CM Dhami Updates NICDIT on IMC Khurpia Progress: Full 1,002-Acre Land Handed to NUITL, Infrastructure on Track

17 August 2026: Chief Minister Pushkar Singh Dhami virtually participated in the third apex monitoring meeting of the National Industrial Corridor Development and Implementation Trust (NICDIT) chaired by Union Finance Minister Nirmala Sitharaman in New Delhi, where he reported critical milestones for the 1,002-acre Integrated Manufacturing Cluster at Khurpia in Udham Singh Nagar district.

Khurpia Industrial Smart City — CM Dhami Updates NICDIT on IMC Khurpia Progress: Full 1,002-Acre Land Handed to NUITL, Infrastructure on Track
Land StatusEntire 1,002 acres of land earmarked for the project in possession of NUITL with no hindrance at the site
Site Area & Cost1,002-acre site with project cost of ₹1,265 crore and investment potential of ₹6,180 crore, poised to generate over 75,000 jobs
EPC ContractEPC contract for IMC Khurpia executed on 20 March 2026 with construction work commenced
Right of Way Cleared24.1 kilometres of Right of Way cleared and handed over to EPC contractor for road construction and essential works
Road InfrastructureFour-laning of 10.7 kilometres of Nagla–Kichha SH-44 in coordination for better connectivity to IMC Khurpia
Power InfrastructurePTCUL undertaking time-bound construction of 400/220 kV substation to ensure uninterrupted and adequate power supply
Trunk Infrastructure DeadlineTrunk infrastructure works related to IMC Khurpia proposed to be completed by December 2028
LocationLocated just 17 km from Rudrapur in Kichha Tehsil, strategically positioned near NH-09, NH-109, and SH-44

What Happened

CM Dhami virtually participated in NICDIT's third apex monitoring meeting chaired by Union Finance Minister Nirmala Sitharaman in New Delhi, where he apprised the meeting of the progress of the Integrated Manufacturing Cluster (IMC) Khurpia being developed in Uttarakhand and the efforts of the state government.

The meeting reviewed the progress of key industrial corridor projects across the country, their timely execution and the development of essential infrastructure.

Land Acquisition Complete

CM Dhami stated that the entire 1,002 acres of land earmarked for the project is in possession of NUITL (National Unified Industrial Transformation Lease) and there is no hindrance of any kind at the site, providing the necessary base for construction to proceed as per schedule. This represents full clearance of land acquisition, a critical prerequisite for infrastructure development.

Construction Contract Executed, Work Underway

The EPC (Engineering, Procurement, Construction) contract for IMC Khurpia was executed on 20 March 2026 and construction work has commenced, with a total of 24.1 kilometres of Right of Way cleared and handed over to the EPC contractor, enabling rapid progress in road construction and other essential works.

Road and Power Infrastructure on Priority

CM Dhami stated that necessary coordination and action are being ensured for four-laning of about 10.7 kilometres of the Nagla–Kichha SH-44, which will provide better road connectivity to IMC Khurpia and play a crucial role in boosting industrial activity in the region.

PTCUL is undertaking time-bound construction of a 400/220 kV substation to ensure uninterrupted and adequate power supply for the project. The CM emphasised that the success of any large industrial cluster depends not only on the establishment of units but also on strong connectivity, reliable power supply and modern trunk infrastructure.

Timeline and Next Steps

The trunk infrastructure works related to IMC Khurpia are proposed to be completed by December 2028. The CM directed officials to maintain continuous monitoring of each stage of the project, ensure effective coordination among departments and focus on maintaining quality and speed in construction.

The CM observed that IMC Khurpia is a crucial project for promoting industrial investment in Uttarakhand and would create new employment opportunities locally, noting the government's endeavour is to ensure development brings employment and skill development opportunities for local youth, and expressed expectation of necessary cooperation from the SPV constituted by Government of India and NICDIT/NICDC.

Project Context

Khurpia Farm in Udham Singh Nagar, Uttarakhand, is a 1,002-acre Integrated Manufacturing Cluster under the Amritsar Kolkata Industrial Corridor (AKIC), located just 17 km from Rudrapur in Kichha Tehsil, strategically located near NH-09, NH-109, and SH-44. The IMC Khurpia includes an Automobile and Engineering Cluster as a mixed development area.

Frequently asked questions

What is IMC Khurpia?

IMC Khurpia is a 1,002-acre Integrated Manufacturing Cluster in Udham Singh Nagar, Uttarakhand, under the Amritsar Kolkata Industrial Corridor, approved as part of the National Industrial Corridor Development Programme.

What was confirmed in the August 2026 NICDIT meeting?

The entire 1,002 acres of land earmarked for the project is in possession of NUITL with no hindrance at the site, and the EPC contract was executed on 20 March 2026 with construction work commenced.

When will trunk infrastructure be ready?

Trunk infrastructure works related to IMC Khurpia are proposed to be completed by December 2028.

What external infrastructure is being developed?

Four-laning of about 10.7 kilometres of the Nagla–Kichha SH-44 is in coordination, and PTCUL is undertaking time-bound construction of a 400/220 kV substation for power supply.

How many jobs is IMC Khurpia expected to create?

The IMC is poised to generate over 75,000 jobs.

Who are the main development agencies?

The project is overseen by NICDC (National Industrial Corridor Development Corporation) at the national level and NUITL at the state level, with PTCUL handling power infrastructure and SIIDCUL supporting state-level coordination.