Reliance Consumer Products Limited has commissioned a beverage manufacturing plant at Orvakal in Kurnool district, inside the Orvakal Industrial Smart City being built by NICDC on the Hyderabad-Bengaluru Industrial Corridor. Reports describe it as Asia's largest beverage plant, and it makes Campa Cola, fruit juices and packaged drinking water.

Orvakal Industrial Smart City — Orvakal Industrial Smart City Gains a Running Plant as Reliance Starts Production in Kurnool
Plant operatorReliance Consumer Products Limited (Reliance Industries group)
LocationOrvakal, Kurnool district, Andhra Pradesh
ProductsCampa Cola, fruit juices and packaged drinking water
Foundation stoneNovember 2025, laid by Chief Minister N. Chandrababu Naidu
Cabinet clearance29 October 2026, revised investment of Rs 2,606 crore
Expected employmentAbout 1,200 jobs (Cabinet clearance figure)
Operating statusCommissioned and operational, as reported in November 2026
Industrial node statusUnder construction as of 11 November 2026, with trunk infrastructure works under way

What happened at the Orvakal plant

Reliance Consumer Products Limited has commissioned what it describes as Asia's largest beverage manufacturing plant at Orvakal in Kurnool district. Production started about 12 months after the foundation ceremony in November 2025, a pace that reporting on the project calls quick.

Andhra Pradesh Minister Nara Lokesh announced the commissioning. He said the Campa brand is being revived in Rayalaseema and that the products will reach consumers across India and later in international markets. Reports name two local employees now working at the plant, Mahesh Hari from Nandyal and RK Spoorthi from Kurnool.

Cabinet clearance and the job numbers

The Andhra Pradesh Cabinet cleared a revised Rs 2,606 crore packaged beverage plant at Orvakal on 29 October 2026. The meeting was chaired by Chief Minister N. Chandrababu Naidu and the plant was expected to create about 1,200 jobs. The commissioning reported this month is the start of a plant that was already cleared. It is not a new approval.

Thousands of indirect jobs in transport, packaging and local services are estimated to be linked to the plant.

What it means for the Orvakal industrial node

The plant is the first large operating unit that reporting ties directly to the Orvakal node. The node is a planned industrial township in Orvakal mandal, built under the National Industrial Corridor Development Programme by NICDC and NICDIT with the state's APIIC. The notified master plan covers 9,718.84 acres (GO Ms No. 121, 8 July 2025). The first activation area is 2,621 acres, and 2,346 acres of that are already under state government possession.

NICDC gives an investment potential of Rs 12,000 crore and a projected 45,071 direct jobs for the node. Other projects in the same Cabinet cycle show the wider pipeline. Jakson Integrated Solar has been allotted 290 acres at Meedivemula village for a Rs 6,863 crore solar manufacturing plant. Agastya Green Energy announced a Rs 7,800 crore ingot and wafer plant at Orvakal, with a foundation ceremony on 15 August 2026. The Orvakal Drone City, spread over about 600 acres, has 8 of its 12 first-phase plots allotted to drone companies.

For local buyers and landowners, the practical effect is more demand for housing, shops and services in Orvakal, Nandyal and Kurnool as workers move in. Demand depends on how quickly other units start, so the plant alone does not settle the outlook.

Roads, rail, airport and water

The node is served by National Highway 40, National Highway 44 and the Kurnool Bypass. Kurnool Airport is about 12 km away. The airport has already started pilot training activity, with a DGCA-approved flying training organisation inaugurated there on 26 September 2026.

In July 2026, the Andhra Pradesh Industries Minister met the Union Railway Minister and submitted proposals for a new chord line from Dupadu to Bethamcherla via Orvakal and a 53-km railway siding for the node. The Railway Minister said the proposals would be examined for early approval. Freight links are a key cost factor for plants like this one, so these proposals matter for the next phase.

Water supply has been a constraint. The 57-km pipeline from Muchumarri to Orvakal, costed at Rs 288 crore, was reported 50% complete in November 2024, when the Kurnool Collector ordered the remaining works to be completed quickly.

What comes next

Trunk infrastructure works on the first activation area are the main ongoing task at the node. The EPC contract for these works was signed on 30 October 2025 with M/s GVPR Engineers Ltd, with a letter of award value of Rs 1,197 crore. Reliance's work on the plant is complete, and reports say the company is advancing further food and beverage investments in India.

For buyers and investors, the next checkpoints are the progress of the trunk works, the railway proposals, the allotment of remaining drone and manufacturing plots, and whether the expected jobs turn into hiring at the new units.

Frequently asked questions

Is the Reliance beverage plant at Orvakal running?

Yes. Reports dated 23 November 2026 describe the Orvakal facility as operational after its commissioning.

What does the Orvakal beverage plant make?

The plant produces Campa Cola, fruit juices and packaged drinking water.

How many jobs will the Orvakal plant create?

The Cabinet clearance on 29 October 2026 expected the revised Rs 2,606 crore plant to create about 1,200 jobs.

Where is the Orvakal Industrial Smart City located?

It is in Orvakal mandal, Kurnool district, Andhra Pradesh, on the Hyderabad-Bengaluru Industrial Corridor, with National Highway 40, National Highway 44 and the Kurnool Bypass nearby.

Is Orvakal Industrial Smart City under construction?

Yes. As of 11 November 2026 it is under construction, with trunk infrastructure works under way on the first activation area.