Industrial power supply
AURIC Bidkin Takes a Step Toward Power for Two Sector 13 Factory Plots
The Maharashtra Industrial Township Limited (MITL) has issued separate tenders for electrical works that will supply power to two industrial plots in Sector 13 of the AURIC Bidkin industrial area near Chhatrapati Sambhajinagar (Aurangabad). The combined estimated cost of the two works is about Rs 12.17 lakh, and the work is at the tender stage as of 17 November 2026.

| Authority | Maharashtra Industrial Township Limited (MITL) |
|---|---|
| Location | Sector 13, AURIC Bidkin industrial area, Chhatrapati Sambhajinagar (Aurangabad), Maharashtra |
| Plot beneficiaries | Viraj Industries and Aditya Rudra Industries, each on its own plot |
| Combined estimated cost of electrical works | Rs 12,17,000 (about Rs 12.17 lakh) |
| Feeder pillar, earthing and foundation estimate | Rs 4,55,441 (mini feeder pillar of 315-320 ampere capacity) |
| Tender date | Published 12 November 2026 |
| Status (as of 17 November 2026) | Tender stage; MITL has published the works as separate contracts |
What MITL has tendered
MITL has floated separate tenders for electrical works that will set up the power distribution system on two plots in Sector 13 of the AURIC Bidkin industrial area. One work covers the plot allotted to Viraj Industries and the other covers the plot allotted to Aditya Rudra Industries. The two contracts are being handled separately, but together they carry an estimated cost of about Rs 12.17 lakh.
One sub-item stands out. It covers a mini feeder pillar of 315-320 ampere capacity, along with earthing and a concrete foundation, with an estimated cost of Rs 4,55,441. The feeder pillar is the point where the supply is split and distributed to the plot, so it is the piece that makes electricity available to the factories once they are built.
- Authority: MITL, which administers the Bidkin and Shendra nodes of AURIC
- Scope: electrical works for the power distribution system on both plots
- Combined estimated cost: about Rs 12.17 lakh
- Status as of 17 November 2026: tender stage
What this changes for Bidkin and Sector 13
For the two allottees, the tenders are the step that turns an allotted plot into a site that can be connected to power. Factories need a dependable supply before equipment can be installed and tested, so the power work sits early in the sequence of building a plant.
For the wider Bidkin belt, the move shows the utility layer of the AURIC plan being filled plot by plot. Each allotted plot that gets its own distribution connection adds to the industrial base in Sector 13 and gives the next allottee a working example of how the supply is laid out.
AURIC Bidkin in context
AURIC, also known as Aurangabad Industrial City, is a 10,000-acre greenfield industrial smart city spread across the Shendra and Bidkin areas, with about 8,000 acres at Bidkin and about 2,000 acres at Shendra. It is built and run by MITL, a joint venture of MIDC and NICDC, and is an anchor node of the Delhi-Mumbai Industrial Corridor. As of November 2026 the project is under construction.
- 323 plots allotted, covering 3,029 acres of industrial land and 117 acres of mixed-use land (as of September 2025)
- More than 300 companies allotted plots (mid-2026)
- Committed investment above ₹1.5 lakh crore (mid-2026)
- Investment potential of ₹71,343 crore and about 62,405 direct and indirect jobs (as of September 2025)
Other allottees are moving ahead. Ather Energy says its factory inside AURIC remains on track for phased commercial output from December 2026. Godawari Power and Ispat has approved a ₹100 crore container manufacturing line at AURIC Bidkin, with commissioning expected by March 2028, and has moved its ₹1,100 crore cold rolling mill project there from Chhattisgarh. In August 2026, MIDC proposed a new 5,000-acre industrial estate in Bidkin because AURIC is nearing plot saturation.
Local demands and what comes next
Power is one of several needs in the area. In mid-November 2026, local residents in the Bidkin industrial corridor raised pending local jobs, water supply, a bypass road and a ring road, and said work had stalled despite earlier orders from the Industries Minister. They planned to take these demands to the Chief Minister in Mumbai.
For the two Sector 13 plots, the next stage is the award of the electrical contracts, followed by the works themselves. Buyers and allottees who track the Bidkin belt should watch for contract awards, the commissioning of the first AURIC factories from December 2026, and any response to the road, water and jobs demands raised by residents.
Frequently asked questions
Who is supplying power to the two Sector 13 plots in AURIC Bidkin?
MITL, the Maharashtra Industrial Township Limited, has issued separate tenders for the electrical works that will set up the power distribution system on the plots allotted to Viraj Industries and Aditya Rudra Industries.
How much will the electrical works cost?
The two electrical works have a combined estimated cost of about Rs 12.17 lakh, and the feeder pillar, earthing and foundation sub-item is estimated at Rs 4,55,441.
Which companies are the two plots allotted to?
The two plots in Sector 13 are allotted to Viraj Industries and Aditya Rudra Industries, with each company holding its own plot.
Is AURIC Bidkin operating yet?
As of November 2026 AURIC is under construction, and Ather Energy says its factory inside AURIC is on track for phased commercial output from December 2026.
How big is AURIC Aurangabad Industrial City?
AURIC is a 10,000-acre greenfield industrial smart city across the Shendra and Bidkin areas near Chhatrapati Sambhajinagar (Aurangabad), developed by MITL.
Sources
- Bidkin electricity upgrade, Marathi report on MITL electrical works tenders
- AURIC Aurangabad Industrial City, official site
- AURIC official site, doing business
- Godawari Power acquires 31.45-acre land at AURIC Bidkin Industrial, Maharashtra
- Ather plugs into Maharashtra to roll out 1 million e2Ws every year
- Auric set for 3rd phase