Connectivity and Access
Prayagraj Industrial Smart City: Roads, Rail and Air Links
Prayagraj Industrial Smart City is the Integrated Manufacturing Cluster (IMC) Prayagraj at Saraswati Hi-Tech City in Karchana block, about 25 km south of Prayagraj city in Uttar Pradesh, built by NICDC and UPSIDA under the Amritsar-Kolkata Industrial Corridor. Its road, rail and air links are a mix of operational routes, works under construction and proposals, as of November 2026.

| Site | Saraswati Hi-Tech City, Karchana block, about 25 km south of Prayagraj city |
|---|---|
| Nearest airport | Prayagraj Airport (IXD), about 24 km; operational, domestic flights only (as of 2026) |
| Nearest rail freight link | New Karchana EDFC Station, about 7 km; Eastern Dedicated Freight Corridor operational through Prayagraj |
| Highways named by NICDC | NH-35 and NH-30, both operational |
| Expressway | Ganga Expressway, 594 km, Meerut to Prayagraj; Phase 1 inaugurated 29 April 2026 |
| Prayagraj Ring Road (NHAI) | 71.5 km in two phases; Rs 7,048 crore; Phase 1 at land acquisition stage, Phase 2 DPR cleared (as of February 2026) |
| Prayagraj Metro | Proposed only; revised DPR issued April 2026; not under construction (as of November 2026) |
| Site works (as of May 2026) | EPC contractor RCC Developers Pvt Ltd appointed; site survey, clearing and design under way |
Connectivity status at a glance
The table below lists each link with its status and the date that status was reported. Dates matter because several projects have moved stage in 2026.
| Mode | Link | Status |
|---|---|---|
| Air | Prayagraj Airport, about 24 km | Operational, domestic only (2026) |
| Freight rail | New Karchana EDFC Station, about 7 km | Operational (EDFC through Prayagraj) |
| Freight corridor | Eastern Dedicated Freight Corridor | Operational through Prayagraj |
| Highway | NH-35 and NH-30 | Operational; named by NICDC as direct links |
| Highway | NH-19 Prayagraj to Handia-Rajatalab, 73 km six-lane | Operational (recently upgraded) |
| Expressway | Ganga Expressway Phase 1, Meerut to Prayagraj | Operational; inaugurated 29 April 2026 |
| Expressway | Spur-2, Prayagraj to Ballia | Pre-construction; preparatory work ongoing (as of August 2025) |
| Ring road | Prayagraj Ring Road Phase 1, 29.8 km | Land acquisition under way (as of February 2026) |
| Ring road | Prayagraj Ring Road Phase 2, 41.662 km | DPR cleared; construction not started (as of February 2026) |
| Rail hub | Prayagraj Junction redevelopment, second phase | Under redevelopment; target December 2026 (as of April 2026) |
| Metro | Prayagraj Metro | Proposed; revised DPR April 2026 |
| Metro | Prayagraj Metrolite | Proposed |
| Freight junctions | Manauri and Karchhana, near Prayagraj | Proposed |
Prayagraj Airport: the nearest air link
Prayagraj Airport (IATA: IXD), also searched as Allahabad Airport, is about 24 km from the site according to NICDC's project page. It covers roughly 800 acres and is run jointly by the Indian Air Force and the Airports Authority of India.
- One runway (12/30), 2,560 metres long, ILS CAT-I compliant for night, bad weather and fog.
- Passenger traffic passed 1 million for the first time in FY2024-25, placing it among India's top 20 busiest airports that year.
- In 2025 it ran around 30 flights a week to six destinations in India.
- It is part of the UDAN regional connectivity scheme.
- Ahead of Magh Mela 2026, the airport announced plans to expand services for expected pilgrim and tourist traffic.
- International routes, including talk of Gulf and Southeast Asia services, remain under discussion. No date has been fixed.
Expressways and national highways
The Ganga Expressway is the newest major link in the region. It is a 594 km, six-lane, access-controlled greenfield expressway from Meerut to Prayagraj, inaugurated by Prime Minister Narendra Modi on 29 April 2026. The trip between the two cities falls from 12-13 hours to about 6-7 hours.
The eastward extension is not yet built. Spur-2, from Prayagraj to Ballia, is in pre-construction. UPEIDA completed surveys in 2024, and preparatory work was ongoing as of August 2025.
NH-19 between Prayagraj, Handia and Rajatalab is a 73 km six-lane section and the main eastern gateway to Varanasi. It is operational after recent upgrades.
NICDC's project page names NH-35 and NH-30 as the site's direct highway links to Saraswati Hi-Tech City. Both are operational. NICDC's description also lists waterways among the site's connections.
Eastern Dedicated Freight Corridor and the New Karchana link
The Eastern Dedicated Freight Corridor runs from Ludhiana in Punjab to Dankuni near Kolkata, through Meerut, Kanpur, Prayagraj and Chandauli. The Prayagraj stretch is operational.
The New Karchana EDFC Station is about 7 km from the site, according to NICDC. Proposed junctions at Manauri and Karchhana near Prayagraj are still at the proposal stage.
The corridor's Operation Control Centre at Prayagraj, built by Alstom, monitors all trains and power supply on the line. It sits on a 4.2-acre facility and is staffed by 150 people.
Prayagraj Junction: the passenger rail hub
Prayagraj Junction (PRYJ) is under redevelopment. By 2023, remodelling had expanded the station to 12 platforms with two mega concourses. A new electronic interlocking system was commissioned in November 2024.
The second phase began in May 2024 with a budget of Rs 960 crore. It targets full modernisation, including airport-like amenities, by December 2026. City-side construction was scheduled to start on 15 April 2026, with associated parking restrictions. Buyers should check the latest status of the December 2026 target before relying on it.
Prayagraj Ring Road and the internal road network
The Prayagraj Ring Road is a 71.5 km NHAI project costing Rs 7,048 crore, in two phases.
- Phase 1 (29.8 km): runs from Sahson on NH-19 to Dandupur on Rewa Road. Land acquisition from around 5,000 farmers across 194 hectares was under way as of February 2026. The original two-year target set in 2023 has passed.
- Phase 2 (41.662 km): a four-lane road from Madhopur near NH-19. The DPR has been cleared and NHAI is advancing the project. Construction had not started as of February 2026.
Until the Ring Road is complete, traffic between the site and the rest of the city depends on existing state and national highways.
Metro and rapid transit proposals
Prayagraj Metro is a proposal only. A revised DPR was issued in April 2026, focusing on rail and air connections. Reporting has described a plan scaled up to about 60 km, with stations planned at the airport and Sangam. A lighter Metrolite option has also been proposed for the city. None of these is under construction as of November 2026.
Site progress and the dates that matter
These dates show how far the site has moved, separate from the transport links above:
- 28 August 2024: Cabinet approval as one of 12 new NICDP projects.
- 8 November 2024: State Support Agreement and Shareholder Agreement signed by the Government of Uttar Pradesh, UPSIDA and NICDIT.
- 30 January 2025: project SPV, AKIC Integrated Manufacturing Cluster Agra-Prayagraj Ltd, incorporated.
- 10 March 2025: Environmental Clearance granted by the UP State Environment Impact Assessment Authority.
- 351.43 acres transferred to the SPV, with Rs 323.09 crore in matching equity from NICDIT. Four industrial plots covering about 42 acres have been allotted to investors.
- May 2026: EPC contractor RCC Developers Pvt Ltd appointed; site survey, clearing and design under way.
The project has an investment potential of Rs 1,600 crore, a trunk infrastructure cost of Rs 658 crore and employment potential of 17,700 jobs. Target industries are e-mobility automobiles and food and beverage processing.
Frequently asked questions
How far is Prayagraj IMC from Prayagraj Airport?
Prayagraj Airport is about 24 km from the site, according to NICDC's project page. It is operational for domestic flights only.
Is the Ganga Expressway open?
Phase 1 of the Ganga Expressway, a 594 km route from Meerut to Prayagraj, was inaugurated on 29 April 2026. The eastward extension to Ballia is still in pre-construction.
Is there a rail freight link near the site?
The New Karchana EDFC Station is about 7 km from the site, and the Eastern Dedicated Freight Corridor is operational through Prayagraj.
Is the Prayagraj Metro under construction?
No. Prayagraj Metro is still a proposal, and a revised DPR was issued in April 2026.
When will Prayagraj Junction redevelopment be finished?
The second phase of Prayagraj Junction redevelopment targets full modernisation by December 2026.
What is the status of the Prayagraj Ring Road?
Phase 1 (29.8 km) was at the land acquisition stage as of February 2026, and Phase 2 (41.662 km) had its DPR cleared but construction had not started.
Sources
- Imc Prayagraj Uttar Pradesh | NICDC
- NICDC & UPSIDA partner to develop key clusters in Agra and Prayagraj (PIB)
- Wikipedia: Prayagraj Airport
- Wikipedia: Ganga Expressway
- NHAI (X): NH-19 Prayagraj Handia-Rajatalab six-lane section
- Wikipedia: Eastern Dedicated Freight Corridor
- Construction World: Prayagraj junction's redevelopment phase 2 starts
- Construction World: Next stage of Prayagraj Junction redevelopment kicks off
- Swarajya: Prayagraj Inner Ring Road Phase II cleared
- Construction World: Prayagraj Inner Ring Road Phase II gets go-ahead
- PropNewsTime: NHAI moves ahead with second phase of Prayagraj Inner Ring Road
- Metro Rail Today: Revised DPR of Prayagraj Metro focuses on seamless Rail-Air connectivity
- Swarajya: Prayagraj Metro project scaled up to 60 km
- Wikipedia: Prayagraj Metrolite
- Metro Rail News: Prayagraj Light Metro or Metrolite proposed for Sangam City
- Cabinet approves 12 industrial smart city projects - NICDC
- NICDC DMU Report, 31.05.2026
- UPSIDA: Saraswati Hi-Tech City