Power & Energy
GIFT Power Seeks Approval for 10 MW Round-the-Clock Renewable Procurement
GIFT Power Company Limited has petitioned the Gujarat Electricity Regulatory Commission (GERC) for approval to invite bids for 10 MW of round-the-clock renewable power, with an option to raise procurement by up to 100%. As of October 15, 2026, GERC has listed the petition and invited stakeholder views; the procurement and proposed contract terms remain subject to the commission’s consideration.

| Petition | GERC Petition No. 2728 of 2026 |
|---|---|
| Base procurement | 10 MW of round-the-clock renewable energy |
| Capacity option | Up to a 100% green-shoe option |
| Proposed PPA term | 25 years |
| Petition listed | October 13, 2026 |
| Regulator | Gujarat Electricity Regulatory Commission |
What GIFT Power has requested
GIFT Power Company Limited has asked GERC to approve a Request for Selection (RfS) document for procuring 10 MW of round-the-clock renewable energy from grid-connected renewable projects within Gujarat. The proposed 100% green-shoe option could allow the selected procurement to increase by up to the base capacity, subject to the tender process and the company’s requirements.
The company has also requested deviations from central procurement guidelines, including a change in the power delivery point and removal of the standard limit restricting a single bidder to 50% of contracted capacity. The petition proposes power-purchase agreements with a 25-year term.
Why the procurement matters
GIFT Power says the procurement is intended to serve rising electricity demand in GIFT City, also known as Gujarat International Finance Tec-City, and support its renewable-purchase and energy-storage obligations. Round-the-clock supply is intended to provide firmer availability than intermittent renewable generation alone.
The requested delivery-point change is from the Central Transmission Utility interconnection to the periphery of the State Transmission Utility. The company says this would help manage the cost of power delivered to its distribution area.
Regulatory process
GERC lists the matter as Petition No. 2728 of 2026, filed by GIFT Power Company Ltd. under Sections 63 and 86 of the Electricity Act, 2003. The commission has invited stakeholder comments before considering the requested approvals and deviations. The petition is a proposal, not an approval to procure power; the next step is GERC’s consideration after the comment process.
As of October 15, 2026, no procurement award or executed power-purchase agreement is established by the material available for this article.
Frequently asked questions
What is GIFT Power asking GERC to approve?
Approval to issue an RfS for 10 MW of round-the-clock renewable energy, including an option to increase capacity by up to 100%, and approval of requested procurement deviations.
Has GERC approved the procurement?
The petition has been listed and stakeholder comments invited. The proposed procurement is awaiting the commission’s consideration.
How long would the proposed power contracts run?
The petition proposes power-purchase agreements with a 25-year term.
What changes to standard procurement terms has GIFT Power sought?
It has proposed changing the delivery point to the State Transmission Utility periphery and removing the standard 50% cap on the capacity allocated to one bidder.
Why does GIFT Power say it needs the renewable power?
The company cites increasing electricity demand in GIFT City and the need to support its renewable-purchase and energy-storage obligations.