Environmental clearance decision
Godawari New Energy gets environmental clearance for 20 GWh battery storage building at AURIC Bidkin
Maharashtra's State Expert Appraisal Committee-3 (SEAC-3) cleared an industrial building for a 20 GWh battery energy storage system (BESS) at the AURIC Bidkin Industrial Area, Chhatrapati Sambhajinagar. The clearance was reported in early October 2026 and was granted to Godawari New Energy Private Limited, a wholly owned subsidiary of Godawari Power and Ispat Limited. It permits building work to start; it does not mean the plant is operating.

| Decision type | Environmental clearance for an industrial building (greenfield BESS facility) |
|---|---|
| Deciding body | State Expert Appraisal Committee-3 (SEAC-3), Maharashtra, at its 299th meeting |
| Date of clearance | 5 October 2026, as reported by company-linked and trade press (as of October 2026) |
| Applicant | Godawari New Energy Private Limited, wholly owned subsidiary of Godawari Power and Ispat Limited (GPIL) |
| Site | AURIC Bidkin Industrial Area, District Chhatrapati Sambhaji Nagar (formerly Aurangabad), Maharashtra |
| Project size | 20 GWh battery energy storage system |
| Capital spent on BESS | About ₹501 crore as of 30 June 2026, per company disclosure |
| Plot area, boundaries and EC reference number | Not found in sources reviewed |
What was decided
SEAC-3 granted an environmental clearance for an industrial building that will house a 20 GWh BESS. The building sits in the AURIC Bidkin Industrial Area. Reports describe the clearance as fresh, meaning it was issued new for this project rather than extended from an earlier approval.
The reports describe the site as greenfield. They do not describe any existing plant on the land.
Who decided, and when
The clearance came from the State Expert Appraisal Committee-3 of Maharashtra. One report ties it to the committee's 299th meeting. Another gives the grant date as 5 October 2026. The Moneylife weekly roundup that first carried the item is dated 9 October 2026 and does not state the clearance date itself. One trade report places the grant under the national Ministry of Environment, Forest and Climate Change framework, while the committee itself is a state body.
Operative details
- Facility: one industrial building to house a 20 GWh battery energy storage system.
- Location: AURIC Bidkin Industrial Area, Chhatrapati Sambhaji Nagar district, Maharashtra.
- Applicant: Godawari New Energy Private Limited.
- Parent: Godawari Power and Ispat Limited (GPIL), which is steel-focused and is moving into energy storage.
- Not found: plot number, plot area, built-up area, boundary coordinates, EC reference number, validity period, and commissioning date.
Funding and related company moves
Company disclosures put the BESS capital spend at about ₹501 crore as of 30 June 2026. Reports differ on the parent's equity stake in the subsidiary. Moneylife's June 2026 roundup gives a total of ₹450 crore after a 4 June 2026 rights allotment. A later report says a further ₹150 crore was subscribed on 3 July 2026, for a total of ₹600 crore. Separately, GPIL incorporated Godawari Energy Solutions Private Limited, an EPC and O&M company for BESS and related projects, on 1 October 2026.
Practical effect
- Construction: the clearance removes one environmental approval step for building the facility. Reports say it opens the regulatory path for physical construction.
- Operation: no commissioning date, operating licence or grid connection was found in the sources. The plant should not be treated as operating.
- Other approvals: the sources do not list other permits such as building plan sanction, consent to establish, or power connection. Those may still be required.
- Broader plan: one older trade report describes a 20 GWh first phase within a wider plan to grow from 10 GWh to 40 GWh, with a total investment of ₹1,625 crore. This figure is older than the October 2026 clearance and was not confirmed in later sources.
Background: the AURIC project
AURIC (Aurangabad Industrial City) is developed by Aurangabad Industrial Township Limited (AITL). AITL is a special purpose vehicle set up by the Delhi-Mumbai Industrial Corridor Development Corporation and the Maharashtra Industrial Development Corporation. AITL acts as single point of contact for building permissions and utility connections in the area.
Planning documents describe about 10,000 acres of overall development area across the Shendra and Bidkin nodes, with the industrial area making up about 60% of that. Bidkin's area is listed as 31.79 sq km. The Shendra Bidkin Industrial Area was notified by the Government of Maharashtra on 23 September 2016, and a 2019 regulatory order gives its total area as 4,143.89 hectares. These figures come from older documents and should be checked against current AITL records.
Plot sales in Bidkin have been reported in earlier trade and local press. Those reports list plots from about 153 sq m to 8,475 sq m. They are older than the clearance and may not reflect current availability.
What is not confirmed
- The exact clearance date appears in some reports and is absent from the original Moneylife item.
- The brief does not give a parcel number, so the plot cannot be matched to AITL's allotment records.
- No independent copy of the SEAC-3 order was found. The details above rest on company statements and press reports.
Frequently asked questions
Who granted the environmental clearance for the Godawari BESS?
Reports say the State Expert Appraisal Committee-3 (SEAC-3) of Maharashtra granted it, at its 299th meeting. The applicant is Godawari New Energy Private Limited.
When was the clearance granted?
Company-linked and trade reports give 5 October 2026 as the date. The Moneylife roundup that first reported it is dated 9 October 2026 and does not give the clearance date.
Where is the project located?
The site is the AURIC Bidkin Industrial Area in Chhatrapati Sambhaji Nagar district, formerly Aurangabad, in Maharashtra. No plot number or boundary was found.
Does the clearance mean the battery plant is running?
No. The clearance is for an industrial building. The sources reviewed do not give a commissioning date, and they do not confirm construction has started.
What is AURIC and who runs it?
AURIC is the Aurangabad Industrial City. It is developed by Aurangabad Industrial Township Limited (AITL), a special purpose vehicle between the Delhi-Mumbai Industrial Corridor Development Corporation and the Maharashtra Industrial Development Corporation.
How much has Godawari spent on the BESS project?
Company disclosures put capital spend at about ₹501 crore as of 30 June 2026. Reports differ on the total equity invested in the subsidiary, so check the latest filings.
Sources
- Market This Week, Moneylife (9 Oct 2026)
- Godawari Power Arm Gets Environmental Clearance for 20 GWh Battery Storage Facility in Maharashtra, India CSR
- Godawari Power Gets Green Light For 20 GWh Battery Energy Storage System In Maharashtra, Sahi
- Godawari Power Subsidiary Receives Environment Clearance for 20 GWh Storage Facility, Whalesbook
- Godawari Power Arm Gets Clearance for 20 GWh Battery Storage, Equitypandit
- Global Battery Storage News Snippets, Taiyang News
- Godawari Power & Ispat share news, Scanx
- Market This Week, Moneylife (5 June 2026)
- Godawari Power & Ispat invests in newly incorporated Godawari New Energy, Business Standard
- AURIC Pitchbook, National Single Window System
- Aurangabad Industrial City (AURIC): A Gateway For Businesses To Enter India, The Brief
- Maharashtra Industrial Township Limited (AITL) profile, IndiaMART
- Order in Case No. 29 of 2019, Maharashtra Electricity Regulatory Commission (AURIC distribution licence)
- AITL shifts focus to Bidkin industrial estate, Lokmat Times