Land Acquisition
Prayagraj IMC Land Acquisition: Compensation and Current Stage
IMC Prayagraj, the Integrated Manufacturing Cluster in Saraswati Hi-Tech City near Naini, Prayagraj district, sits on a notified area of about 352 acres. As of November 2026, 351.43 acres have been transferred by the Uttar Pradesh government to the project company, and no per-acre compensation rate or village-wise list has been announced for the parcel.

| Notified project area | 351.43 to 352 acres: about 231 acres greenfield and 120 acres within Saraswati Hi-Tech City (as of July 2026) |
|---|---|
| Land transferred to project SPV | 351.43 acres, by the Uttar Pradesh government (as of July 2026) |
| Acquisition model | Land transfer to the project SPV under the State Support Agreement of 8 November 2024; no separate farmland award round reported |
| Compensation rate | No per-acre rate announced for this parcel (as of November 2026) |
| Trunk infrastructure cost | ₹658 crore, as listed by NICDC |
| Matching equity from NICDIT | ₹323.09 crore (as of July 2026) |
| Plots allotted to investors | 4 industrial plots, about 42 acres (as of July 2026) |
| Location | Karchana block, adjoining Saraswati Hi-Tech City, about 25 km south of Prayagraj city, Prayagraj district |
| Current stage | EPC contractor RCC Developers Pvt Ltd appointed (as of May 2026); site survey, clearing and design underway |
How the land was secured
The IMC Prayagraj site is a mix of two parts. The project description lists about 231 acres of greenfield land and 120 acres inside Saraswati Hi-Tech City, which together make up the notified area of 351.43 to 352 acres.
The land was transferred by the Uttar Pradesh government to AKIC Integrated Manufacturing Cluster Agra-Prayagraj Ltd, the project company incorporated on 30 January 2025. The transfer followed a State Support Agreement and a Shareholder Agreement signed on 8 November 2024 by the Government of Uttar Pradesh, UPSIDA and NICDIT. Those agreements also released matching central equity.
The host township, Saraswati Hi-Tech City, covers 1,138.78 acres near Naini. UPSIDA's own project record states that this land has already been acquired. NICDC describes the cluster as an augmentation of that township, with developed land available for the electric vehicle sector.
No separate farmland notification or award round for this cluster has been reported.
Compensation rates for the IMC Prayagraj parcel
No per-acre, per-hectare or circle-rate multiple has been announced for the IMC Prayagraj parcel. The land moved to the project company through a government transfer, so no farmer payout figures for this project have been published.
Readers should not apply rates from other land actions in Prayagraj district. The Prayagraj Development Authority runs separate urban housing and commercial schemes. Those are different agencies and different projects.
Villages and tehsils covered
The site lies in the Karchana block and Naini belt of Prayagraj district, south of the city. The nearest rail reference point is New Karchana EDFC Station, about 7 km away, and Prayagraj Airport is about 24 km away.
A village-by-village breakdown of the 352 acres, including per-village hectarage, has not been announced. Readers should not assume that district-level acquisition notices for other projects in Prayagraj cover this site.
Budget allocated
NICDC lists a project cost of ₹658 crore for the cluster, with an investment potential of ₹1,600 crore and employment potential of 17,700 jobs.
- The ₹658 crore covers trunk infrastructure on the site, not land purchase.
- NICDIT has released ₹323.09 crore in matching equity (as of July 2026).
- No separate budget line for land acquisition has been announced for this component.
Disputes and farmer negotiations
No protests, farmer disputes or compensation negotiations tied to the 352-acre IMC Prayagraj parcel have been reported. The land was transferred from the state rather than acquired through a live award process, which is the usual source of such disputes.
Current stage: what has happened and what is next
- 10 March 2025: The State Environment Impact Assessment Authority of Uttar Pradesh granted environmental clearance, the last major approval before trunk works could begin.
- Early 2026: NICDC's tender for design, construction and operation of trunk infrastructure was floated.
- May 2026: EPC contractor RCC Developers Pvt Ltd was appointed. Site survey, clearing and design are underway.
- July 2026: NICDC's status report recorded 351.43 acres transferred to the SPV and four plots of about 42 acres allotted to investors.
- 5 November 2026: UPSIDA issued a letter of intent to Airtel Nxtra Private Limited for a proposed 10 MW data centre at Saraswati Hi-Tech City, with an estimated investment of ₹220 crore and around 300 jobs. The data centre is a separate allotment on the same township and is at the letter-of-intent and land-allotment stage.
Plots in Saraswati Hi-Tech City also went to a UPSIDA e-auction for residential and commercial use in July 2026. That round is separate from the industrial cluster.
What the cluster is for
The cluster is one of 12 new projects approved under the National Industrial Corridor Development Programme on 28 August 2024. Its target industries are e-mobility and automobiles, and food and beverage processing. It forms part of the Amritsar Kolkata Industrial Corridor, with the Eastern Dedicated Freight Corridor as its backbone.
Frequently asked questions
Was farmland acquired for IMC Prayagraj?
The Uttar Pradesh government transferred 351.43 acres of the project site to the project company, AKIC Integrated Manufacturing Cluster Agra-Prayagraj Ltd, under agreements signed on 8 November 2024. No separate farmland award round for the cluster has been reported.
What compensation rate applies to IMC Prayagraj land?
No per-acre compensation rate has been announced for the 352-acre IMC Prayagraj parcel. Rates set for other Prayagraj projects do not apply to this site.
Which villages are covered by the IMC Prayagraj project?
The site lies in the Karchana block near Naini in Prayagraj district, about 25 km south of Prayagraj city. A village-wise list of the 352 acres has not been announced.
What is the budget for IMC Prayagraj?
NICDC lists a project cost of ₹658 crore for trunk infrastructure, with an investment potential of ₹1,600 crore and 17,700 jobs. No separate land-acquisition budget has been announced.
Are there farmer protests over IMC Prayagraj land?
No protests, farmer disputes or compensation negotiations tied to this parcel have been reported.
Who is building the IMC Prayagraj site?
RCC Developers Pvt Ltd was appointed as the EPC contractor as of May 2026, and site survey, clearing and design work is underway.
Sources
- IMC Prayagraj Uttar Pradesh | NICDC
- Saraswati Hitech City - UPSIDA
- Saraswati Hi Tech City, Prayagraj - UPSIDA
- IMC at Prayagraj in Prayagraj (Uttar Pradesh): Project Updates & Investment Details | IIG
- AKIC IMC Agra Prayagraj Limited - E-Tender Notice
- NICDC & UPSIDA partner to develop key clusters in Agra and Prayagraj (PIB)
- Cabinet approves 12 Industrial nodes/cities under National Industrial Corridor Development Programme (PIB)
- National Industrial Corridor Development Programme (NICDP) - DPIIT
- National Industrial Corridor Development Corporation - DMU Report, 31.05.2026
- Uttar Pradesh Signs Agreements for Industrial Clusters - ThePrint
- Uttar Pradesh to Set Up 16 Industrial Zones Under SVPEIZ Scheme - Indian Masterminds
- Airtel Nxtra data centre Prayagraj 220 crore investment - Indian Masterminds