Decision Record
Environmental Clearance Granted for Khurpia Industrial Manufacturing Cluster (IMC) by Uttarakhand SEIAA — 9 March 2023
On 9 March 2023, the State Environment Impact Assessment Authority (SEIAA) of Uttarakhand granted Environmental Clearance for the Integrated Manufacturing Cluster (IMC) at Khurpia Farm, Udham Singh Nagar — a step that came after the project's SPV was incorporated and its state support agreement was signed, and ahead of Cabinet-level approval a year and a half later.

| Decision | Environmental Clearance (EC) granted |
|---|---|
| Deciding body | State Environment Impact Assessment Authority (SEIAA), Uttarakhand |
| Date of decision | 9 March 2023 |
| Project category | 8(b) Townships and Area Development, Category B1 |
| Site area assessed for EC | 410.10 ha (1,013.386 acres) |
| Land later confirmed by state govt. | 1,002 acres (as of Oct 2025 DPIIT report) |
| Villages covered | Khurpia, Bandiya, Deoria, Gauri Kalan & Bhooragauri, Kichha tehsil |
| Project proponent (EC applicant) | SIIDCUL (State Infrastructure & Industrial Development Corporation of Uttarakhand Ltd) |
| Project SPV | NICDC Uttarakhand Industrial Township Limited (incorporated 21 Oct 2022) |
| Power demand assessed | 115 MVA (100 MVA industrial + 15 MVA residential/commercial/utilities) |
What was decided
The Uttarakhand SEIAA approved Environmental Clearance for the Integrated Manufacturing Cluster (IMC) proposed at Khurpia Farm in Udham Singh Nagar district. The proposed IMC covers an area of 410.10 ha, which is less than 500 ha, with a mixed-use built-up area of 16,60,000 sq.mt, and hence falls under the EIA Notification 2006 as an 8(b) Townships and Area Development project, Category B1. Category B1 projects are appraised and cleared at the state level by SEIAA rather than by the Union Ministry of Environment, Forest and Climate Change.
The clearance was recorded in NICDC's own delivery-monitoring update to the Department for Promotion of Industry and Internal Trade (DPIIT): EC for the project has been granted by SEIAA, Uttarakhand on 9th March, 2023.
Who applied, and the site the clearance covers
The application was filed by the state's own industrial land agency. State Infrastructure and Industrial Development Corporation of Uttarakhand Limited (SIIDCUL) proposed the Integrated Manufacturing Cluster at Khurpia Farm, and the proposed IMC site covers an area of 1,013.386 acres (410.10 ha) of Khurpia, Bandiya, Deoria, Gauri Kalan & Bhooragauri. Based on assessment of alternative sites in Uttarakhand, the state government gave its consent and approval for the Khurpia-Prag Farms IMC near Kichha in Udham Singh Nagar district.
At the time of application, the land was undeveloped and unoccupied. The identified land was in possession of SIIDCUL and was currently barren land, and the project area is free from habitation.
On boundaries and drainage, the EC filing notes: River Beni forms the eastern boundary of the site and connects with the Gaula/Kichha river towards the south of the site near Kichha town, while the Paha canal traverses through the north of the plot.
Operative details assessed in the clearance
- Built-up area: Total construction built-up area of 16,60,000 sq.mt over 410.10 acres was assessed, of which residential built-up area is 1,13,312 sq.mt.
- Population: total working population is projected at about 19,000 and total residential population at about 17,670.
- Power demand: total power demand for the Khurpia IMC is 115 MVA, of which 100 MVA is for the industrial area and the remaining 15 MVA for residential, commercial, street lighting and utilities.
- Solid waste: solid waste generation during operation is estimated at about 22.77 TPD, comprising 11.7 TPD municipal waste and 11 TPD industrial waste.
- Water source: the source of fresh water is groundwater, for which permission from the Central Ground Water Board (CGWB) will be taken.
Where the EC sits in the approval timeline
The Environmental Clearance was one step in a longer sequence of state and central approvals reported by NICDC to DPIIT's Delivery Monitoring Unit:
| Date | Milestone |
|---|---|
| 14 Jul 2021 / 30 Apr 2022 | State Support Agreement / State Highway Agreement (SSA/SHA) for the project was approved by NICDIT on 14 July 2021 and executed on 30 April 2022 |
| 8 Jun 2022 | The project proposal was recommended by NICDIT at its meeting held on 8 June 2022 |
| 21 Oct 2022 | NICDC Uttarakhand Industrial Township Limited, the project SPV, was incorporated on 21 October 2022 |
| 9 Mar 2023 | EC for the project was granted by SEIAA, Uttarakhand on 9 March 2023 |
| 28 Aug 2024 | CCEA (Cabinet Committee on Economic Affairs) approval was received on 28 August 2024 |
| 8 Jul 2025 | Letter of Award was issued by the SPV for a Programme Manager for New Cities (PMNC) |
| 18 Oct 2025 | Second call EPC tender was floated on 18 October 2025 |
By the most recent DPIIT reporting cycle referenced, land transfer and matching state equity had progressed well beyond the position at the time of the EC: 1,180.9 acres of land had been transferred by the state government to the Project SPV, with matching equity of Rs. 301.03 crore released, against a total notified project footprint of 1,002 acres.
Practical effect of the decision
Environmental Clearance under the EIA Notification, 2006 is a statutory precondition for constructing and operating a project of this size and category — it does not by itself hand over land, release funds, or start construction, but it removes the principal environmental-regulatory barrier to those steps. In the Khurpia case, the 9 March 2023 EC preceded and enabled the subsequent Cabinet-level (CCEA) approval in August 2024, the appointment of a Programme Manager for New Cities, and the floating of EPC (trunk infrastructure) tenders for roads, water, power and waste-treatment systems on the site.
Practically, developers, allottees and local landholders should treat 9 March 2023 as the date from which the specific 410.10 ha (1,013.386-acre) EC boundary — covering Khurpia, Bandiya, Deoria, Gauri Kalan and Bhooragauri villages — was legally cleared for the mixed industrial-residential-commercial development described in the EC application, subject to whatever conditions SEIAA attached in its order (not reproduced in the source documents reviewed here). Any expansion of the footprint beyond this boundary, such as the additional land later brought under the SPV, would require its own clearance process.
Frequently asked questions
What exactly did the Uttarakhand SEIAA approve on 9 March 2023?
It granted Environmental Clearance (EC) for the Integrated Manufacturing Cluster (IMC) at Khurpia Farm, a Category B1 'Townships and Area Development' project under the EIA Notification, 2006, as reported in NICDC's monitoring update to DPIIT.
Does this Environmental Clearance mean construction was complete or the city is operational?
No. EC is a regulatory clearance needed before construction and operation can lawfully proceed; it followed the SPV's incorporation and the state support agreement, and was itself followed by Cabinet (CCEA) approval in August 2024 and EPC tendering in 2025.
Who applied for the clearance, and who runs the project now?
The application was filed by SIIDCUL, the state's industrial land corporation. Project delivery has since moved to the dedicated SPV, NICDC Uttarakhand Industrial Township Limited, incorporated on 21 October 2022.
What area does the clearance cover, and does it match the land actually being developed?
The EC assessment covered 410.10 hectares (1,013.386 acres) across Khurpia, Bandiya, Deoria, Gauri Kalan and Bhooragauri villages. Later government reporting refers to a 1,002-acre notified footprint and, in more recent monitoring reports, land transfers to the SPV exceeding that figure — so the operative development area has evolved since the 2023 clearance.
What infrastructure capacities were assessed as part of the clearance?
The filing assessed a total power demand of 115 MVA (100 MVA industrial, 15 MVA non-industrial), solid waste generation of about 22.77 TPD, and a projected population of roughly 19,000 workers and 17,670 residents.
What comes after Environmental Clearance in a project like this?
Typically: land transfer to the project SPV, release of matching state/central equity, detailed master planning and engineering, Cabinet-level investment approval, and EPC tendering for trunk infrastructure — all of which followed for Khurpia between 2023 and 2025.
Sources
- National Industrial Corridor Development Corporation — DMU report to DPIIT (31.10.2025)
- Form 1, Category 8(b) B1 — IMC at Khurpia Farm (Environment Clearance portal)
- Brief Summary of Project Parameters — IMC Khurpia (Environment Clearance portal)
- IMC Khurpia Uttarakhand — NICDC project page
- IMC Khurpia — beipl.co.in project details