City Growth Plan
Third and Fourth Mumbai: a $100 billion push to reshape land, roads and jobs across Raigad and beyond
Chief Minister Devendra Fadnavis announced plans for a Third and a Fourth Mumbai at the World Mayors' Forum 2026 in Mumbai on 25 November 2026, with a target of attracting about $100 billion in infrastructure investment over five years. For Third Mumbai, the Karnala-Sai-Chirner (KSC) New Town in Raigad district, the announcement adds a wider investment frame to a land and planning process that is already underway.

| Announced on | 25 November 2026, at the World Mayors' Forum 2026, Mumbai |
|---|---|
| Announced by | Chief Minister Devendra Fadnavis, Government of Maharashtra |
| Investment target | About $100 billion in infrastructure investment over five years (as of 25 November 2026) |
| Mumbai Metropolitan Region figure | $50 billion, cited for the MMR within the wider plan |
| Third Mumbai area | KSC New Town: 323.44 sq km across 124 villages in Uran, Panvel and Pen talukas, Raigad district |
| Development authority | MMRDA, acting as New Town Development Authority (NTDA), notified 15 October 2024 |
| MMRDA budget 2026-27 | Rs 4,000 crore earmarked for KSC New Town |
| Master plan timeline | Land-use plan and masterplan now targeted for Q1 2027 (as of 21 August 2026) |
What the Chief Minister announced
Speaking at the World Mayors' Forum 2026, Fadnavis said cities generate about 65% of India's GDP and framed smart urbanisation as an opportunity for the state. He set a target of attracting about $100 billion in infrastructure investment over the next five years.
The plan covers three areas: a Third Mumbai and a Fourth Mumbai as new urban nodes, expansion of transport links, and redevelopment of existing urban centres. The $100 billion figure is an investment target. It is not a sanctioned budget, and no separate notification has yet been issued for the Fourth Mumbai.
Some reports put the Mumbai Metropolitan Region share at around $50 billion. Within that figure, they list more than 300 km of metro network, along with roads, flyovers, tunnels, water supply, sewage treatment and solid waste projects.
What changes for Third Mumbai and KSC New Town
Third Mumbai is the popular name for the Karnala-Sai-Chirner New Town. It spans 323.44 sq km and 124 villages in Uran, Panvel and Pen talukas of Raigad district. MMRDA, acting as the New Town Development Authority, is responsible for planning it. Of the total area, around 104 sq km is developable land. The rest is villages, forests and green areas.
The announcement describes the Third Mumbai near Navi Mumbai airport as a group of specialised cities. These are an education city, a sports city, a medi-city, an innovation city and a global capability centre city. Each is framed as a separate ecosystem for education, sports, medical services, innovation and the in-house technology and service centres of global companies.
For local residents and landowners, the most direct change is in land. Land acquisition began in March 2026. Project-affected landowners are offered options that include 22.5% of developed land back, monetary compensation, or compensation through transferable development rights or floor space.
Jobs, roads and the airport link
The Navi Mumbai International Airport began commercial operations in December 2025, and the surrounding Navi Mumbai Airport Influence Notified Area (NAINA) is the zone where most early works are taking place. On 25 October 2026, the Chief Minister and Deputy Chief Ministers Eknath Shinde and Sunetra Pawar launched development works in the zone and opened a bypass for Uran in Raigad district.
The government projects that NAINA could create about 15 lakh jobs. Of these, 5 lakh would be high-paying roles and 10 lakh basic-to-intermediate roles. Local residents are to get first access to these jobs. These are government projections, not guaranteed outcomes.
- Road and bridge links between the airport, Atal Setu and Panvel are part of the early works.
- Water supply and sewage treatment appear in the wider MMR list of projects.
- The Atal Setu (MTHL) is cited as a foundation for the new economic ecosystem.
Approvals and what comes next
The Maharashtra Cabinet approved a land acquisition and allocation policy for KSC New Town on 10 February 2026. A government resolution dated 16 March 2026 formalised it. MMRDA then opened an online consent drive for the 124 villages from 27 April 2026, and the 2026-27 MMRDA budget set aside Rs 4,000 crore for the project.
The master plan is the next major step. Earlier reporting had expected a land-use plan by the end of August 2026. Surbana Jurong Infrastructure was signed as the masterplan consultant on 7 August 2026, and the timeline has since moved to the first quarter of 2027. Village opposition has been one reason for the delay.
Land matters are still active. On 5 November 2026, Panvel MLA Prashant Thakur asked the Revenue Minister for government land for schools, health centres and playgrounds in NAINA villages, and for the long-pending expansion of the Shivkar settlement. No decision on that request has been reported.
What this means for buyers and investors
For buyers, the announcement confirms that the state is pushing this corridor as a long-term growth area, but the timing of any specific development will depend on the master plan. Until the land-use plan is published, the zoning of individual parcels will remain open.
For the wider Panvel, Khopoli and Karjat belt, the practical signals to watch are the master plan, the first allotments under the land policy, and the start of roads and utility works. The $100 billion target is best read as a policy goal that will be tested against approvals, budgets and delivery over the next five years.
Frequently asked questions
What did Fadnavis announce about Third and Fourth Mumbai?
Chief Minister Devendra Fadnavis announced plans for a Third and a Fourth Mumbai at the World Mayors' Forum 2026 in Mumbai on 25 November 2026, with a target of about $100 billion in infrastructure investment over five years.
Where is Third Mumbai located and how big is it?
Third Mumbai is the Karnala-Sai-Chirner (KSC) New Town, covering 323.44 sq km across 124 villages in Uran, Panvel and Pen talukas of Raigad district, with MMRDA acting as the New Town Development Authority.
Is the $100 billion a sanctioned budget?
No. The $100 billion is a target for attracting infrastructure investment over five years, and it has not been converted into a sanctioned budget or a new land notification in the reports announced so far.
When will the master plan for KSC New Town be ready?
The land-use plan and masterplan were earlier expected by August 2026, but the timeline has moved to the first quarter of 2027, with Surbana Jurong Infrastructure appointed as the masterplan consultant.
How many jobs are expected in the NAINA zone?
The government projects about 15 lakh jobs in the NAINA zone, including 5 lakh high-paying roles, with local residents to get first access. These are government projections.
Sources
- Fadnavis at World Mayors' Forum announces Third and Fourth Mumbai plan with $100 billion infrastructure target (NewsBytes)
- Preparations underway to build a Third and Fourth Mumbai; Fadnavis unveils $100 billion plan (The Focus India)
- New Town Development Authority (NTDA) Overview, MMRDA
- MMRDA Official: Present Status (KSC New Town)
- Karnala-Sai-Chirner New Town Unveiled As Third Mumbai By MMRDA (Free Press Journal)