NICDC Floats Second EPC Tender for Khurpia IMC Infrastructure in Uttarakhand

On 18 October 2025, NICDC Uttarakhand Industrial Township Ltd floated a second-call EPC (Engineering, Procurement and Construction) tender for trunk infrastructure works at Khurpia Integrated Manufacturing Cluster in Uttarakhand. The invitation covers design, construction, testing, commissioning, operation and maintenance of infrastructure works at IMC Khurpia under the Amritsar-Kolkata Industrial Corridor (AKIC).

Khurpia Industrial Smart City — NICDC Floats Second EPC Tender for Khurpia IMC Infrastructure in Uttarakhand
Tender Date18 October 2025
Development EntityNICDC Uttarakhand Industrial Township Ltd (50:50 JV between NICDIT and Uttarakhand Government)
Cluster Area1,002 acres, Khurpia, Udham Singh Nagar district
Industrial CorridorAmritsar-Kolkata Industrial Corridor (AKIC) along Eastern Dedicated Freight Corridor backbone
Truck Terminal8.23 acres allocated; design and construction by EPC contractor
Road NetworkApproximately 24.11 km of hierarchical roads (arterial, sub-arterial, collector, feeder)
Power Infrastructure3 nos. 33kV substations and 1 no. 11 kV substation
Entrance GatesTwo gates in Phase 1; third gate planned in Phase 2 upon land acquisition
Land Transferred500 acres to Project SPV; matching equity of Rs. 207.09 crore released by NICDIT
Pre-bid MeetingHeld 25 October 2025

What Was Announced

NICDC Uttarakhand Industrial Township Ltd, a 50:50 joint venture between NICDIT and the Uttarakhand Government, invited bids for design, construction, testing, commissioning, operation and maintenance of infrastructure works at IMC Khurpia.

The EPC contract covers Component A (roads, civil works, wet utilities, power civil works and HT line realignment, ICT ducts and access chambers), Component B (CETP and STP), and Component C (three 33kV substations and one 11kV substation).

Scope of Work

The truck terminal facility spans 8.23 acres in the master plan, with space for rest areas, loading/unloading, warehousing and access roads. The contractor is responsible for detailed design, construction and delivery of all trunk infrastructure, including roads, bridges, culverts, structures and miscellaneous works.

The total road network spans approximately 24.11 km, including 60m, 45m, 30m, 24m, 18m and 7m right-of-way roads distributed across industrial, residential and utility zones.

Two entrance gates are to be developed in Phase 1: Gate 1 at Access 1 from Kichha Bypass via a 60m right-of-way road, and Gate 2 for private vehicles and intermediate public transport from SH-44. A future Access 3 from SH-44 will be built in Phase 2 upon acquisition of additional land.

Project Context

Khurpia Farm in Udham Singh Nagar is a 1,002-acre Integrated Manufacturing Cluster under the Amritsar-Kolkata Industrial Corridor, located 17 km from Rudrapur in Kichha Tehsil near NH-09, NH-109 and SH-44.

NICDC Uttarakhand Industrial Township Limited, the Special Purpose Vehicle (SPV), was incorporated on 21 October 2022. Environmental clearance was granted by SEIAA Uttarakhand on 9 March 2023, and CCEA (Cabinet Committee on Economic Affairs) approval was received on 28 August 2024.

The project has an estimated infrastructure cost of ₹1,265 crore and an investment potential of ₹6,180 crore, expected to generate over 75,000 jobs.

Implementation Progress

The Programme Manager for New Cities (PMNC) was appointed by the SPV on 8 July 2025. The project was reviewed by the Prime Minister during the 49th Pragati meeting on 24 September 2025.

500 acres of land was transferred by the state government to the Project SPV, and matching equity of Rs. 207.09 crore was released by NICDIT to the Project SPV.

Detailed master planning and preliminary engineering along with cost estimates have been completed by the appointed consultant.

Next Steps

A pre-bid meeting was held on 25 October 2025. The tender evaluation will proceed according to the standard two-envelope system (technical and financial), with a pre-bid meeting having established clarifications on scope and requirements.

Once bids are evaluated and an EPC contractor is selected via Letter of Award (LoA), trunk infrastructure construction will commence, beginning with road networks, utility systems and power substations to enable Phase 1 access points and the truck terminal facility.

Frequently asked questions

Who is developing Khurpia IMC and under what authority?

NICDC Uttarakhand Industrial Township Limited, incorporated on 21 October 2022, is the Special Purpose Vehicle (SPV) implementing the project. It is a 50:50 joint venture between NICDIT (National Industrial Corridor Development and Implementation Trust) and the Uttarakhand Government.

What is the total area and investment scale of Khurpia IMC?

The cluster spans 1,002 acres in Udham Singh Nagar. The infrastructure cost is ₹1,265 crore with a total investment potential of ₹6,180 crore and expected job creation of over 75,000 positions.

What infrastructure components are covered by the EPC tender?

The tender covers trunk infrastructure including roads and civil works, wet utilities, power infrastructure with HT line realignment and ICT ducts, Common Effluent Treatment Plant (CETP), Sewage Treatment Plant (STP), and three 33kV substations plus one 11kV substation.

Why was a second-call EPC tender needed?

The first tender was floated on 16 July 2025 but was re-issued as a second call on 18 October 2025, likely due to modifications in scope, requirements or evaluation outcomes from the initial round.

When is the cluster expected to become operational?

No specific operational date has been announced. Phase 1 includes two entrance gates and truck terminal; Phase 2 infrastructure will be built upon acquisition of additional land. Timeline depends on contractor selection and mobilization, typically spanning 2–3 years for trunk infrastructure completion.

How much land has been transferred to the project so far?

500 acres have been transferred by the state government to the Project SPV, with matching equity of Rs. 207.09 crore released by NICDIT out of the total 1,002-acre site.