Chief Secretary Sets March 2026 Deadline for IMC Gaya Implementation Agency Selection

Bihar Chief Secretary Amrit Lal Meena reviewed the IMC Gaya project in detail and directed authorities to finalize selection of the implementation agency by the end of March 2026, with land already acquired by the state government. The township will become Bihar's largest industrial township, with an EPC tender for the industrial township likely to be floated in the first week of July 2025.

Gaya Industrial Smart City — Chief Secretary Sets March 2026 Deadline for IMC Gaya Implementation Agency Selection
Total Site Area1,670 acres
Project Cost (including land)₹1,339 crore (including land cost of ₹462.14 crore)
Investment Potential₹16,524 crore
Expected JobsApproximately 1,09,185 jobs
Agency Selection DeadlineEnd of March 2026
EPC Tender TimelineFirst week of July 2025
Environmental ClearanceGranted March 18, 2025 by Ministry of Environment and Forest
LocationDobhi block, Sherghati sub-division, Gaya district

What the Chief Secretary Decided

Bihar Chief Secretary Amrit Lal Meena reviewed the project in detail and directed to finalize selection of the implementation agency by the end of March 2026, as land has already been acquired by the state government. He described it as set to become the state's largest industrial township. This decision accelerates a project that had its special purpose vehicle Bihar Integrated Manufacturing City Gaya Ltd (BIMCGL) incorporated on January 06, 2025.

The Numbers

The IMC project spans 1,670 acres in Dobhi block and will be developed at a cost of ₹1,339 crore including land cost of ₹462.14 crore. The tender is being finalized in consultation with NICDC. Upon completion, the project will have an estimated investment potential of ₹16,524 crore and create about 1,09,185 jobs.

What Comes Next

An EPC tender for the industrial township is likely to be floated in the first week of July 2025. In an EPC contract, a single contractor is responsible for all aspects of the project, including design, procurement of material and equipment, and physical construction. The state cabinet had on May 16, 2025 approved a greenfield alignment of approximately 7 km connecting the site with the Golden Quadrilateral (NH-19) at an estimated cost of ₹142 crore.

Project Context and Sectors

IMC Gaya is being established under the AKIC (Amritsar–Kolkata Industrial Corridor) project, one of 11 industrial corridors being developed by the Central government, being implemented in five states. Focused sectors proposed include agro and food processing, readymade garments, technical industry (auto component, steel-based products, aerospace and defence), building materials, furniture, handloom, and handicrafts.

Infrastructure and Facilities

The cluster will support industrial operations and workforce needs with a skill development center, fire station, administrative office, parking, and commercial space, plus extensive infrastructure including a 29.89 km internal road network, 220/33 KV and 33/11 KV electrical substations, 162 MVA assured power supply, and a 19 MLD water supply system. The cluster will also feature 'Plug n Play' infrastructure, such as stormwater drainage, solid waste management, water treatment, sewage treatment, and common wastewater treatment plants, as well as green landscaping.

Key Approvals and Timeline

The Cabinet Committee on Economic Affairs (CCEA) gave approval to the project on August 28, 2024 while environmental clearance was granted by Ministry of Environment and Forest on March 18, 2025. The state government notified it as the industrial area and granted stamp duty waiver in March 2025.

Frequently asked questions

Who is developing IMC Gaya?

The State Support Agreement (SSA) and Shareholder Agreement (SHA) for the establishment of IMC Gaya were signed by the Government of Bihar, NICDC, and the Bihar Industrial Area Development Authority (BIADA).

What does EPC tender mean?

In an EPC contract, a single contractor is responsible for all aspects of the project, including design (engineering), purchase of material and equipment (procurement), and physical construction.

When will the project be completed?

According to India Investment Grid, the project shows a timeline from April 1, 2026 to April 10, 2029 (as of current status), though actual completion dates may adjust based on EPC contractor performance.

How is IMC Gaya connected to other regions?

IMC Gaya is expected to become an appealing hub for both domestic and foreign businesses due to its strong connectivity, which includes the Golden Quadrilateral and multi-track railway lines. NH-19 (Golden Quadrilateral) is 10 km away, NH-22 is 2 km away, with proximity to Gaya Junction (40 km) and the upcoming New Paharpur Railway Station under EDFC (45 km).

What was the state's role in land acquisition?

The land has already been acquired by the state government, as directed by Chief Secretary Amrit Lal Meena.

Which industrial sectors will the IMC attract?

Building materials, agri-food processing, leather goods, ready-made clothing, furniture, handloom and handicrafts, engineering and fabrications, and medical equipment are among the sectors the IMC Gaya will be designed to attract.