Central Decision
CCEA Approves Rs 2,139.44 Crore for Krishnapatnam Industrial Area Phase 1 Trunk Infrastructure (30 December 2020)
On 30 December 2020, the Cabinet Committee on Economic Affairs approved Rs 2,139.44 crore for trunk infrastructure works in Phase 1 of the Krishnapatnam Industrial Area in Andhra Pradesh, one of two nodes cleared that day to kick-start the Chennai-Bengaluru Industrial Corridor. This page records that decision and traces what has actually been built on the ground since.

| Deciding body | Cabinet Committee on Economic Affairs (CCEA), chaired by PM Narendra Modi |
|---|---|
| Date of approval | 30 December 2020 |
| Recommending department | Department for Promotion of Industry & Internal Trade (DPIIT) |
| Approved project cost | Rs 2,139.44 crore (Phase 1 trunk infrastructure) |
| Phase 1 activation area | ~2,139 acres (land later transferred: 2,139.15 acres); DPIIT status note records Phase 1 area as 2,500 acres |
| Corridor | Chennai-Bengaluru Industrial Corridor (CBIC), also in the influence zone of the Vizag-Chennai Industrial Corridor (VCIC) |
| Employment projection (Phase 1) | ~98,000 jobs, of which ~58,000 on-site |
| Implementing SPV | NICDIT Krishnapatnam Industrial City Development Ltd (NKICDL), later renamed AP Industrial Corridor Infrastructure Development Corporation (APICDC) |
| Total node land identified | ~11,095-11,096 acres across North Node (SPSR Nellore) and South Node (Chittoor) |
What Was Decided
The Cabinet Committee on Economic Affairs chaired by Prime Minister Narendra Modi approved proposals of the Department of Promotion of Industry & Internal Trade for construction of various trunk infrastructure components for the Krishnapatnam Industrial Area in Andhra Pradesh, with an estimated project cost of Rs 2,139.44 crore. The approval covered the construction of various trunk infrastructure components in Phase 1 of Krishnapatnam Industrial Area at this estimated cost. The Cabinet Committee approved the proposals from the Department for Promotion of Industry & Internal Trade, and the project involved construction of various trunk infrastructure components for the industrial area.
Companion Approvals the Same Day
The same Cabinet approval also covered the Tumakuru Industrial Area in Karnataka, with an estimated cost of Rs 1,701.81 crore, and a Multi Modal Logistics Hub (MMLH) and Multi Modal Transport Hub (MMTH) at Greater Noida in Uttar Pradesh, with an estimated cost of Rs 3,883.80 crore. In total, the CCEA approved three DPIIT proposals — two Industrial Corridor nodes at Krishnapatnam and Tumakuru plus the Greater Noida hub — at a combined estimated cost of ₹7,725 crore. The release from the Ministry of Commerce and Industry described Krishnapatnam and Tumakuru as approved to kick-start development of the Chennai Bengaluru Industrial Corridor, envisioned as self-sustained greenfield industrial cities with world-class infrastructure, road and rail connectivity to ports and logistics hubs, reliable power, and quality social infrastructure.
Operative Details: Area, Cost and Jobs
An EPC tender for the Phase 1 activation area of 2,139 acres was finalised for issue shortly after the approval, though the NICDC's own project page later cites a slightly different figure — an EPC tender for a Phase 1 activation area of 2,006 acres — reflecting refinements to the master plan over time. Government status reporting from late 2025 records the approval differently again: GoI accorded approval of the project on 30 December 2020 for a Phase 1 area of 2,500 acres.
For the Krishnapatnam node, the estimated employment projection on completion of the first phase was around 98,000, of which about 58,000 persons were likely to be employed at the site itself. Across all three approved projects, industrialisation was expected to generate employment opportunities for more than 2.8 lakh persons.
Location, Land and Villages Affected
Per the initial master plan and State Support Agreement, the total land identified for development is about 11,096 acres, with the Node spread across two sites roughly 60 km apart — the North Node and the South Node — the North Node lying along the coastline south of Krishnapatnam Port in SPSR Nellore district. The North Node covers eight villages in Chillakuru and Kota mandals of SPSR Nellore district, later identified by name as Thamminapatnam, Ballavolu, Momidi, Vellapalem, Thurpu Kanupuru, Kothapatnam, and Siddavaram in Chillakuru and Kota mandals. The South Node is in Chittoor district, about 100 km south-west of Krishnapatnam Port and roughly 2 km south of NH-71. The North Node is further subdivided into three phases based on development timeline, with Phase 1 planned to commence first, followed by other North Node phases and subsequently the South Node.
The State government, NICDIT, and APIIC had already entered into a State Support Agreement (SSA) and Shareholders' Agreement (SHA) on 29 November 2017, ahead of the CCEA's cost approval three years later.
Institutional Mechanism: The SPV
Implementation runs through a dedicated Special Purpose Vehicle — NICDIT Krishnapatnam Industrial City Development Ltd (NKICDL) — to which the Andhra Pradesh government allots land for development of the Krishnapatnam Industrial Node. The SPV was incorporated in 2018 with equal equity of APIIC (Government of Andhra Pradesh) and NICDIT (Government of India); its mandate, originally limited to Krishnapatnam, was expanded to include the Orvakal and Kopparthy nodes through an SSA/SHA amendment dated 30 October 2024, and the SPV was subsequently renamed the "AP Industrial Corridor Infrastructure Development Corporation".
What Happened After the Approval — Timeline
- 11 May 2021: The Andhra Pradesh government's GO Ms No 30 transferred activation-area land measuring 2,139.15 acres from APIIC to the SPV, exempting stamp duty of about Rs 34 crore on the transfer.
- 10 May 2022: Environmental clearance for the project was granted by the Ministry of Environment, Forest and Climate Change.
- February 2024: The EPC contractor for the trunk infrastructure was appointed, with construction of major bridges, road and storm-water drain, utility ducts, external raw-water pipeline and STP subsequently reported in progress.
- January 2025: The Prime Minister laid the foundation stone for the project on 8 January 2025 (recorded elsewhere as 9 January 2025).
- 24 September 2025: The project was reviewed by the Prime Minister during the 49th Pragati Meeting.
- As of 30 November 2025: The State government had transferred 2,139.15 acres of land to the SPV, with matching equity of Rs 533.86 crore released, and cumulative physical progress on the works stood at 24.75%.
Practical Effect for Investors and Locals
The CCEA's December 2020 decision was a budget and mandate approval, not a construction completion. It authorised the Union government's financial commitment to Phase 1 trunk infrastructure (roads, drainage, utilities, water and sewage systems) on the activation-area land carved out of the larger Krishnapatnam Node. Subsequent steps — land transfer to the SPV, environmental clearance, EPC contractor appointment, and the January 2025 foundation-stone laying — mark the shift from paper approval to physical execution. As of the DPIIT's November 2025 status update, works were roughly a quarter complete by physical progress, meaning the industrial plots and jobs promised at approval are not yet available; investors and local landholders should treat the 2020 CCEA nod as the funding decision that made the subsequent land transfer, clearances and construction contracts possible, not as evidence the industrial city is operational.
Development phases
Frequently asked questions
What exactly did the CCEA approve on 30 December 2020?
It approved DPIIT's proposal for construction of trunk infrastructure components in Phase 1 of the Krishnapatnam Industrial Area, at an estimated project cost of Rs 2,139.44 crore.
Was Krishnapatnam the only project approved that day?
No. The same CCEA sitting also approved the Tumakuru Industrial Area in Karnataka (Rs 1,701.81 crore) and a Multi Modal Logistics/Transport Hub at Greater Noida, Uttar Pradesh (Rs 3,883.80 crore), together with Krishnapatnam totalling about Rs 7,725 crore.
How big is the Phase 1 activation area?
Figures vary slightly across official sources: the initial EPC tender referenced 2,139 acres, the NICDC project page later cited 2,006 acres, and a DPIIT status note records a Phase 1 area of 2,500 acres. Land actually transferred to the SPV was 2,139.15 acres.
How many jobs is Phase 1 expected to create?
The government's projection at approval was around 98,000 jobs on completion of the first phase, of which about 58,000 would be employed at the site itself.
Where exactly is the Krishnapatnam Industrial Area located?
It spans a North Node in SPSR Nellore district (covering eight villages across Chillakuru and Kota mandals, near Krishnapatnam Port) and a South Node in Chittoor district, about 60 km apart, under the Chennai-Bengaluru Industrial Corridor.
Who is implementing the project?
A dedicated SPV, NICDIT Krishnapatnam Industrial City Development Ltd, jointly held by APIIC (Andhra Pradesh) and NICDIT (Government of India), later renamed the AP Industrial Corridor Infrastructure Development Corporation after its mandate was expanded to other AP nodes.
Is the industrial area operational yet?
No. As of the DPIIT's status report dated 30 November 2025, cumulative physical progress on Phase 1 trunk infrastructure stood at 24.75%, with the EPC contractor appointed in February 2024 and the Prime Minister laying the foundation stone in January 2025.
Sources
- Cabinet approves Industrial Corridor nodes at Krishnapatnam and Tumakuru under CBIC (PIB press release)
- Krishnapatnam gets big infra push from Centre - Deccan Chronicle
- Cabinet approves industrial corridor nodes at Krishnapatnam, Tumakuru - Business Standard
- Krishnapatnam Industrial Area, Andhra Pradesh - NIC Blog
- Krishnapatnam Industrial Area, Andhra Pradesh - NICDC.in
- Krishnapatnam industrial city gets 2,139 acres - The Hans India
- AP allots 2,139 acres for K'patnam industrial city - Bizz Buzz
- Kriscity to come up in coastal belt of Nellore - The Hans India
- Centre Approves Krishnapatnam Industrial Corridor Node At Rs 2,139 Crore - Sakshi English
- Modi Cabinet Approves Krishnapatnam Industrial Corridor In Andhra Pradesh - Swarajya
- National Industrial Corridor Development Corporation Status Report, 30.11.2025 - DPIIT
- National Industrial Corridor Development Corporation Status Report, 31.05.2026 - NICDC
- National Industrial Corridor Development Corporation Status Report, 31.07.2025 - NICDC
- KRIS City / APICDC (formerly NICDIT Krishnapatnam Industrial City Development Ltd)
- Industrial Corridors - DPIIT, Ministry of Commerce and Industry