Telangana Government Appoints Surbana Jurong to Prepare Bharat Future City DPR

On 27 December 2025 the Telangana government engaged Singapore-based consultancy Surbana Jurong to prepare the Detailed Project Report (DPR) for the 30,000-acre core phase of Bharat Future City, with zoning to be finalised across 15,000 acres and land allocation to proceed only through global tenders.

Bharat Future City — Telangana Government Appoints Surbana Jurong to Prepare Bharat Future City DPR
Decision date27 December 2025
Consultant appointedSurbana Jurong (Singapore-based)
DeliverableDetailed Project Report (DPR) for Bharat Future City core phase
Core phase area30,000 acres
Zoned functional area within DPR15,000 acres (education, health, IT, AI, sports, film city)
Remaining core-phase area15,000 acres reserved as forest/urban forestry zone
Land allocation mechanismGlobal tenders only
Governing authorityFuture City Development Authority (FCDA)
Core villages namedMucherla, Meerkhanpet, Kandukur
Announcement contextTelangana Rising Global Summit 2025, held 8–9 December 2025 at Mucherla

What was decided

The Telangana state government roped in Singapore-based global consultancy Surbana Jurong to prepare the Detailed Project Report (DPR) for the development of Bharat Future City on the outskirts of Hyderabad. The state government has roped in Singapore-based global consultancy Surbana Jurong to prepare the Detailed Project Report (DPR) for the development of Bharat Future City on the city outskirts, spread over 30,000 acres in its core phase, official sources said.

This is a consultant appointment/notification for the DPR of the core 30,000-acre zone — it is a planning-stage decision, not a construction or land-allotment order. The Telangana state government roped in Singapore-based consultancy Surbana Jurong to prepare the detailed project report (DPR) for the Bharat Future City project, located on the outskirts of the city.

Operative details: areas and zoning

The core phase of the development will span 30,000 acres, with 15,000 acres dedicated to various functional zones, including education, health, IT, AI, sports, and film city facilities. Official sources said the DPR has reached final stages, proposing development of a 15,000-acre core city, while the remaining 15,000 acres will be developed as forest and urban forestry zones with eco-friendly activities.

The proposed Future City will largely extend across areas falling under Mucherla, Meerkhanpet and Kandukur villages. The master plan has been prepared after assessing geographical suitability and soil conditions, with planners deciding on the precise location of each functional zone accordingly.

Within the zoning framework, later reporting citing the DPR indicated specific sectoral allocations: a life sciences hub (4,000 acres), an electric vehicle and energy park (1,976 acres), an electronics and advanced manufacturing zone (2,177 acres), a residential zone (2,477 acres), data centre hub (313 acres), education and university zone (255 acres), an AI city (403 acres), and a health city (594 acres), attributed to ETRealty.com reporting.

Road, drainage and connectivity parameters were also part of the DPR scope: the DPR will detail road widths, drainage systems, underground cabling, grid-based road networks and integrated metro rail connectivity to prevent future traffic congestion.

Practical effect: how land will be allocated

The decision fixes the process by which companies can obtain land in Bharat Future City. Project approvals will be through global tenders, sources added. Chief Minister A. Revanth Reddy framed this as a transparency measure: "We will ensure transparency and high standards through global tenders," said Chief Minister A Revanth Reddy.

Two early corporate proposals were cited at the time of the announcement: Reliance Group's Vantara initiative has proposed a world-class zoo and eco-tourism zone, while Salman Khan Ventures Pvt Ltd has announced a ₹10,000-crore integrated township and film studio project. These remain proposals pending the formal tender process, not confirmed allotments.

Context: Telangana Rising Global Summit

The DPR appointment was announced around the state's flagship investment event. Several reputed companies expressed interest in launching operations in Bharat Future City during the Telangana Rising Global Summit 2025 held earlier this month. The summit itself was held at Bharat Future City in Mucherla on December 8 and 9, and used the site partly as a live showcase for the project.

Which body governs the decision

Bharat Future City is administered by the Future City Development Authority (FCDA), a statutory body created ahead of this DPR appointment. The Future City Development Authority (FCDA) master plan land Hyderabad layer covers 765.28 sq km spanning 56 revenue villages across seven mandals south of the Outer Ring Road, governed exclusively by the Future City Development Authority (FCDA) established via Telangana Cabinet order in March 2025 for the Bharat Future City project.

Separately from the 30,000-acre core DPR, the government also widened the project's overall footprint around the same period: The state government has expanded the Future City footprint by merging surrounding villages, increasing the area to nearly two lakh acres. The Future City Development Authority (FCDA) will invite requests for proposals in January 2026 to prepare a comprehensive master plan for these 2 lakh acres covering 56 revenue villages across multiple mandals, sources added.

What happened next (status update)

As of April 2026, the follow-on master-plan tender process — distinct from the Surbana Jurong DPR appointment covered in this record — had progressed: As of April 2026, the project has reached a critical milestone. Out of an initial pool of 12 global applicants, six prominent firms are now in the final race to prepare the Master Plan-2047. While many consultancy firms initially requested a one-year window to map out the sprawling 1.80 lakh acres, the government has held firm on a December 2026 completion target.

Earlier, bidding for that broader master plan had opened: 12 companies have officially submitted applications in response to the global tender notification. Bids are scheduled to open on March 16, 2026.

Note: this later tender is for the wider ~1.8–2 lakh acre area master plan under FCDA, and should not be confused with the narrower Surbana Jurong DPR appointment for the 30,000-acre core phase dated 27 December 2025, which is the subject of this record.

Development phases

Core city (functional zones)DPR stage, Dec 202515,000 acres for education, health, IT, AI, sports,film cityForest/urban forestry zoneDPR stage, Dec 202515,000 acres of the core 30,000-acre phaseWider FCDA footprintRFP planned Jan 2026; master plan due Dec 2026Nearly two lakh acres across 56 revenue villages

Land use

Core functional zones (education,health, IT, AI, sports, film city)50%Forest / urbanforestry zone50%

Frequently asked questions

What exactly was decided on 27 December 2025?

The Telangana government appointed Surbana Jurong, a Singapore-based consultancy, to prepare the Detailed Project Report (DPR) for the 30,000-acre core phase of Bharat Future City, with zoning to be defined across 15,000 acres.

Does this decision allot land to any company?

No. The brief and reporting are clear that land allocation to companies will happen only through global tenders; the DPR appointment itself is a planning step, not a land allotment.

Which villages fall inside the core Bharat Future City area covered by this DPR?

Sources say the proposed Future City in this core phase will largely extend across Mucherla, Meerkhanpet and Kandukur villages.

What happens to the other 15,000 acres of the 30,000-acre core if only 15,000 acres are zoned for functional use?

Official sources indicated the remaining 15,000 acres of the core phase will be developed as forest and urban forestry zones with eco-friendly activities, rather than built-up functional zones.

Who governs Bharat Future City and enforces this decision?

The Future City Development Authority (FCDA), a statutory body established via a Telangana Cabinet order in March 2025, governs the project area.

Is this the same as the later master-plan tender covering nearly two lakh acres?

No. This record covers the narrower Surbana Jurong DPR appointment for the 30,000-acre core phase (Dec 2025). A separate, later FCDA tender process covers a comprehensive master plan for a much larger area of nearly two lakh acres across 56 revenue villages, with bids opening in 2026.