As reported on October 8, 2026, a committee chaired by Uttar Pradesh’s chief secretary asked officials to clarify flood risk and whether a licence fee would apply to YEIDA’s proposed Heritage City in Raya. The revised proposal must undergo further review before it can go to the state cabinet and a developer tender can proceed.

| Development authority | Yamuna Expressway Industrial Development Authority (YEIDA) |
|---|---|
| Proposed site plan | About 750 acres in the Raya Urban Centre, Mathura district |
| Estimated project cost | ₹6,210 crore |
| Flood-risk action | The irrigation department was asked to assess flood risk after parts of the proposed site reportedly flooded during recent rains. |
| Decision still pending | The proposal requires further review before cabinet consideration and a developer tender. |
Flood assessment requested
The committee chaired by the Uttar Pradesh chief secretary asked officials to assess the risk of Yamuna flooding at the proposed site. The October 8 report said recent rains had left parts of the area under water, prompting the request for an assessment by the irrigation department. The report said the assessment is needed before the tender process moves forward.
Licence-fee question remains open
The committee also sought clarity on whether a licence fee would apply to the project. Officials were asked to obtain the finance department’s view and prepare a revised proposal. YEIDA is to place that proposal before its board and then return it to the secretary-level committee for review.
Cabinet and tender are later steps
As of October 2026, the reported sequence is further committee review, followed by possible submission to the state cabinet. A tender to select a developer under the proposed public-private partnership model would come after those steps. The project has not yet reached the developer-tender stage described in the report.
YEIDA’s project page describes Heritage City as part of the Raya Urban Centre and says an updated detailed project report is to be placed before the authority’s board for approval. It also describes subsequent preparation of request-for-proposal and concession-agreement documents.
Frequently asked questions
What prompted the latest review of Heritage City?
The committee sought a flood-risk assessment after parts of the proposed site reportedly flooded during recent rains, and asked officials to clarify whether a licence fee would apply.
Who asked for the flood assessment?
A committee chaired by Uttar Pradesh’s chief secretary asked officials to obtain an assessment from the irrigation department.
How large and costly is the proposal?
The October 8 report describes a plan of about 750 acres with an estimated cost of ₹6,210 crore.
Has a developer tender been issued?
The reported process places further proposal review and cabinet consideration before a developer tender. The October 8 report said the tender process was not yet ready to proceed.
What happens next?
Officials are to clarify the licence-fee question, prepare a revised proposal for review, and seek further approvals before cabinet consideration and a developer tender.