Godawari New Energy gets environmental clearance for 20 GWh battery storage building at AURIC Bidkin

Maharashtra's State Expert Appraisal Committee-3 (SEAC-3) cleared an industrial building for a 20 GWh battery energy storage system (BESS) at the AURIC Bidkin Industrial Area, Chhatrapati Sambhajinagar. The clearance was reported in early October 2026 and was granted to Godawari New Energy Private Limited, a wholly owned subsidiary of Godawari Power and Ispat Limited. It permits building work to start; it does not mean the plant is operating.

AURIC Aurangabad — Godawari New Energy gets environmental clearance for 20 GWh battery storage building at AURIC Bidkin
Decision typeEnvironmental clearance for an industrial building (greenfield BESS facility)
Deciding bodyState Expert Appraisal Committee-3 (SEAC-3), Maharashtra, at its 299th meeting
Date of clearance5 October 2026, as reported by company-linked and trade press (as of October 2026)
ApplicantGodawari New Energy Private Limited, wholly owned subsidiary of Godawari Power and Ispat Limited (GPIL)
SiteAURIC Bidkin Industrial Area, District Chhatrapati Sambhaji Nagar (formerly Aurangabad), Maharashtra
Project size20 GWh battery energy storage system
Capital spent on BESSAbout ₹501 crore as of 30 June 2026, per company disclosure
Plot area, boundaries and EC reference numberNot found in sources reviewed

What was decided

SEAC-3 granted an environmental clearance for an industrial building that will house a 20 GWh BESS. The building sits in the AURIC Bidkin Industrial Area. Reports describe the clearance as fresh, meaning it was issued new for this project rather than extended from an earlier approval.

The reports describe the site as greenfield. They do not describe any existing plant on the land.

Who decided, and when

The clearance came from the State Expert Appraisal Committee-3 of Maharashtra. One report ties it to the committee's 299th meeting. Another gives the grant date as 5 October 2026. The Moneylife weekly roundup that first carried the item is dated 9 October 2026 and does not state the clearance date itself. One trade report places the grant under the national Ministry of Environment, Forest and Climate Change framework, while the committee itself is a state body.

Operative details

Funding and related company moves

Company disclosures put the BESS capital spend at about ₹501 crore as of 30 June 2026. Reports differ on the parent's equity stake in the subsidiary. Moneylife's June 2026 roundup gives a total of ₹450 crore after a 4 June 2026 rights allotment. A later report says a further ₹150 crore was subscribed on 3 July 2026, for a total of ₹600 crore. Separately, GPIL incorporated Godawari Energy Solutions Private Limited, an EPC and O&M company for BESS and related projects, on 1 October 2026.

Practical effect

Background: the AURIC project

AURIC (Aurangabad Industrial City) is developed by Aurangabad Industrial Township Limited (AITL). AITL is a special purpose vehicle set up by the Delhi-Mumbai Industrial Corridor Development Corporation and the Maharashtra Industrial Development Corporation. AITL acts as single point of contact for building permissions and utility connections in the area.

Planning documents describe about 10,000 acres of overall development area across the Shendra and Bidkin nodes, with the industrial area making up about 60% of that. Bidkin's area is listed as 31.79 sq km. The Shendra Bidkin Industrial Area was notified by the Government of Maharashtra on 23 September 2016, and a 2019 regulatory order gives its total area as 4,143.89 hectares. These figures come from older documents and should be checked against current AITL records.

Plot sales in Bidkin have been reported in earlier trade and local press. Those reports list plots from about 153 sq m to 8,475 sq m. They are older than the clearance and may not reflect current availability.

What is not confirmed

Frequently asked questions

Who granted the environmental clearance for the Godawari BESS?

Reports say the State Expert Appraisal Committee-3 (SEAC-3) of Maharashtra granted it, at its 299th meeting. The applicant is Godawari New Energy Private Limited.

When was the clearance granted?

Company-linked and trade reports give 5 October 2026 as the date. The Moneylife roundup that first reported it is dated 9 October 2026 and does not give the clearance date.

Where is the project located?

The site is the AURIC Bidkin Industrial Area in Chhatrapati Sambhaji Nagar district, formerly Aurangabad, in Maharashtra. No plot number or boundary was found.

Does the clearance mean the battery plant is running?

No. The clearance is for an industrial building. The sources reviewed do not give a commissioning date, and they do not confirm construction has started.

What is AURIC and who runs it?

AURIC is the Aurangabad Industrial City. It is developed by Aurangabad Industrial Township Limited (AITL), a special purpose vehicle between the Delhi-Mumbai Industrial Corridor Development Corporation and the Maharashtra Industrial Development Corporation.

How much has Godawari spent on the BESS project?

Company disclosures put capital spend at about ₹501 crore as of 30 June 2026. Reports differ on the total equity invested in the subsidiary, so check the latest filings.