Tension prevailed in Medipalli and Kurmaddi villages of Yacharam mandal when revenue officials with police tried to take possession of farmers' land using a JCB, while farmers resisted claiming a court-issued stay order was in effect as of July 1, 2026.

| Total land acquired for Pharma City (2014–2021) | 14,000 acres: 10,000 in Nanaknagar, Tadipatri, Kurmaddi and Medipalli villages in Yacharam mandal; 4,000 in Kandukur mandal |
|---|---|
| Court stay order scope | 2,000 acres in Yacharam villages; revenue officer stated the land being surveyed may fall outside the stay order's scope |
| Land handover status | Acquired land already handed over to Telangana Industrial Infrastructure Corporation (TGIIC) |
| Land acquisition in three mandals | Yacharam, Kandukur and Kadthal; officials said acquisition was largely complete with 432 acres of patta land disputed under court litigation |
| Pharma City original target | 19,333 acres across 10 villages in Yacharam, Kandukur and Kadthal mandals under BRS government (pre-2023) |
| Land repurposed for Future City | More than 7,000 acres acquired for Pharma City now being used for Bharat Future City under Congress government |
| Revenue officer's claim | "There is a stay order, but it concerns 2,000 acre in these villages. The concerned land may not be the land on which the stay is in effect," Yacharam Mandal Revenue Officer Ayyappa said |
| Farmer allegation | A farmer claimed several had approached court and obtained stay order against land acquisition |
Survey and Confrontation
Tension prevailed in Medipalli and Kurmaddi villages of Yacharam mandal in Rangareddy district when revenue officials, along with police, tried to take possession of farmers' land using a JCB. Farmers strongly resisted the action, claiming there was a stay issued by a court.
Farmers alleged the government was proceeding with surveys, boundary marking and acquisition without clarity on compensation. Villagers and farmers obstructed revenue staff who attempted to dig pits and erect TGIIC boards on government and assigned lands, questioning how boards could be installed without compensation.
Officials halted work and shifted TGIIC boards and equipment to the panchayat office.
Revenue Officer's Response
Yacharam Mandal Revenue Officer Ayyappa confirmed a total 14,000 acres of land was acquired during the BRS government for Pharma City: 10,000 acres in Nanaknagar, Tadipatri, Kurmaddi and Medipalli villages in Yacharam mandal, and 4,000 acres in Kandukur mandal.
The officer stated "There is a stay order, but it concerns 2,000 acre in these villages. The concerned land may not be the land on which the stay is in effect." He clarified records related to farmers, land acquisition and compensation are maintained by the Revenue Divisional Office and that acquired land has already been handed to TGIIC.
Land Acquisition History and Repurposing
During the BRS regime, the government had decided to acquire 19,333 acres across 10 villages in Yacharam, Kandukur and Kadthal mandals for Pharma City. Nearly 10,000 acres were identified in villages such as Nakkarthamedipalli, Nanaknagar, Tadiparti and Kurmidda in Yacharam mandal.
More than 7,000 acres were acquired, which now form part of the land being repurposed by the Congress government for Bharat Future City. As of February 2026, officials said land acquisition in Yacharam, Kandukur and Kadthal mandals was largely complete, with disputes pending only over 432 acres of patta land that are under court litigation.
Future City Development Authority Project
Bharat Future City is a 30,000-acre Net-Zero smart city developed by the Telangana government in the south of Hyderabad. The Future City Development Authority (FCDA) is the planning body for Telangana's Fourth City and began operations from June 2025.
Future City is planned in South Hyderabad beyond the Outer Ring Road, covering parts of Maheshwaram, Kandukur, Kadthal, Ibrahimpatnam, Manchal, Yacharam, and Amangal mandals. The project area spans approximately 765 sq km across 56 villages.
Farmer Resistance and Legal Challenges
Farmers from at least four major villages—Medipally, Nanaknagar, Tatiparthy, and Kurmidda—in Ranga Reddy district are actively putting up resistance against land acquisition for the project. Farmers from Kurumidda, Tatiparthi, Nanaknagar and Medipally had approached court and obtained stay orders.
The opposition has formally raised the question of whether land previously acquired under the Land Acquisition Act for Hyderabad Pharma City can lawfully be repurposed for Future City, a separate project. That legal dispute has not been resolved.
What is Next
The immediate issue is resolution of the competing claims over the 2,000 acres covered by court stay order and clarification on the scope of the stay. FCDA will serve as the sole authority to approve building layouts and infrastructure development within the Future City limits, though the legal questions surrounding land title and farmer consent remain unresolved as of July 2026.
Frequently asked questions
Why are officials surveying land if a court stay order exists?
The Yacharam Mandal Revenue Officer stated the court stay order covers only 2,000 acres in these villages and the land being surveyed may not fall within the stay order's scope. He said the acquired land has already been handed to TGIIC.
How much land was originally acquired for Pharma City?
The BRS government had decided to acquire 19,333 acres across 10 villages in Yacharam, Kandukur and Kadthal mandals for Pharma City.
How is land acquired for Pharma City being used for Future City?
More than 7,000 acres acquired for Pharma City under the previous government now form part of the land being repurposed for Bharat Future City under the Congress government.
Who is the Telangana Industrial Infrastructure Corporation (TGIIC)?
TGIIC is the entity to which acquired land has been handed over and holds records and further details on the acquisition.
What is the Future City Development Authority (FCDA)?
The FCDA is the planning body for Telangana's Fourth City and began operations from June 2025.
Are there pending legal disputes over the land?
Land acquisition in Yacharam, Kandukur and Kadthal mandals was largely complete as of February 2026, with disputes pending only over 432 acres of patta land under court litigation.
Sources
- Officials plough land for Future City, farmers say court gave stay
- Bharat Future City Land Acquisition Picks Up Pace
- Future City Hyderabad Master Plan & Land Prices
- FCDA to Begin Operations From June in Future City
- Telangana's ambitious 'Future City' project hits roadblocks
- Anti-Pharma City panel questions Revanth over Future City land issue
- FCDA Masterplan — Bharat Future City Zone
- Hyderabad Pharma City — Grokipedia