transfer Record

Hisar Industrial Smart City: 990 Acres Transferred to NICDC for Phase I

On 16 November 2026, the Hisar district administration completed the transfer of 990 acres of land near Maharaja Agrasen International Airport to NICDC Limited for Phase I of the Hisar Integrated Manufacturing Cluster, also called Hisar Industrial Smart City. The cluster is developed by NICDC with the Government of Haryana, and its status as of November 2026 is Upcoming.

Hisar Industrial Smart City — Hisar Industrial Smart City: 990 Acres Transferred to NICDC for Phase I
Decision date16 November 2026
Decided byHisar district administration, through the Land Acquisition Department
Land transferred990 acres near Maharaja Agrasen International Airport, Hisar, Haryana
Receiving bodyNICDC Limited, for the first phase of the cluster
Original landownerHaryana Civil Aviation Department
Phase I land earmarked1,605 acres, of which 990 acres formally transferred so far
Whole cluster2,988 acres; project cost about Rs 4,680 crore (as of November 2026)
StatusUpcoming, as of November 2026

What was decided

The Hisar district administration, acting through the Land Acquisition Department, completed the registration of 990 acres in the name of NICDC Limited. The land is for the first phase of the Integrated Manufacturing Cluster, the industrial zone that is also known as Hisar Industrial Smart City. Officials described it as the first formal transfer of land ownership among the proposed IMC sites in the country.

The decision moves ownership of the land from a state department to the national agency that is building the cluster. It is a land step, not a plot launch.

Operative details of the transfer

Practical effect for buyers and investors

With the 990 acres registered to NICDC, the agency now holds the land it needs to carry out development work on that part of Phase I. The decision covers land ownership only. It does not set plot prices, allotment terms, booking schedules or a completion date for the cluster.

Anyone following the project should watch three things next: the registration of the remaining Phase I land, the award of the Rs 707 crore infrastructure contract, and any later announcement on plot allotment.

How this decision fits the project timeline

  1. 20 August 2025: NICDIT, the Government of Haryana and the Haryana Airports Development Corporation signed a State Support Agreement and a Shareholder Agreement for the 2,988-acre cluster.
  2. 15 April 2026: Chief Secretary Anurag Rastogi chaired a high-level review and directed departments to speed up implementation, as the project had remained largely at the planning stage.
  3. 18 May 2026: the Haryana Cabinet, chaired by Chief Minister Nayab Singh Saini, approved a waiver of about Rs 132.41 crore in stamp duty and registration charges on the transfer of land from the Civil Aviation Department to NICDC.
  4. June 2026: an EPC tender worth Rs 707 crore, excluding O&M and GST, was floated for trunk infrastructure covering internal roads, water supply, sewerage and stormwater drainage, with 30 months of construction and five years of maintenance.
  5. 17 August 2026: the Chief Minister told the Apex Monitoring Authority of NICDIT that bids for the EPC project had been received and were being evaluated.
  6. 16 November 2026: 990 acres were registered in NICDC's name for Phase I.

About the Hisar Industrial Smart City

The Hisar Integrated Manufacturing Cluster is planned over 2,988 acres of government-owned land in Hisar district, Haryana. It is one of 12 industrial smart cities under the Amritsar-Kolkata Industrial Corridor programme. The project cost is about Rs 4,680 crore, with an estimated investment potential of Rs 32,417 crore and employment potential of about 1.25 lakh jobs on full build-out, as of September 2026.

The cluster is planned to house manufacturing, logistics and industrial units. Full power demand at build-out is about 232 MW, and the plan includes a 220-kV power substation and water supply for the airport.

The developer and the agency behind the cluster

The National Industrial Corridor Development Corporation (NICDC) is responsible for developing the industrial cluster, working with the Government of Haryana. The project is run through a joint special purpose vehicle, NICDC Haryana Integrated Manufacturing Cluster Hisar Project Limited. The state side includes the Civil Aviation Department and the Haryana Airports Development Corporation.

The 990-acre registration is the first formal land transfer for the cluster, and it follows the agreements, approvals and tender steps listed above.

Hisar and the airport corridor as context

Hisar is a district town in Haryana, and the cluster sits beside Maharaja Agrasen International Airport. Access is planned directly from National Highways 9 and 52. Because the land is airport-side and near the main highways, the site is aimed at manufacturing and logistics users who need road and air links. Land prices and rental trends for the wider Hisar area depend on how fast the cluster moves from land transfer to construction and allotment, and those stages are still ahead as of November 2026.

Development phases

Frequently asked questions

What land did the Hisar district administration transfer to NICDC?

The Hisar district administration transferred 990 acres near Maharaja Agrasen International Airport, registered in the name of NICDC Limited for the first phase of the cluster.

How much of Phase I land has been transferred so far?

990 of the 1,605 acres earmarked for Phase I have been formally transferred, and the rest is to follow once the ongoing process is complete.

Who owned the land before the transfer?

The land belonged to the Haryana Civil Aviation Department before it was registered to NICDC.

Does this decision mean plots are on sale in Hisar Industrial Smart City?

No, this decision covers only the transfer of land ownership, and it does not set plot prices, allotment terms or booking schedules.

How large is the whole cluster and what will it house?

The full Hisar Integrated Manufacturing Cluster is planned over 2,988 acres and will house manufacturing, logistics and industrial units, with a project cost of about Rs 4,680 crore as of September 2026.

How much did the Haryana Government pay toward the project?

The Haryana Government released about Rs 624.49 crore to the Civil Aviation Department as its share in the project.

Sources