GIFT City Master Plan: Area, Phases, Land Use & Targets

GIFT City's original master plan covers 359 hectares (886 acres) between Ahmedabad and Gandhinagar, targeting 62 million sq ft of built-up area; a further expansion of roughly 161 acres is now being drafted, after a larger 2,300-acre proposal was shelved.

GIFT City — GIFT City Master Plan: Area, Phases, Land Use & Targets
Notified core area359 hectares / 886 acres
SEZ portion106 hectares / 261 acres
Domestic Tariff Area (DTA) portion~253 hectares / 625 acres
Total planned built-up area (BUA)62 million sq ft
BUA completed (as of April 2026)~6 million sq ft
BUA allotted, pipeline to mid-202829.1 million sq ft
Land-use split of BUA67% commercial, 22% residential, 11% social/community
Announced expansion (2026)+161 acres (to ~1,220 acres total)
Original master plannerEast China Architectural Design & Research Institute (ECADI)

Planning horizon and total area

The GIFT City Master Plan governs land use across 886 acres (359 ha) on the banks of the Sabarmati River between Ahmedabad and Gandhinagar, administered by Gujarat International Finance Tec-City Company Limited (GIFTCL). Within this notified area, the total area for the development of GIFT is 359 hectares (886 acres) out of which the SEZ (Special Economic Zone) constitutes 106 hectares (261 acres), with the remainder classified as Domestic Tariff Area (DTA).

The project has since moved into an expansion stage. As of April 2026, GIFT City is set to expand by more than 15 per cent, with plans to add 161 acres to its existing 1,065-acre area, taking the total development footprint to over 1,220 acres. According to the CEO, around 31 hectares of land on the Sabarmati riverbank will be added through reclamation as part of the larger riverfront development, which "is on the river bank and will entail a different master planning." A draft of the revised master plan is expected to be submitted to the Government of Gujarat within the next four months of that April 2026 report.

This is a scaled-back version of an earlier idea. This marks a shift from the larger expansion proposal floated in 2023, when authorities had considered increasing GIFT City's footprint by around 2,300 acres — a plan that would have taken the total area to roughly 3,365 acres by absorbing four surrounding villages in Gandhinagar district, but did not move ahead in its original form. Policy makers later opted for a more gradual development strategy, with greater emphasis on orderly expansion and infrastructure readiness within the existing framework before taking on a much larger territorial increase.

Planned vs. developed built-up area (BUA)

The master plan's core metric is built-up area (BUA), not just land. GIFT City is being developed in phases over 886 acres with a planned built-up area of 62 million square feet.

As of April 2026, actual delivery remains a fraction of this target: out of the total planned development of 62 million square feet, around 6 million square feet has already been completed, while another 29.1 million square feet has been allotted and is expected to be finished by mid-2028. Separately, Wikipedia's summary of Phase-I allotment notes that around 780,000 square metres (8.4 million sq ft) of built-up area has already been allotted from the 1,200,000 square metres (13 million sq ft) available for commercial, residential and social use in that initial tranche. Read together, these figures show a project roughly one-tenth built out against its full 62-million-sq-ft ambition, with a large allotted pipeline still under construction.

Land-use split (share of built-up area)

The master plan allocates built-up area — not raw land — across three uses. GIFT City is a 359-hectare (886-acre) integrated project that creates 62 million square feet of built-up area, including 67% commercial space, 22% residential space and 11% community space. A more granular breakdown from one planning-data source puts this at approximately 42 million sq ft for commercial use, 14 million sq ft for residential use, and 6 million sq ft for social infrastructure, distributed across the SEZ and DTA zones and developed in phases by GIFTCL and private developers.

Zones: SEZ vs DTA

Land within the notified area is split regulatory-wise into two main zones. The SEZ covers 261 acres and is exclusively for IFSC financial services regulated by IFSCA, with operations in foreign currency, while the DTA covers 625 acres and supports domestic businesses, IT firms, and residential development under standard Indian regulations in INR. GIFT City is the first SEZ in India to receive dual-use approval from the SEZ Board of Approvals and the Government of Gujarat, meaning non-IFSC entities can now legally occupy and buy premises in the SEZ zone, removing the earlier restriction that confined SEZ space only to IFSC-registered financial institutions.

Phasing

Historical project documentation describes a multi-phase build-out, though timelines have shifted repeatedly since the project's 2007 launch. Early ambitions were larger than what was eventually built: in its first phase to be complete by 2010, GIFT was to be developed on a land area of 500 acres, with a built-up area potential of up to 75 million sq. ft., with the next phase envisaged for the development of townships around the city. Actual delivery lagged well behind this schedule.

A later project summary describes the realised phasing as: being developed in phases over 886 acres with a planned built-up area of 62 million square feet, where Phase 1 involved 11.2 million square feet and saw some buildings completed and occupied, while Phase 2 plans for 20 million square feet and is ongoing. Of the Phase 1 allocation, about 3.4 million square feet is fully developed and operational, 2.3 million square feet is under construction and 5.5 million square feet is under planning. One retrospective assessment noted that only about 20% of the planned development is complete after over 10 years, underlining how far actual construction has trailed the original master-plan schedule.

The current expansion phase (2026) is distinct from the original BUA phasing and concerns additional land: the +161-acre riverfront/government-land addition described above, with a revised master plan due for submission to the state government.

Population and employment targets

Employment and population targets have been revised down sharply from the project's early aspirations. In a 2013 interview, GIFT City's then managing director projected that by 2020, Gandhinagar and Ahmedabad would convert into international cities with development of GIFT City which would provide around 0.2 to 0.3 million jobs which in turn would generate around 0.9 million population in and around it — a target that was not met on that timeline.

Actual, current figures (as of early-to-mid 2026) are far more modest. By 2026, GIFT City hosts 500+ operational entities and supports 20,000–25,000 jobs, with rapid growth expected. On resident population, the city is host to a population of 15,000 to 20,000 residents and has over 5,000 residential buildings that are already occupied (figures reported in 2025). The long-term policy framing positions GIFT City as part of India's flagship Viksit Bharat 2047 project, with an ambition to compete with Dubai and Singapore as a global financial centre by 2047, rather than a fixed near-term population or jobs number.

Planner and design consultants

The original master plan was designed by a Chinese firm known for shaping modern Shanghai. The concept of GIFT City was ideated in 2007 and its planning was awarded to East China Architectural Design & Research Institute (ECADI), which is credited with the planning of much of modern-day Shanghai. Design and construction delivery has involved several other firms: Design and Architecture — East China Architectural Design & Research Institute (ECADI) and Fairwood Consultants India; Construction — IL&FS, AECOM India, L&T Infrastructure Engineering, CBRE India. Gujarat-based planning firm HCP Design, Planning and Management has separately been engaged for a "Revised Masterplan and Development Plan for GIFT City, Gandhinagar," as listed among its urbanism projects.

Where to find official plan documents

Investors and residents should verify current zoning, FAR/FSI, and land-use rules directly against primary regulatory documents rather than third-party summaries:

Note: zoning and boundary information found in third-party summaries is indicative; users should verify details with Gujarat International Finance Tec-City Co. directly, especially given the ongoing 2026 master-plan revision.

Development phases

Original Phase 1 target (2007 plan)target 2010500 acres of land; built-up potential of up to 75 million sq ft envisaged at launchPhase 1 (realised)ongoing since ~201111.2 million sq ft; ~3.4 million sq ft operational, 2.3 million sq ft under construction, 5.5 million sq ft under planningPhase 2ongoing20 million sq ft plannedCurrent build-out statusas of April 2026~6 million sq ft completed; 29.1 million sq ft allotted, targeted for completion by mid-2028Area expansion (new)draft master plan due ~mid/late 2026+161 acres (including ~31 ha riverfront reclamation), taking total footprint to ~1,220 acresLarger expansion proposal (shelved)proposed 2023, not proceeded+2,300 acres (to ~3,365 acres total), would have absorbed 4 surrounding villages

Land use

Commercial67%Residential22%Social/community infrastructure11%

Frequently asked questions

What is the total planned area of GIFT City?

The original notified master-plan area is 359 hectares (886 acres). As of April 2026, GIFT City authorities have proposed adding 161 acres (via riverfront reclamation and adjoining government land), which would take the total footprint to over 1,220 acres, per statements from GIFTCL's managing director.

Is the 62 million sq ft built-up area target fully built?

No. As of April 2026, around 6 million sq ft of the 62-million-sq-ft target had been completed, with another 29.1 million sq ft allotted and expected to be finished by mid-2028. The remainder is still at planning or pre-allotment stage.

Was a much bigger expansion planned for GIFT City?

Yes. In 2023, authorities considered adding about 2,300 acres (taking the total to roughly 3,365 acres) by absorbing four villages in Gandhinagar district. That proposal did not move ahead in its original form; a smaller, calibrated expansion of about 161 acres is being pursued instead.

What is the land-use split in the master plan?

Of the total built-up area target, the plan allocates 67% to commercial use, 22% to residential use and 11% to social/community infrastructure, split across the SEZ and Domestic Tariff Area (DTA) zones.

Who designed GIFT City's master plan?

The original master plan was awarded to East China Architectural Design & Research Institute (ECADI), the firm credited with much of modern Shanghai's planning, working alongside Fairwood Consultants India on design and architecture. A revised master plan has separately been worked on by Gujarat-based planning firm HCP Design, Planning and Management.

How many jobs and residents does GIFT City currently support?

As of 2026, GIFT City hosts 500+ operational entities supporting an estimated 20,000–25,000 jobs, with a resident population reported at roughly 15,000–20,000 in 2025. This is far below the 2013-era projection of 200,000–300,000 jobs and a surrounding population of about 900,000 by 2020.

Where can I see the official GIFT City master plan documents?

The GIFT Area Development Control Regulations (GDCR), which govern zoning, FAR and permitted uses, are published on the official GIFT Gujarat downloads portal. The parent entity, Gujarat Urban Development Company Limited (GUDC), and the state Urban Development & Urban Housing Department also list official project details.