Project Announcement
KICDC Announces Single-Phase Development for Palakkad Industrial Smart City; Works to Start by October 2025
The Kerala Industrial Corridor Development Corporation (KICDC) announced on 9 October 2025 that the infrastructure development of the Palakkad Industrial Smart City, a key project under the Kochi–Bengaluru Industrial Corridor, will be implemented in a single phase. The project's development works are expected to commence by the end of October or early November 2025.

| Total Project Cost (EPC Contract) | ₹1,316.13 crore (including GST) |
|---|---|
| Infrastructure Completion Timeline | 42 months from project start |
| Land Area Covered | 1,710 acres across Pudussery Central, Pudussery West, and Kannambra |
| Contractor Consortium | Dilip Buildcon Limited (DBL) and PSP Projects Limited |
| Land Already Acquired by State | 1,450 acres acquired through Kerala Infrastructure Investment Fund Board (KIIFB) investment of ₹1,489 crore |
| Central Government Investment | ₹1,789.92 crore for infrastructure development |
| Expected Job Creation | 51,000 jobs |
| Implementation Authority | KICDC—jointly formed by KINFRA (State) and NICDIT (Central) with equal equity participation |
| Project Status Among National Industrial Nodes | Kerala is the first state to complete procedures for infrastructure development among 12 industrial corridor-smart city projects sanctioned nationally |
The Announcement
On 9 October 2025, the Kerala Industrial Corridor Development Corporation (KICDC) announced that infrastructure development for the Palakkad Industrial Smart City, a flagship project under the Kochi–Bengaluru Industrial Corridor, will be implemented in a single phase. KICDC has initiated preliminary steps in this regard.
The first coordination meeting involving representatives of the contracting consortium Dilip Buildcon–PSP Projects and the National Industrial Corridor Development and Implementation Trust (NICDIT) is scheduled to be held the week following the announcement.
What This Means: Single-Phase Development Strategy
Although land transfer will be in phases based on central fund availability, infrastructure development is planned to be completed in a single phase on the land already acquired. The Centre will release project funds in stages, with the state government transferring a proportionate share of land acquired by KINFRA once the central share is confirmed.
KICDC plans to complete infrastructure development within 42 months, after which land allotment to companies will begin.
The Contractor and Contract
The construction contract, valued at ₹1,316.13 crore (including GST), was awarded to a joint venture between Dilip Buildcon Limited (DBL) and PSP Projects Limited after a competitive national tender process in which four companies participated.
The EPC contract covers the design, construction, and maintenance of key infrastructure, including roads, bridges, drainage networks, water supply systems, and firefighting infrastructure.
The contract was finalized after national competitive bidding, with the construction contract awarded to the DBL-PSP joint venture.
Land Acquisition and Funding Status
Two years ago, the state government spent ₹1,489 crore through the Kerala Infrastructure Investment Fund Board (KIIFB) for the acquisition of 1,450 acres. By July 2022, 85 per cent of the required land had been acquired, with 1,152 acres acquired in just 14 months.
According to KICDC, the central government will release funds for the project in phases. The central government will invest ₹1,789.92 crore for infrastructure development in the project area.
On 24 October 2025, the Central government sanctioned the third instalment of ₹300.2 crore for the project.
Implementation Timeline and Next Steps
Industries Principal Secretary APM Mohammed Hanish stated that the project's development works are expected to commence by the end of October 2025 or early November 2025.
A high-level review meeting in Kochi in late October 2025 decided to sign the project agreement within that month and begin groundwork immediately, with emphasis on completing the infrastructure ahead of schedule. The meeting was attended by A.P.M. Mohammed Hanish (Principal Secretary, Industries), Rajit Saini (MD & CEO, NICDIT), Santosh Koshi Thomas (MD, KICDC), and representatives from the Dilip Buildcon–PSP Projects joint venture.
Location and Strategic Significance
The Palakkad Node, covering 1,710 acres across three land parcels—Pudussery Central, Pudussery West, and Kannambra—is located 20 km from Palakkad City, 150 km from Cochin, and 50 km from Coimbatore, offering exceptional connectivity for industrial growth.
Palakkad Junction is one of Kerala's largest railway stations under the Southern Railway zone, and Cochin and Coimbatore International Airports provide domestic and international connectivity. The site is within close proximity to Cochin Port (115 km) and Kozhikode Port (124 km).
Why Single-Phase Development Matters
Officials noted that Kerala is ahead of schedule compared to other states implementing similar Industrial Smart City projects, with tendering for infrastructure already completed. This makes Kerala the first state to complete tender procedures among the 12 industrial corridor smart city projects sanctioned last year.
The decision to implement Palakkad Industrial Smart City in a single phase underlines a strong commitment to integrated, streamlined infrastructure delivery.
Development phases
Frequently asked questions
Why is single-phase development being chosen instead of multi-phase?
Although land transfer will be in phases based on central fund availability, infrastructure development is planned to be completed in a single phase on the land already acquired to ensure integrated, streamlined delivery.
What companies are building the infrastructure?
The construction contract is awarded to a joint venture between Dilip Buildcon Limited (DBL) and PSP Projects Limited.
When will construction actually begin?
Industries Principal Secretary APM Mohammed Hanish stated that the project's development works are expected to commence by the end of October 2025 or early November 2025. A high-level meeting decided to sign the project agreement within October 2025 and begin groundwork immediately.
How much has Kerala already spent on this project?
Two years ago, the state government spent ₹1,489 crore through the Kerala Infrastructure Investment Fund Board (KIIFB) for the acquisition of 1,450 acres.
How long will infrastructure development take?
KICDC plans to complete infrastructure development within 42 months, after which land allotment to companies will begin.
Why is Kerala ahead of other states in this national program?
Kerala has become the first state to complete the procedures for infrastructure development among the 12 industrial corridor-smart city projects sanctioned in the country. Officials noted that Kerala is ahead of schedule compared to other states, with tendering for infrastructure already completed.
Sources
- KICDC to implement Palakkad Industrial Smart City in single phase work to start by month-end
- Kerala: Palakkad Industrial Smart City To Be Developed In Single Phase Under Kochi–Bengaluru Corridor
- KICDC to implement Palakkad industrial smart city in single phase
- Centre sanctions Rs 300 crore for Palakkad Industrial Smart City Project
- Kerala completes tender process for Palakkad Smart City infrastructure development
- Dilip Buildcon secures Palakkad Industrial Smart City contract
- Industrial Area Palakkad, Kerala — KICDC Official
- Palakkad Industrial Area Kerala — NICDC Official
- National Industrial Corridor Development Corporation (NICDC) honoured with Udyog Vikas Award