Consumer Court Order
NCDRC Orders GMADA to Reassess Purab Premium Apartments Completion Certificates
The National Consumer Disputes Redressal Commission has asked the Greater Mohali Area Development Authority to reconsider the completion certificates for Purab Premium Apartments in Sector 88, Mohali, and issue fresh certificates within 30 days of receiving a certified copy of its order dated 8 October 2026.

| Authority | Greater Mohali Area Development Authority (GMADA) |
|---|---|
| Deciding body | National Consumer Disputes Redressal Commission, New Delhi |
| Order reserved | 10 September 2026 |
| Order pronounced | 8 October 2026 |
| Case numbers | Execution Applications 124 of 2024 and 140 of 2024 |
| Deadline for fresh certificates | 30 days from receipt of the certified copy of the order |
| Certificates under challenge | Memo No. 1652 (19 towers) and Memo No. 1654 (8 towers), both issued 18 October 2024 |
| Project size | 37.5 acres with 1,620 flats, according to a press report |
| Status as of 20 October 2026 | Order pronounced; fresh certificates yet to be issued |
What the Commission ordered
The National Consumer Disputes Redressal Commission, sitting in New Delhi with Presiding Member Dr. Inder Jit Singh and Member Shashi Nandkeolyar, has asked GMADA to take a fresh look at the completion certificates it issued for Purab Premium Apartments in Mohali. GMADA must issue new certificates within 30 days of receiving a certified copy of the order.
The Commission said the Chief Administrator of GMADA has to review the technical reports closely, confirm that every promised work has been finished, and put on record the actual date of completion. It also observed that the earlier certificates were issued as an administrative step based on a Technical Wing report, and that they did not name any specific completion date.
The order was reserved on 10 September 2026 and pronounced on 8 October 2026 in Execution Applications 124 of 2024 and 140 of 2024.
Why the certificates were in dispute
The dispute traces back to a May 2023 judgment in Consumer Complaints 1278 of 2016 and 1634 of 2018. In that ruling, the Commission found that GMADA, acting as both developer and competent authority, had issued allotment letters in June 2016 without a valid Occupation or Completion Certificate. It gave GMADA 45 days to obtain one.
The 2023 ruling linked delay compensation at 6% simple interest to the completion date shown on the certificate. Compensation would run only up to June 2016 if the certificate confirmed completion by then, and to a later date if it showed later completion. A clarificatory order of November 2023 applied the same condition to maintenance charges.
On 18 October 2024, GMADA issued two completion certificates: Memo No. 1652 for 19 towers and Memo No. 1654 for 8 towers. The Allottees Association challenged them in execution proceedings. It argued that the certificates resembled a July 2018 certificate that the Commission had already rejected, that they came after an inordinate delay, that the Chief Administrator signed them alone although a 2022 notification calls for a committee, and that valid fire and environmental clearances were missing. GMADA has defended the certificates.
What changes and what comes next
- GMADA must re-examine the technical reports and record a specific completion date for the project's works.
- The fresh certificates are due within 30 days of GMADA receiving the certified copy of the 8 October 2026 order. The clock therefore starts from that receipt, not from the order date.
- A recorded completion date matters for delay compensation, because the 2023 ruling ties that compensation to the date shown on the certificate.
- As of 20 October 2026, the order has been pronounced and the fresh certificates have not yet been issued.
The project and the wider GMADA picture
Purab Premium Apartments is one of GMADA's flagship residential schemes in Sector 88, Mohali. A press report describes it as spread over 37.5 acres, with 1,620 flats that became available in 2017. The same report said the Punjab government was set to buy 167 flats in the complex for Rs 121.96 crore to house officials.
GMADA is the planning and development authority for the wider Greater Mohali area. On 2 June 2026 it issued a notification for the Eco City-4 project, which is listed on its notifications page under the Housing and Urban Development department. Eco City-4 is a separate project from Purab Premium Apartments, and the Commission's order does not concern it.
For buyers and residents in GMADA schemes, the order is a reminder that completion records and certificates decide how delay claims and handovers are judged.
Frequently asked questions
Who issued the order on Purab Premium Apartments?
The National Consumer Disputes Redressal Commission in New Delhi issued the order, directing GMADA to reconsider the completion certificates it had issued for the project.
How long does GMADA have to act?
GMADA must issue fresh completion certificates within 30 days of receiving a certified copy of the order. The period runs from receipt of that copy.
What is the main point the Commission wants GMADA to fix?
The Commission wants GMADA to base the certificates on a review of the technical reports and to record the actual date of completion, rather than issuing them without a specific date.
Why does the completion date matter to flat owners?
A May 2023 ruling in the same dispute tied delay compensation at 6% simple interest to the completion date shown on the certificate, so the date recorded can affect the compensation period.
Is Eco City-4 part of this order?
No. Eco City-4 is a separate GMADA project, for which GMADA issued a notification on 2 June 2026. The Purab Premium Apartments order concerns a different scheme in Sector 88, Mohali.