Telangana hands Southern Regional Ring Road stretch to HGCL, linked to Future City land acquisition

On 22 October 2026, the Telangana government entrusted the southern part of the Regional Ring Road to Hyderabad Growth Corridor Ltd (HGCL), citing that the corporation already handles land acquisition for Bharat Future City. The alignment still needs NHAI approval, and the decision has drawn allegations over tenders and farmer protests.

Bharat Future City — Telangana hands Southern Regional Ring Road stretch to HGCL, linked to Future City land acquisition
DecisionSouthern part of the Regional Ring Road entrusted to HGCL
Deciding bodyGovernment of Telangana
Reported on22 October 2026
Stated reasonHGCL is already handling land acquisition for Future City
Southern stretch lengthAbout 201 km, six-lane expressway, Choutuppal (Thangdapalli) to Sangareddy
Land to be acquired (estimate)Over 2,000 hectares
Central approval status (as of 23 October 2026)NHAI has not yet approved the southern alignment; Union Cabinet Committee on Economic Affairs clearance is still needed
State share of land acquisition cost50 percent, with Rs 1,525 crore allocated in the 2026-27 budget
Future City Development Authority area765.28 sq km; 71 revenue villages after later additions

What the state decided

The Telangana government has handed the southern portion of the Regional Ring Road to HGCL, a corporation that operates as a wing of the Hyderabad Metropolitan Development Authority. A senior official from the Roads and Buildings department said the corporation received the stretch because it is already acquiring land for Future City. The move was reported on 22 October 2026, while controversy continued over Radial Road 2 tenders that HGCL had floated.

The decision changes which agency is answerable for the southern stretch. It does not, on its own, settle the final route, because the alignment still awaits approval from the National Highways Authority of India.

Southern stretch: scope and status

The southern stretch is planned as a 201-km six-lane expressway from Thangdapalli in Choutuppal to Sangareddy, passing through Sangareddy, Rangareddy, Nagarkurnool, Yadadri Bhongir, Vikarabad, Mahabubnagar and Nalgonda districts. Officials estimate that over 2,000 hectares of land will have to be acquired. The alignment and its details have been sent to the Centre, but the Union Cabinet Committee on Economic Affairs has not yet given the clearance needed for execution, and officials say this has forced tenders to be extended repeatedly.

Earlier process steps are on record. A Cabinet sub-committee was formed on 25 September 2024 to examine alignment options, and the State Cabinet approved alignment options on 23 June 2025. The state has reportedly paid Rs 627 crore to NHAI toward the project, and the same report says more than 90 per cent of land acquisition has been completed.

The northern stretch is handled differently. The Ministry of Road Transport and Highways approved it on 5 March 2021, and NHAI invited bids in November 2025 for five packages with an estimated cost of Rs 8,535 crore. The final bid date was 29 April 2026.

Objections and protests

The decision has been made amid objections. A Congress MLA from Munugode, K. Rajgopal Reddy, alleged irregularities in the Radial Road 2 tenders and said the state had lost Rs 600 crore. A separate company alleged that the final tender allocation caused that loss. These are allegations and have not been established by a finding in the reporting.

On the southern stretch, farmers protested changes to the initial alignment. They argued that land belonging to influential people and industrialists was spared, while small and marginal farmers were targeted for acquisition. Leaders from left parties and the Congress party also objected to the alignment changes.

Future City context and HGCL's role

The Future City Development Authority was created by the state Cabinet as a special authority to oversee a project of about 30,000 acres between the Nagarjunasagar and Srisailam highways. The Cabinet also moved 36 villages out of HMDA limits and into the new authority. Later reporting says the authority now covers 71 revenue villages across 765.28 sq km, after 15 more villages were added.

HGCL is also tied to other road works. A greenfield radial road from the Outer Ring Road at Raviryal to the Regional Ring Road at Amangal is to be built by HGCL, and the state has said HMDA's jurisdiction could not extend to the Regional Ring Road because of the 36 villages moved out. Future City's planned land pooling would involve about 16,000 acres, which is part of a 30,000-acre plan.

What comes next

As of 23 October 2026, the main open steps are NHAI approval of the southern alignment and the Union Cabinet Committee on Economic Affairs clearance for execution. Until those are in place, the southern route remains subject to change, and the tender timetable depends on them. Residents and landowners near the proposed route should check the final approved alignment before relying on it, since the reported route has changed more than once.

Frequently asked questions

What exactly did the Telangana government decide?

It entrusted the southern part of the Regional Ring Road to Hyderabad Growth Corridor Ltd, reported on 22 October 2026. The stated reason was that the corporation already handles land acquisition for Future City.

Has the southern alignment been approved?

As of 23 October 2026, reports say NHAI has not yet approved the southern alignment, and the Union Cabinet Committee on Economic Affairs still has to clear execution.

How much land will the southern stretch need?

Officials estimate that over 2,000 hectares must be acquired for the project.

Who is HGCL?

HGCL is a corporation described as a wing of the Hyderabad Metropolitan Development Authority. It is also handling a greenfield radial road linking the Outer Ring Road to the Regional Ring Road.

What is the Future City Development Authority?

It is a special authority the state Cabinet created to oversee the Future City project between the Nagarjunasagar and Srisailam highways. It took 36 villages out of HMDA limits when it was formed.

What are the main objections to the decision?

Critics have alleged tender irregularities, including claims of a Rs 600 crore loss, and farmers have protested that the alignment changes spare influential landholders while targeting small farmers.