Airport and Connectivity
Dholera Airport Operator Deal Brings the City's Air Link Closer to Service
Airports Authority of India and Dholera International Airport Company Ltd have signed an operations and maintenance agreement for the airport that will serve the Dholera Special Investment Region (Dholera SIR, also searched as DSIR) in Gujarat. The main airside works are complete, but commercial flights had not started as of 4 November 2026.

| Reported | 4 November 2026 |
|---|---|
| Parties | Airports Authority of India (AAI) and Dholera International Airport Company Ltd (DIACL) |
| Agreement type | Operations and maintenance (O&M) |
| Airport site | About 1,426 hectares near Navagam village, Dholera taluka, Gujarat |
| Distance | About 80 km from Ahmedabad and about 20 km from the Dholera SIR boundary |
| Construction (as stated in July 2026) | About 80% complete overall; runway, taxiway and ATC tower complete; terminal about 75% built |
| Licence and flights (as of 4 November 2026) | No DGCA aerodrome licence or airline schedule reported; commercial flights not started |
| Operations target | September or October 2026, set in July 2026 and dependent on DGCA licensing |
What was signed and by whom
Reports dated 4 November 2026 state that Airports Authority of India and Dholera International Airport Company Ltd signed an operations and maintenance agreement for Dholera International Airport in Gujarat. AAI is the central body that operates many of the country's airports. DIACL is a state-government special-purpose company set up for this airport.
An O&M agreement sets out who runs the airport day to day once it is in service. For Dholera, this is the step that moves the airport from construction toward handing over operations.
Where the airport stands
The airport has moved well past the planning stage. The main points of progress reported are:
- Runway, taxiway and air traffic control (ATC) tower: reported complete at the July 2026 review.
- Passenger terminal: about 75% built, planned at 25,000 sq m with capacity for 20 lakh passengers a year.
- Cargo terminal: a planned 2,500 sq m facility to support the industrial ecosystem.
- Trial landing: an AAI aircraft completed a trial landing at the airport on 5 June 2026. The runway is 3,200 metres long and rated for wide-bodied aircraft (Code 4E).
Opening is still ahead. Commercial service needs a DGCA aerodrome licence first. As of 4 November 2026, no DGCA licence notice and no airline schedule had been reported, so the airport is not yet taking scheduled passengers.
What it means for land, roads and jobs in Dholera
The airport is being built to serve the Dholera SIR and its wider hinterland, and to take overflow traffic from Ahmedabad airport. The SIR covers about 920 sq km notified across 22 villages of Dholera taluka, with a sanctioned developable area of about 580 sq km, because roughly one-third lies within the Coastal Regulation Zone. The working core, the 22.54 sq km Activation Area, is the place where air links would matter most to buyers and investors.
Road access is already in place: the Ahmedabad–Dholera Expressway, about 109 km long, is reported operational, and the airport lies about 80 km from Ahmedabad.
For jobs, the strongest link is industrial. Tata Electronics' semiconductor fab, with investment of up to ₹91,000 crore, is the anchor project. It was about 50% construction complete as of April 2026, and commercial output is targeted for mid-2028. DHL has announced a semiconductor logistics warehouse of about ₹50 crore in the SIR, targeted to start operations by August 2027. A memorandum of understanding between Embraer and Adani Aviation Systems envisages a final assembly line for regional aircraft at the airport by 2028. That is an MoU, not a completed plant.
Land values and plot demand in the SIR depend on whether these projects reach operation on schedule. The airport is one of the main infrastructure pieces that supports that schedule, but it does not by itself change the SIR's land-use plan.
What comes next
- DGCA aerodrome licensing, which must be completed before the airport opens.
- An opening date, which is still to be set. The July 2026 target of September or October 2026 depended on licensing.
- Cargo or charter flights, which the state's outlook expects by the end of 2026.
Buyers and businesses should treat the airport as a project near completion whose operating start is not yet confirmed, and check the DGCA and airport operator for the next official notices.
Frequently asked questions
Has Dholera International Airport started commercial flights?
No. As of 4 November 2026, no DGCA aerodrome licence or airline schedule had been reported, so commercial flights had not started.
Who signed the operations and maintenance agreement for the airport?
Airports Authority of India and Dholera International Airport Company Ltd signed the agreement, as reported on 4 November 2026.
Where is Dholera International Airport and how far is it from Ahmedabad?
The airport sits on about 1,426 hectares near Navagam village in Dholera taluka, about 80 km from Ahmedabad and about 20 km from the Dholera SIR boundary.
When will Dholera International Airport open?
The July 2026 target was September or October 2026, but that depends on DGCA licensing, and the exact opening date is still to be set.
Why does the airport matter for the Dholera SIR?
The airport is built to serve the SIR and its hinterland, adding air cargo and passenger links to a region whose anchor projects include Tata Electronics' semiconductor fab.
Sources
- Dholera Times news listing
- Dholera International Airport - Wikipedia
- Dholera Special Investment Region - Wikipedia
- NICDC: Dholera Special Investment Region Gujarat
- Dholera Official: About Us (DICDL)
- Ahmedabad–Dholera Expressway Is Bringing Cities, Families & Dreams Closer - PIB
- Gujarat chief minister visits Dholera SIR, reviews progress of key projects
- Tata Group to Build the Nation's First Fab in Dholera