GMADA Issues Final Notification to Acquire 196.44 Acres for Sector 87 Commercial Hub, Mohali

The Greater Mohali Area Development Authority (GMADA) has issued its final land acquisition notification covering 196.4438 acres in four villages on Mohali's southern edge to build Sector 87, a new commercial sector conceived as Mohali's version of Chandigarh's Sector 17. The notification follows an earlier gazette notice and a Section 15 hearing of objections from affected landowners.

GMADA Eco City-4 / Greater Mohali-New Chandigarh Urban Expansion — GMADA Issues Final Notification to Acquire 196.44 Acres for Sector 87 Commercial Hub, Mohali
Acquiring authorityGMADA (Greater Mohali Area Development Authority), under Punjab's Housing and Urban Development Department
DecisionFinal land acquisition notification for Sector 87 commercial infrastructure
Reported date18 July 2026
Total area acquired≈196.4438 acres (~196.44 acres)
Villages affectedManak Majra, Nanu Majra, Sohana, Sambhalki
Village-wise land157 kanal (Manak Majra), 891 kanal (Nanu Majra), 520 kanal (Sohana), 1 kanal 12 marla (Sambhalki)
Prior gazette/objection noticePublished and uploaded to GMADA's website on 9 March 2026, with a 30-day objection window
Designated end useCommercial hub — retail, business and civic core, styled on Chandigarh's Sector 17
Compensation routeRs 5 lakh one-time lump sum or annuity, plus developed plots and rehabilitation benefits

What was decided

The Greater Mohali Area Development Authority (GMADA) has issued the final notification to acquire close to 197 acres (196.4438 acres, to be precise) of land spread across four villages on Mohali's southern edge, to build a brand-new commercial sector, Sector 87, envisioned as a retail, business and civic hub, much like the iconic Sector 17 of Chandigarh. Close to 196.4438 acres is being acquired: 157 kanal from Manak Majra, 891 kanal from Nanu Majra, 520 kanal from Sohana and 1 kanal 12 marla from Sambhalki.

The GMADA website's own land-acquisition listings confirm the corresponding procedural document: Acquisition of land setting up Commercial Infrastructure in Sector 87 at SAS Nagar, Hearing of Objections under Section 15.

How the notification got here

This final notification did not appear in isolation — it followed an earlier statutory stage. In an earlier notification, the department declared 196.4 acres in Manakmajra, Nanumajra, Sohana and Sambhalki villages as a resettlement area for setting up commercial infrastructure in Sector 87, Mohali; that notification was published in the Punjab Government Gazette and uploaded to the GMADA website on 9 March 2026. Landowners and other stakeholders were given 30 days from that point to submit objections.

The final notification was published in the Punjab Government Gazette and uploaded to the GMADA website following that earlier round of public notice and a hearing of objections under Section 15 of the land acquisition process; landowners in the affected villages had already been given the opportunity to raise objections and suggestions before this final call was made.

Compensation and rehabilitation on offer

Families can choose a one-time payment of Rs 5 lakh or an annuity option, along with developed plots in new sectors and other rehabilitation benefits as applicable — under the rehabilitation policy, eligible families can opt for developed plots in the newly planned sectors instead of, or alongside, monetary compensation. A related GMADA rehabilitation package for a comparable Mohali acquisition (Sector 103) set out a lump sum rate of Rs 5 lakh to each affected family and a resettlement allowance of Rs 50,000 only to the family whose livelihood is affected, with the acquiring body bearing the stamp duty and registration charges for land or houses allotted to the affected family.

The final notification itself does not fix a specific cash rate per acre for Sector 87; that is normally settled at the subsequent award stage. From the date the gazette notification is published, affected landowners get 30 days to file claims or objections with the Land Acquisition Collector (Urban Development) at PUDA Bhawan, Sector 62, Mohali — anyone with land under Change of Land Use category, or disputes over ownership, compensation amount or plot entitlement, needs to act within this window.

Why Sector 87, and why now

Sector 87 is one of the flagship pieces of a much larger urban-expansion drive around Mohali and New Chandigarh. In a major push for urban development, the Punjab Government gave the nod to acquire 6,285 acres of land to develop nine new sectors and complete pending development in five already-developed sectors in Mohali, with GMADA developing new sectors 84, 87, 103, 120, 121, 122, 123, 124 and part of 101. Sector 84 was designated as an institutional area, Sector 87 as commercial, Sectors 101 and 103 as industrial, while Sectors 120 to 124 and 76 to 80 were earmarked as residential pockets.

The commercial branding of Sector 87 has been consistent across official statements. Officials have described a vision in which "Sector 87 rises as Mohali's Sector 17" alongside a commercial Aerotropolis and a world-class New Chandigarh township. In planning circles, Sector 87 has long been discussed as Mohali's answer to Chandigarh's Sector 17 — a central commercial and civic core where courts, offices, retail and entertainment would sit within walking distance of each other.

By March 2026 this had scaled into an even larger drive. The state government set in motion the compulsory acquisition of 11,103 acres across Greater Mohali and New Chandigarh to build seven new townships, seven new sectors, three new pockets of Aerotropolis, and a brand-new commercial city centre in Sector 87 modelled on Chandigarh's Sector 17.

Location and what surrounds it

Sector 87 sits in the heart of Mohali's most active development corridor, adjoining the fully developed JLPL Sectors 90-91 on one side and the upcoming GMADA Sectors 88-89 on the other, with the district judicial complex in Sector 76 just across the road. A nearby property overview similarly notes the continued development of the Sector 87 City Centre as part of Mohali's overall administrative-hub status around the DAC.

Context: not without friction

GMADA's wider land-acquisition push in Greater Mohali has faced sustained resistance from landowners, and the compensation framework itself has been repeatedly revised. On 6 July 2026 the Punjab Government formally notified the third revision of its Land Pooling Policy in twelve months, amending a policy first issued in January 2021 and revised in November 2025, following an in-principle decision at an April high-level meeting that the Council of Ministers approved on 1 July. Under the revised policy, the commercial SCO component was increased from 200 to 210 square yards per acre, and the commercial land category entitlement was raised from 800 to 840 square yards per acre.

Separately, farmer opposition specific to Sector 87 land has been recorded: landowners of several Mohali villages, including Sohana, protested against a related land pooling policy for Aerotropolis Phase-2, with protesting landowners stating they would not give their land in Sector 87 to GMADA at any cost.

Practical effect for landowners and property watchers

The final notification moves Sector 87 from proposal to an active, legally-backed acquisition. Only after this stage can the award process, compensation disbursal and physical handover of land begin — understanding this sequence helps affected families know what to expect next, and helps property watchers gauge how far along a project really is. Once developed, Sector 87 is expected to anchor footfall and business activity for the surrounding residential sectors, the kind of infrastructure push that tends to lift property values in a ripple effect across nearby localities.

Mohali's growth pattern has typically run: government notification, then road and civic infrastructure, then residential development, then the commercial layer — a sequence Sectors 88 to 91 followed, and which now count among the most sought-after mid-segment addresses in the tricity.

Frequently asked questions

What exactly did GMADA decide?

GMADA issued the final land acquisition notification for 196.4438 acres across four villages — Manak Majra, Nanu Majra, Sohana and Sambhalki — to build Sector 87, a planned commercial sector on Mohali's southern edge.

Which villages and how much land from each?

157 kanal is being taken from Manak Majra, 891 kanal from Nanu Majra, 520 kanal from Sohana, and 1 kanal 12 marla from Sambhalki, totalling roughly 196.44 acres.

What stage of the acquisition process is this?

This is the final notification, which follows an earlier gazette notice (published 9 March 2026) and a hearing of objections under Section 15 of the land acquisition process. The next steps are the award and compensation disbursal stage.

What compensation will affected landowners get?

Affected families can choose a one-time payment of Rs 5 lakh or an annuity, along with developed plots in new sectors and other rehabilitation benefits; a comparable GMADA scheme also lists a resettlement allowance for livelihood-affected families and authority-borne stamp duty on allotted land.

Why is Sector 87 significant?

It is being developed as Mohali's answer to Chandigarh's Sector 17 — a retail, business and civic hub intended to sit alongside courts, offices and entertainment within a compact core.

How does Sector 87 fit into the bigger Mohali expansion plan?

It is one of nine new GMADA sectors (originally covering about 6,285 acres) in a Punjab government plan that later scaled up to a roughly 11,103-acre acquisition drive across Greater Mohali and New Chandigarh, covering new townships, sectors and Aerotropolis extensions.

Has the acquisition faced opposition?

Yes. Landowners in villages including Sohana have protested against related GMADA land pooling and acquisition drives, and the state's land pooling policy for Greater Mohali has been revised multiple times in response to farmer pushback.