Hisar IMC Floats ₹707-Crore Tender for Trunk Infrastructure—First Across 12 AKIC Cluster Projects

The Haryana project of the National Industrial Corridor Development Corporation (NICDC) has taken its first step toward implementation as a tender worth Rs 707 crore has been floated for developing infrastructure in about 2,988 acres near the Maharaja Agrasen airport in Hisar town. This is one of the 12 industrial smart cities projects under the ambitious AKIC programme across the country.

Hisar Industrial Smart City — Hisar IMC Floats ₹707-Crore Tender for Trunk Infrastructure—First Across 12 AKIC Cluster Projects
Tender amount (EPC basis)₹707 crore (excluding O&M and GST)
Site area covered2,988 acres
Implementation timeline30 months construction + 5 years maintenance
Total project investment potential₹32,417 crore
Expected job creation1.25 lakh
Project cost (full cluster)₹4,680 crore
Land ownership status2,988 acres of encumbrance-free government land already transferred
Status among 12 AKIC clustersFirst to reach EPC tender and implementation stage

What Happened: The Tender Launch

The NICDC Haryana Integrated Manufacturing Cluster Hisar Project Limited (NHIMCHPL) has floated this tender for the development of trunk infrastructure at the proposed IMC in Hisar under the Amritsar-Kolkata Industrial Corridor (AKIC). The project will be executed on an Engineering, Procurement and Construction (EPC) basis and cover the design, construction, testing, commissioning and operation and maintenance of the cluster's trunk infrastructure. The trunk infrastructure will include internal roads, water supply, sewerage, stormwater drainage among others.

The tender has been issued through the e-tendering process by NHIMCHPL, a special purpose vehicle jointly promoted by the Centre and the Haryana Government for developing trunk infrastructure at the Cluster.

Why Hisar Is First: Land Advantage

IMC Hisar began with a significant advantage as it has nearly 2988 acres of encumbrance-free government land already transferred by the state government that has given the initial advantage to this project. In contrast, land acquisition has been one of the biggest bottlenecks in industrial corridor development nationwide, delaying comparable projects in other states.

What It Changes: From Planning to Execution

Prior to this tender, the Hisar IMC had remained at the planning and approvals stage despite being designated for development under AKIC. Procedural progress had remained slow, with the appointment of consultants still under process and the Engineering, Procurement and Construction (EPC) tender—which marks the beginning of physical infrastructure work—yet to be floated (as of June 2026).

The tender marks a concrete transition from design to physical implementation. The successful bidder will have to complete the construction work within 30 months and maintain the infrastructure for five years. If met, trunk infrastructure would be operationalised by end of 2028.

The Project's Scale and Strategic Rationale

IMC Hisar, spread across 2,988 acres, is being developed under the Amritsar-Kolkata Industrial Corridor near the newly inaugurated Maharaja Agrasen International Airport, Hisar, Haryana. With an investment potential of ₹32,417 crore and a project cost of ₹4,680 crore, it is expected to generate 1.25 lakh jobs.

Strategically located between the EDFC and WDFC, it offers excellent connectivity via NH-52, NH-09, rail links, and proximity to major logistics hubs. The cluster will serve as a key center for aircraft maintenance, repair, and overhaul (MRO) activities, along with food processing, ready-made garments, and engineering industries.

What Comes Next

Following tender award, design and construction of roads, utilities, drainage and water-supply systems across the 2,988-acre site will commence. The IMC will benefit from multi-modal connectivity with air, road and rail initially through the Hisar city Junction in the first phase of its development (2027) and the rail terminal for freight in the airport by 2032 and final phase (2037).

The National Industrial Corridor Development Corporation (NICDC) will support the Government of Haryana in developing the Integrated Manufacturing Cluster (IMC) at Hisar, following this infrastructure phase with investor allotment and sectoral zoning.

Development phases

Trunk InfrastructureDevelopment2026–2028 (30 months from award)2,988 acres; roads, water, sewerage,power distribution, drainagePhase 1 OperationalConnectivity2027Air, road and rail access via Hisarcity JunctionFreight Rail Terminal2032Dedicated freight rail connection toEastern Dedicated Freight CorridorviaFinal Build-Out2037Full cluster operational with 1.25lakh jobs

Frequently asked questions

Why is Hisar IMC the first among 12 AKIC clusters to float an EPC tender?

IMC Hisar began with a significant advantage as it has nearly 2988 acres of encumbrance-free government land already transferred by the state government, removing the primary procedural bottleneck that has delayed other projects.

What is the difference between the ₹707 crore tender and the ₹4,680 crore total project cost?

The ₹707 crore funds trunk (common) infrastructure—roads, water, sewerage, utilities. The ₹4,680 crore total includes sectoral infrastructure, utilities, and operational facilities for industrial units and ancillary services.

What infrastructure is included in the trunk system?

The trunk infrastructure will include internal roads, water supply, sewerage, stormwater drainage among others.

When will the cluster be ready for industrial plot allotment?

The successful bidder will have to complete the construction work within 30 months and maintain the infrastructure for five years, positioning the cluster for investor allotment by late 2028, with phased operational activation through 2032 and beyond.

Who decided to award this tender and when was it announced?

The tender has been issued through the e-tendering process by NHIMCHPL, a special purpose vehicle jointly promoted by the Centre and the Haryana Government. The tender was publicly announced around late June 2026.

How many people is the Hisar IMC expected to employ?

It is expected to generate 1.25 lakh jobs.

What sectors will operate in Hisar IMC?

IMC Hisar's master plan has demarcated the cluster into separate industrial sectors such as metal fabrication and engineering, textiles and apparel, food and agro-processing, defence supply chain, logistics and warehousing and light manufacturing.