Industry Expansion
Ather Energy Reaffirms December 2026 Start at AURIC Plant and Adds Capacity
Electric two-wheeler maker Ather Energy says its new factory inside Aurangabad Industrial City (AURIC) remains on track for phased commercial output from December 2026. The company also plans to lift that plant's annual capacity by 1.5 lakh units, to 6.5 lakh, by Q2 FY28.

| Company | Ather Energy (Bengaluru-based electric two-wheeler maker) |
|---|---|
| Location | AURIC, Chhatrapati Sambhajinagar (formerly Aurangabad), Maharashtra |
| Phase 1 annual capacity | 5 lakh units, with commercial production in phases from December 2026 |
| Planned addition at AURIC | 1.5 lakh units, taking the plant to 6.5 lakh units by Q2 FY28 |
| Hosur plant change | 75,000 units, from 4.2 lakh to 4.95 lakh units by December 2026 |
| Combined installed capacity (Hosur and AURIC) | About 11.4 lakh units by Q2 FY28 |
| Investment for the capacity additions | About ₹122 crore across the two facilities, as of October 2026 |
| Development authority | Aurangabad Industrial Township Ltd (AITL) |
What Ather Energy announced
Ather's new facility in AURIC, Chhatrapati Sambhajinagar, is on track to begin commercial production in phases from December 2026, with Phase 1 having an annual production capacity of 5 lakh units. The update came in the company's quarterly results disclosure to the stock exchanges, which covered its results for the second quarter of fiscal 2027.
Ather ties the expansion to demand. Co-founder and CEO Tarun Mehta said demand has more than doubled year-on-year this quarter, and to meet it the company is further augmenting production capacity at Hosur and AURIC.
Capacity and investment figures
The company's plan covers two sites. At Hosur in Tamil Nadu, manufacturing capacity will be enhanced by 75,000 units, from 4.2 lakh to 4.95 lakh units. At AURIC, the plant is to be raised by 1.5 lakh units to 6.5 lakh units.
With these expansions, Ather's combined installed annual production capacity across its Hosur and AURIC facilities is projected to reach approximately 11.4 lakh units by Q2 FY28. The company plans to invest approximately ₹122 crore across these two facilities to support these significant capacity enhancements.
| Site | Current or first-stage capacity | Planned capacity | Timing |
|---|---|---|---|
| Hosur, Tamil Nadu | 4.2 lakh units | 4.95 lakh units | By December 2026 |
| AURIC, Chhatrapati Sambhajinagar | 5 lakh units (Phase 1) | 6.5 lakh units | Phase 1 from December 2026; addition by Q2 FY28 |
About AURIC and its development authority
AURIC is a planned and greenfield smart industrial city developed across 10,000 acres in Maharashtra, as part of the Delhi-Mumbai Industrial Corridor (DMIC). The Shendra node is 2,000 acres and the Bidkin node is 8,000 acres. About 60% of the land is zoned for industrial use, while the rest is zoned for residential and commercial use, public spaces, and social and cultural amenities.
AURIC's development and implementation is being undertaken by Aurangabad Industrial Township Limited (AITL), a Special Purpose Vehicle (SPV) between Maharashtra Industrial Development Corporation (MIDC) and Delhi-Mumbai Industrial Corridor Development Corporation (DMICDC). AITL has a single point contact for building permission, water permission and power. It also manages the day-to-day activities of the industrial city.
Ather's plant is not the first large project at the site. In 2024 reports, the company had chosen Aurangabad (formally renamed Chhatrapati Sambhajinagar) in Maharashtra for its third plant, and Bajaj Auto and Škoda already had units around Auric.
What comes next
The next milestones are the start of phased output at AURIC from December 2026, the Hosur addition by the same month, and the AURIC expansion by Q2 FY28. The Chhatrapati Sambhajinagar factory is likely to run at its total capacity around July-September 2027.
Ather has also said it may move faster on later stages at AURIC. In a separate interview, the CEO described the second phase at the plant as expanding production capacity at the new plant four years earlier than planned, owing to demand outweighing supply. Actual output will depend on the plant's ramp-up, which the company has not yet shown in operating figures.
Development phases
Frequently asked questions
What did Ather Energy announce for the AURIC plant?
Ather Energy said its factory in AURIC, Chhatrapati Sambhajinagar, is on track to start commercial production in phases from December 2026, with a first-phase annual capacity of 5 lakh units. It also plans to add 1.5 lakh units, reaching 6.5 lakh units by Q2 FY28.
How much is being invested?
The company puts the investment at about ₹122 crore across its Hosur and AURIC facilities for these capacity enhancements.
What is AURIC?
AURIC is a greenfield smart industrial city of about 10,000 acres in Maharashtra, located at Shendra and Bidkin near Aurangabad and developed as part of the Delhi-Mumbai Industrial Corridor.
Who develops and runs AURIC?
Aurangabad Industrial Township Ltd (AITL) develops and manages AURIC. It is a special purpose vehicle between MIDC and the Delhi-Mumbai Industrial Corridor Development Corporation.
What is the combined capacity once these additions are done?
Ather expects combined installed capacity across Hosur and AURIC to reach about 11.4 lakh units by Q2 FY28.
Sources
- Ather Energy quarterly results disclosure (BSE filing)
- Ather Energy to Expand Production Capacity by 2.25 Lakh Units
- Ather Energy Q2 FY27 Results: Income Rises 62% YoY
- Ather Energy Q2 FY27 Revenue Up 62%, Boosts Capacity
- AURIC Aurangabad Industrial City official site
- Maharashtra Industrial Township Limited, About Us
- Ather plugs into Maharashtra to roll out 1 million e2Ws every year
- Ather to fast track Phase 2 expansion at Chhatrapati Sambhajinagar plant