YEIDA Hires Tractable Engineering as Consultant for the New Agra Urban Centre Master Plan

On 24 July 2024, YEIDA announced it had engaged consultant Tractable Engineering to prepare the master plan for a new urban hub in Agra along the Yamuna Expressway, with a nine-month deadline and an initial footprint of 10,500 hectares. This record sets out what was decided, who decided it, and what has changed since.

New Agra Urban Centre — YEIDA Hires Tractable Engineering as Consultant for the New Agra Urban Centre Master Plan
Decision announced24 July 2024, by YEIDA
Deciding bodyYamuna Expressway Industrial Development Authority (YEIDA)
Consultant appointedTractable Engineering
Timeline given to consultant9 months to complete study and blueprint under Master Plan 2031
Estimated project cost (2024 statement)₹40,000 crore
Planned area at announcement10,500 hectares (about half of Noida)
Villages involved (2024 figure)At least 30 villages
Prior board decision to build the cityNovember 2023
Consultant hiring process startedMarch 2024
Status as of July 2026Master plan revised and approved by state (2025); land acquisition not yet operational

What Was Decided

The Yamuna Expressway Industrial Development Authority (Yeida) said on Tuesday that it has hired an expert consultant to produce a master plan for the development of an urban hub in Agra along the Yamuna Expressway. The consultant, Tractable Engineering, was given nine months to finish this study and prepare the blueprint under Master Plan 2031. Officials said the new city would be half the size of Noida, with an area of 10,500 hectares.

Once the master plan for the urban metropolis was finalised, work would commence on the project, which officials said would cost ₹40,000 crore.

Who Decided It, and the Timeline Behind the Announcement

The July 2024 consultant appointment was the execution step of an earlier authority decision. In November 2023, Yeida's board decided to build a new metropolis on 10,500 hectares in Agra. The board later approved the plan, and in March 2024 Yeida began the process of hiring a consultant.

Yeida CEO Arun Vir Singh said a consultant had been chosen to do market research and area analysis in Agra to build a master plan for a new metropolis along the Yamuna Expressway, and that once the master plan was submitted, discussed and approved by the authority and the state, land acquisition from farmers would begin.

Operative Details: Area, Cost and Land Use as Announced

The metropolitan hub was to be built on land purchased from at least 30 villages. Singh stated that 20% of the land would be earmarked for residential use, 4% for commercial use, 25% for industrial, 13% for transportation, 15% for greenery, 7% for tourism, and 7% for mixed use. The New Agra Urban Centre was described as hosting a wide range of activities, including industrial, residential, and green spaces.

Purpose and Practical Effect of the Decision

According to Singh, the New Agra Urban Centre's main draw would be its emphasis on tourism and the promotion of environmentally friendly manufacturers and businesses. Practically, the decision did not itself acquire any land or fix final boundaries — it authorised a paid study. Development work on the ground was to begin only after the master plan received approval from the state government.

YEIDA's Wider Mandate and Track Record

The Uttar Pradesh government founded Yeida on 24 April 2001 to develop the areas between Greater Noida and Agra, with the goal of establishing industries to create jobs and revitalise the region. Around 2.5 lakh hectares from 1,149 villages across six districts — Gautam Budh Nagar, Bulandshahr, Aligarh, Hathras, Mathura and Agra — were declared under Yeida's jurisdiction. However, by the time of this announcement the authority had only been able to acquire 20,000 hectares of land along the Expressway, with development so far centred solely on Gautam Budh Nagar district, including the Noida International Airport and the proposed Film City. The New Agra decision marked the authority's first serious push to plan land specifically in the Agra district.

What Happened After the July 2024 Announcement

The scope of the project has shifted materially since the original consultant hire, and figures should be read as of the date reported, not as fixed numbers.

Status as of July 2026

As of this writing, the New Agra Urban Centre remains at the planning and approval stage rather than the construction stage. The state government approved the Phase-2 master plan framework in March 2025, and YEIDA reported a completed master plan in April 2025, but on-the-ground execution had not begun. Market commentary from May 2026 anticipates a sharp rise in land and plotted-development demand in the New Agra corridor "especially once infrastructure execution begins on the ground" — language that itself signals execution had not started by that date. Reported area and village counts have varied across sources (10,500 ha/30+ villages in 2024, 12,200 ha/58 villages in 2025, 44 villages in 2026 reporting), and readers should treat all figures as provisional until a formal YEIDA board resolution or state government notification fixes them.

Practical Effect for Landowners and Investors

For residents of the villages named across various reports (Etmadpur tehsil villages have been most consistently cited), the practical effect of this sequence of decisions is that their land lies within an area under active master-plan study, but no compulsory acquisition notification tied specifically to New Agra has been confirmed in the material reviewed. For investors, the project remains pre-acquisition: master-plan approval and land-use zoning are steps that must occur before plots or developer allocations become available. Anyone transacting on the basis of "New Agra" land should verify current status directly with YEIDA's Mathura regional office, which has been named as the office overseeing execution.

Land use

Residential20%Industrial25%Transportation13%Green/environment15%Tourism7%Mixed use7%Commercial4%

Frequently asked questions

What exactly did YEIDA announce on 24 July 2024?

YEIDA announced it had hired consultant Tractable Engineering to prepare the master plan for the New Agra Urban Centre, an urban hub planned along the Yamuna Expressway in Agra district, under Master Plan 2031.

How much land was the New Agra Urban Centre planned to cover at the time of this decision?

At announcement, officials said the city would cover 10,500 hectares — about half the size of Noida — built on land from at least 30 villages. This figure was later revised upward to 12,200 hectares across 58 villages in the April 2025 completed master plan, and later reporting in 2026 cited 44 villages.

What was the estimated cost of the project?

Officials cited an estimated cost of ₹40,000 crore for the project once the master plan was finalised and work commenced.

Did this decision itself authorise land acquisition?

No. The July 2024 decision only authorised the consultant study. YEIDA's CEO stated that land acquisition from farmers would begin only after the master plan was submitted, discussed and approved by the authority and the state government.

Is Tractable Engineering still the named consultant?

The July 2024 announcement named Tractable Engineering. Subsequent reporting from November 2024 referred to the plan's preparer as a firm named Tractwell Sky Group working with Enzyme Company — a discrepancy in source reporting that could not be resolved from the material available.

Has construction of New Agra started as of mid-2026?

No. As of the most recent reporting reviewed (May 2026), commentary still anticipates land-demand growth 'once infrastructure execution begins on the ground,' indicating that construction and large-scale land acquisition had not yet started.

Which master plan does New Agra fall under — 2031 or 2041?

The July 2024 announcement placed the project under Master Plan 2031. Some later reporting (2024–2026) refers to inclusion in a Master Plan 2041 framework, suggesting the planning horizon has been revisited as the project evolved.