Industrial Corridor News
Krishnapatnam Industrial Area Gains Investment Case at CII Summit as Land, Rail and Road Works Move Forward
Krishnapatnam Industrial Area, also known as KRIS City and also searched as Krishnapatnam, is a greenfield industrial smart city beside Krishnapatnam Port in Andhra Pradesh, built by APICDC under the Chennai-Bengaluru Industrial Corridor. As of November 2026 it is under construction, and NICDC showcased it at the 31st CII Partnership Summit 2026 alongside the Orvakal and Kopparthy nodes.

| Status | Under Construction (as of November 2026) |
|---|---|
| Developer | AP Industrial Corridors Infrastructure Development Corporation (APICDC), a joint venture of NICDIT and APIIC |
| Location | Near Krishnapatnam Port, Nellore district, Andhra Pradesh |
| Corridor | Chennai-Bengaluru Industrial Corridor (CBIC) |
| Total project area | 10,834 acres (Lok Sabha reply, 21 July 2026) |
| Phase 1 activation area | 2,500 acres planned; 2,139.15 acres transferred to the project company |
| Phase 1 investment potential | About ₹10,500 crore with about 1 lakh direct and indirect jobs (as of mid-2026) |
| Phase 1 approved cost | ₹2,139.44 crore, approved by the Cabinet Committee on Economic Affairs on 30 December 2020 |
| Phase 1 completion target | February 2027 |
What was shown at the CII Partnership Summit
At the 31st CII Partnership Summit 2026, NICDC ran a pavilion presenting its three Greenfield Industrial Smart City nodes in Andhra Pradesh: Krishnapatnam, Orvakal and Kopparthy. Together the three nodes cover about 7,223 acres, and NICDC put their combined investment potential at roughly ₹31,360 crore and their combined employment potential at about 2 lakh jobs.
NICDC's CEO and Managing Director, Rajat Kumar Saini, briefed visiting dignitaries on progress at each node. The Prime Minister and the Andhra Pradesh Chief Minister visited the NICDC pavilion during the summit. NICDC describes the nodes as investment-ready industrial destinations backed by infrastructure and connectivity.
The figures above are for the three nodes combined. The Krishnapatnam-specific figures are the Phase 1 numbers of about ₹10,500 crore and about 1 lakh jobs, and the wider project area of 10,834 acres.
Land, approvals and the project timeline
The Krishnapatnam project has moved through a series of formal steps over several years. The Cabinet Committee on Economic Affairs approved Phase 1 trunk infrastructure at ₹2,139.44 crore on 30 December 2020. The Andhra Pradesh government issued GO Ms No 30 on 11 May 2021, transferring 2,139.15 acres of activation-area land from APIIC to the project company.
- 10 May 2022: Ministry of Environment, Forest and Climate Change granted environmental clearance covering about 4,490 hectares.
- February 2024: An EPC contractor was appointed to build Phase 1 internal trunk infrastructure.
- 8 January 2025: Prime Minister Narendra Modi laid the foundation stone for the project.
- 12 June 2026: The APICDC board approved a land allotment pricing policy covering the Krishnapatnam node (2, 006.09 acres), along with the Orvakal and Kopparthy nodes.
For investors, the land allotment pricing policy is the step that sets how developed industrial plots will be offered. Trunk works are the roads, utilities and drainage that a plot needs before a factory can be built.
Roads, rail and port links
Road and rail access to Krishnapatnam Port is central to the project's logic. The Cabinet approved a 4-lane Badvel-Nellore highway at ₹3,653.10 crore, a corridor of 108.134 km. It cuts the distance to Krishnapatnam Port by 33.9 km, from 142 km to 108.13 km, saving roughly an hour, and it links the Krishnapatnam, Kopparthy and Orvakal nodes.
In a Rajya Sabha reply in August 2026, the Centre said road and rail connectivity projects worth more than ₹18,233 crore around Krishnapatnam Port have been completed or are under implementation. Of nine identified road projects, seven worth ₹16,021.51 crore were under implementation at that time. The package also includes doubling and electrification of the Krishnapatnam–Venkatachalam railway line.
In July 2026 the Andhra Pradesh Industries Minister asked the Railway Ministry for early approval of a 12 km rail siding linking the Krishnapatnam node to the Obulavaripalle-Krishnapatnam line. On 1 August 2026 the Prime Minister announced plans to modernise Krishnapatnam Port within a Coastal Economic Corridor strategy. That announcement is a policy vision and not a separately sanctioned project.
What comes next for the city
The next milestones are practical. Phase 1 trunk infrastructure is still under construction, and the completion target is February 2027. The draft land allotment and pricing policies set the terms on which factories and logistics units can take plots. Once plots are allotted, the pace of investment and hiring will depend on how quickly those plots are taken up.
For the wider region, the combination of the port, the highway upgrade and the rail projects is what supports the planned jobs. Nellore is being positioned as a logistics and electronics node within India's National Industrial Corridor programme, linked to three industrial corridors.
Who is building it
APICDC is a 50:50 joint venture of NICDIT, representing the Centre, and APIIC, representing the state. It runs the Krishnapatnam project under the National Industrial Corridor Development Programme. NICDC, the national corridor body, reports on progress across the Krishnapatnam, Orvakal and Kopparthy nodes.
Development phases
Frequently asked questions
What is the Krishnapatnam Industrial Area?
Krishnapatnam Industrial Area, also known as KRIS City and also searched as Krishnapatnam, is a planned greenfield industrial smart city beside Krishnapatnam Port in Andhra Pradesh.
Who is developing the Krishnapatnam Industrial Area?
The project is being built by APICDC, a 50:50 joint venture of NICDIT and APIIC, under the Chennai-Bengaluru Industrial Corridor.
What is the current status of the Krishnapatnam project?
As of November 2026 the project is under construction, with Phase 1 trunk infrastructure works in progress.
When is Phase 1 expected to be completed?
The Phase 1 completion target is February 2027.
How many jobs is the Krishnapatnam project expected to create?
The Phase 1 investment potential is about ₹10,500 crore, with about 1 lakh direct and indirect jobs, according to government figures as of mid-2026.
How will the Krishnapatnam area be connected by road?
A 4-lane Badvel-Nellore highway, costing ₹3,653.10 crore and 108.134 km long, is approved to link the industrial nodes and cut the distance to Krishnapatnam Port by 33.9 km.
Sources
- Krishnapatnam Industrial Area, Andhra Pradesh - NICDC
- About KRISCITY - APICDC
- Land Allotment Policy - APICDC
- National Industrial Corridor Development Corporation Status Report, 31.05.2026 - NICDC
- Cabinet approves Development of 4-Lane Badvel-Nellore Highway - PIB
- Union Minister Piyush Goyal Reviews Industrial Nodes in Andhra Pradesh - PIB
- Krishnapatnam industrial city gets 2,139 acres - The Hans India