Toyota Kirloskar Applies for Environmental Clearance for 816-Acre Bidkin Plant; Construction to Begin February 2026

Toyota Kirloskar Motors has applied for environmental clearance for its upcoming passenger vehicle manufacturing plant at Auric Bidkin, with construction set to begin in February 2026 and completion targeted for December 2027. Spread across 816 acres, the plant will be one of the largest industrial investments in Marathwada.

AURIC Aurangabad — Toyota Kirloskar Applies for Environmental Clearance for 816-Acre Bidkin Plant; Construction to Begin February 2026
Land Area816 acres
Initial Annual CapacityTwo lakh (200,000) vehicles
Development StructureThree phases
Construction TimelineFebruary 2026 to December 2027
Permanent Jobs CreatedMore than 5,000
Temporary Construction JobsAround 2,000
Tree Compensation RatioMore than 2.5 trees planted per tree removed
Green Belt Coverage20–30 per cent of the campus
Plant UnitsPressing-welding, painting, vehicle assembly and utility units
Environmental StandardStrict zero-liquid-discharge policy with advanced wastewater treatment and recycling systems

What Toyota Applied For

Toyota Kirloskar Motors has applied for environmental clearance for its upcoming passenger vehicle manufacturing plant at Auric Bidkin. Spread across 816 acres, the plant will be one of the largest industrial investments in Marathwada. The proposed facility will include pressing-welding, painting, vehicle assembly and utility units.

Construction and Timeline

Once approved, the company will begin construction in February 2026 and complete the project by December 2027. Toyota will execute the development in three phases, with an initial annual production capacity of two lakh vehicles.

Environmental and Ecological Plan

The company plans to cut nearly half of the trees on the project site, but has proposed planting more than 2.5 trees for every tree removed, forming a major ecological restoration plan. Officials said the plant will also maintain a green belt across 20–30 per cent of the campus. It will follow a strict zero-liquid-discharge policy, supported by advanced wastewater treatment and recycling systems.

Employment Impact

Around 2,000 people will get temporary employment during construction, while more than 5,000 permanent jobs will be created after the plant becomes operational. The project is also expected to generate significant indirect employment in transport, security, catering and maintenance services.

Strategic Significance

With energy-efficient systems and dedicated test-track facilities, the Auric Bidkin plant is projected to become a major driver of industrial growth, technology adoption and sustainable development in Marathwada. The facility is located within the Bidkin node of the Delhi-Mumbai Industrial Corridor (DMIC), one of India's flagship infrastructure projects, managed by Aurangabad Industrial Township Limited (AITL), a Special Purpose Vehicle created between the DMIC Development Corporation (DMICDC) and the Maharashtra Industrial Development Corporation (MIDC).

Development phases

Phase 1by 2027Initial setup with production capacity of two lakhvehicles annually; pressing-welding, painting andassemblyPhase 2Post-2027Additional capacity expansion as part of three-phasedevelopment planPhase 3Post-2027Final capacity expansion to be executed after initialphases

Frequently asked questions

What is the size of the Toyota Bidkin plant site?

The plant is spread across 816 acres.

When is construction expected to start and finish?

Construction will begin in February 2026 and be completed by December 2027.

How many jobs will the plant create?

Around 2,000 people will get temporary employment during construction, while more than 5,000 permanent jobs will be created after the plant becomes operational.

What is the initial production capacity?

The initial annual production capacity is two lakh vehicles.

What environmental measures will the plant follow?

Toyota has proposed planting more than 2.5 trees for every tree removed, will maintain a green belt across 20–30 per cent of the campus, and will follow a strict zero-liquid-discharge policy with advanced wastewater treatment and recycling systems.

Who developed Auric Bidkin?

Aurangabad Industrial Township Limited (AITL) is a Special Purpose Vehicle created between the DMIC Development Corporation (DMICDC) and the Maharashtra Industrial Development Corporation (MIDC).

Is environmental clearance already granted?

Toyota Kirloskar Motors has applied for environmental clearance, and once approved, construction will begin. As of December 2025, the application is under review pending approval.