Land Acquisition
Gangapar Township Land Acquisition: Prayagraj Development Authority Plan
The Prayagraj Development Authority (PDA) is preparing a township of more than 100 hectares in the Gangapar area. As of October 2026 the project is at the land-identification and survey stage, with landowners in more than 15 villages of Soraon tehsil being contacted.

| Developer | Prayagraj Development Authority (PDA) |
|---|---|
| Planned area | More than 100 hectares (as of October 2026) |
| Location | Gangapar area, around Malaka and Shivgarh, near the Ganga Expressway and National Highway |
| Villages being contacted | More than 15 villages under Soraon tehsil (as of October 2026) |
| Current stage | Land search and survey; formal land acquisition to follow the survey (as of October 2026) |
Current stage
The authority has begun the land-identification exercise for the township. The PDA has begun contacting landowners in more than 15 villages under Soraon tehsil as part of the land identification exercise.
An official team is expected to survey the identified areas and examine factors such as land availability, total area and other requirements for developing the township. After completion of the survey, the land acquisition process is expected to move forward according to the applicable procedure.
Land acquisition has therefore not yet started on the ground, based on the reporting available as of October 2026.
Location and scale
The township is planned for the Gangapar area. The Prayagraj Development Authority (PDA) is preparing to develop a new township on more than 100 hectares of land in the Gangapar area, marking another planned expansion of the city beyond its existing urban limits. The PDA vice-chairman has described the plan as a township around Malaka and Shivgarh, with development targeted across more than 100 hectares.
The township is near the Ganga Expressway and National Highway, with housing and civic infrastructure in focus.
Acquisition model
Reporting so far does not state whether the PDA will acquire Gangapar land through consent-based purchase, a statutory award process, or another route. The only acquisition-model detail in the reporting is the general statement that the land acquisition process is expected to move forward according to the applicable procedure after the survey.
Compensation rates
Any rate will be relevant once the PDA publishes its acquisition terms.
Villages covered
The reported count is more than 15 villages under Soraon tehsil, all in the Prayagraj district. The reporting reviewed does not name the individual villages, so no village list is given here.
For context on the district's land-acquisition history, a 2021 report on the Ganga Expressway said 182-hectare land will be acquired in 20 villages of the district. That was a separate highway project, and its villages are not part of this township count.
Budget
No budget or cost estimate for the Gangapar township has been reported. The only large Ganga Expressway figure in the reporting, the Rs 36,402 crore Ganga Expressway project, applies to that highway as a whole and not to this township.
Disputes and farmer negotiations
The land-owner contact described above is the only documented engagement so far.
Background on PDA jurisdiction
The PDA was set up under the state town planning law and its area has grown over time. In January 2022, the PDA developed a Master Plan-2031, which has since been approved by the government, that increased the city's area from 309 to 398 square kilometres as a total of 639 villages of the district were included.
Frequently asked questions
Where exactly is the Gangapar township planned?
The PDA Vice-Chairman said the authority has planned a township around Malaka and Shivgarh. The site is also described as near the Ganga Expressway and National Highway.
How big is the Gangapar township?
The planned township covers more than 100 hectares, according to the PDA's current plan as reported in October 2026.
How many villages are involved?
The PDA has begun contacting landowners in more than 15 villages under Soraon tehsil. The reporting does not give a final village count after the survey.
Has land acquisition started?
Not yet on the ground. The authority is at the land search and survey stage, and acquisition is to follow the survey under the applicable procedure.
What compensation will farmers receive?
Reporting so far has not set out a compensation rate or acquisition model for this township, so no figure can be given yet.