CCEA Approves Zaheerabad Industrial Smart City Under National Industrial Corridor Programme

On 28 August 2024, the Cabinet Committee on Economic Affairs (CCEA) chaired by Prime Minister Narendra Modi approved the Zaheerabad Industrial Smart City in Sangareddy district, Telangana, as one of 12 new industrial nodes under the National Industrial Corridor Development Programme (NICDP), with a Phase-I outlay of Rs 2,361 crore under the Hyderabad-Nagpur Industrial Corridor (HNIC).

Zaheerabad Industrial Smart City — CCEA Approves Zaheerabad Industrial Smart City Under National Industrial Corridor Programme
Decision date28 August 2024
Approving bodyCabinet Committee on Economic Affairs (CCEA), chaired by PM Narendra Modi
Programme / CorridorNational Industrial Corridor Development Programme (NICDP) — Hyderabad-Nagpur Industrial Corridor (HNIC)
Approved Phase-I costRs 2,361 crore (NICDIT board later cited Rs 2,369 crore)
Total node area≈12,500 acres (NICDC site states 12,635 acres) across 17 villages
LocationNyalkal and Jharasangam mandals, Sangareddy district, Telangana
Phase-I activation area3,245 acres
Target sectorsAutomobile, electrical equipment, food processing, machinery & equipment, metals & non-metallic, transport equipment
Projected jobs (official estimate)≈1,74,000
Implementing SPVNICDIT Zaheerabad Industrial Smart City Limited (TGIIC 51% / NICDIT 49% equity)

What was decided

The Cabinet Committee on Economic Affairs (CCEA) chaired by Prime Minister Narendra Modi on Wednesday approved a project to establish an Industrial Smart City at Zaheerabad in Sangareddy district. The project has been proposed as part of the 12 Industrial Smart Cities which will be established as part of the National Industrial Corridor Development Programme (NICDP) with an estimated investment of Rs 28,602 crore.

The industrial smart city in Zaheerabad will be developed at a cost of Rs.2,361 crore as a part of the Hyderabad-Nagpur Industrial Corridor (HNIC). This was one of twelve simultaneous CCEA approvals that day; the CCEA greenlit the development of 12 industrial smart cities across six major industrial corridors in 10 states, with an estimated investment of Rs 28,602 crore.

Operative area, boundaries and location

The Zaheerabad Industrial Node under Hyderabad Nagpur Industrial Corridor is spread across 17 villages of Nyalkal and Jharasangam Mandals in Sangareddy district. The overall project area (Phase 1 and 2) measures approximately 12,500 acres out of which Phase-I activation area of 3,245 acres is proposed under the National Industrial Corridor Development and Implementation Trust (NICDIT) framework for a project cost of Rs.2,361 crore.

NICDC's own project page gives a marginally different total, stating that the Zaheerabad Industrial Node, spanning 12,635 acres across 17 villages in Sangareddy District, Telangana, is part of the Hyderabad-Nagpur Industrial Corridor.

On connectivity, the site is in close proximity to the 4-lane NH-65 (Pune to Machilipatnam) and is located at a distance of approximately 9 km North of Zaheerabad and about 80 km northwest of Hyderabad, and is also at a distance of approximately 65 km to the Hyderabad Outer Ring Road (ORR), approximately 48 km west of Proposed Regional Ring Road and approximately 10 km northwest of Bidar Town, Karnataka. The tap off point for gas from where the main pipeline carrying petroleum products can be diverted is at a distance of 30 km from the site at Zaheerabad and Bidar.

Land-use breakdown for Phase I (3,245 acres)

Per later state government tendering documents, of the total Phase I area, 1,900 acres will be allocated for industrial purposes, 650 acres for green zones, and the remainder for amenities, logistics, residential, and commercial infrastructure. Officials also noted that the state government has already allotted large industrial plots within the project area — Vem Technologies received 511 acres, while Hyundai was allotted 408 acres — and following these allocations, the total area for Phase I was finalised at 3,245 acres, excluding the land already allotted to these companies.

Financing structure and SPV

Implementation runs through a dedicated special purpose vehicle. TGIIC will hold a 51 percent equity stake worth ₹620.96 crore, while NICDIT will contribute 49 percent, valued at ₹596 crore, with the remaining cost met through debt financing to the SPV, NICDIT Zaheerabad Industrial Smart City Limited, which has been set up for project execution. The NICDIT board approved the proposal, with the project estimated to cost ₹2,369 crore — a figure slightly revised from the ₹2,361 crore cited at the time of CCEA approval.

Target sectors and anchor allotments

Target sectors for the Zaheerabad Industrial Smart City have been identified as automobile, electrical equipment, food processing, machinery and equipment, metals and non-metallic based industries, transport equipment.

Ahead of the formal Cabinet approval, an anchor tenant had already been secured: Rajat Saini, CEO and managing director of National Industrial Corridor Development Corporation (NICDC), said that Hyundai agreed to set up an automobile hub on 450 acres at the Zaheerabad industrial smart city in Telangana before the Cabinet approval. Telangana officials separately said the 3,245-acre industrial smart city, approved by the Centre as part of the Rs 28,602 crore NICDP, had already allotted around 500 acres to anchor clients such as Hyundai (300 acres) for its R&D facility and test track and aerospace & defence player VEM Technologies.

Background: from NIMZ (2013) to Industrial Smart City (2024)

The node is not a new site — it revives a decade-old project. The decision was taken during a Union cabinet meeting in Delhi on Wednesday, August 28, with the smart industrial city seen as a revival of the National Investment and Manufacturing Zone (NIMZ) that was established in Zaheerabad in 2013 during the earlier Congress-led UPA government, brought now under the National Industrial Corridor Development Programme. A local MP noted it was the previous Congress-led UPA government which launched NIMZ-Zaheerabad in 2013 with land acquisition and compensation completed, while the previous BRS government neglected the project from 2014 to 2024. For the first phase, 3,100 acres had already been acquired by the Telangana government, and the Shareholders' Agreement (SHA) and State Support Agreement (SSA) had also been completed by the time of CCEA approval.

Status since approval (as of July 2026)

Notification is distinct from ground-level execution. Post-approval milestones recorded in NICDC's own project monitoring reports show steady but still-in-progress implementation:

As of this writing (July 2026), the project remains under construction — foundation-stone laid and EPC works mobilising — and is not yet operational.

Practical effect

The CCEA decision converted a long-dormant, state-level NIMZ land bank into a centrally co-funded industrial node with dedicated Union equity/debt support via NICDIT, a formal SPV structure, and a defined Phase-I execution boundary. Officials said the project is estimated to generate about 1,74,000 jobs and attract investments worth Rs 10,000 crore, though later state-level briefings referenced higher figures. Telangana officials described the project as expected to attract investments worth over Rs 15,000 crore and create nearly two lakh direct and indirect jobs. For land in the notified villages, the approval means formal transfer to the project SPV and eligibility for compensation/allotment processes already underway; for investors, it means a government-backed plug-and-play industrial park with anchor tenants (Hyundai, VEM Technologies) already committed ahead of full masterplan rollout.

Development phases

Phase IApproved Aug 2024; EPC works underway as of Jan 20263,245 acres activation area, Rs 2,361–2,369 crore,~1,900 acres industrial / 650 acres green zonePhase IINot yet activatedBalance of the ≈12,500–12,635-acre total node areabeyond the Phase-I footprint

Land use

Industrial59%Green zones20%Amenities / residential /commercial / logistics21%

Frequently asked questions

What exactly did the CCEA approve on 28 August 2024?

It approved setting up the Zaheerabad Industrial Smart City as one of 12 new industrial nodes under the National Industrial Corridor Development Programme, with a Phase-I project cost of Rs 2,361 crore under the Hyderabad-Nagpur Industrial Corridor.

How much land does the Zaheerabad node cover?

The overall project area (Phase 1 and 2) is approximately 12,500 acres across 17 villages in Nyalkal and Jharasangam mandals of Sangareddy district; NICDC's project page cites 12,635 acres. Phase-I activation covers 3,245 acres.

Is the Zaheerabad Industrial Smart City operational yet?

No. As of mid-2026, the project is in construction — the Prime Minister laid the foundation stone on 10 May 2026 and the EPC contractor has held its kick-off meeting, but infrastructure and unit commissioning are still in progress.

Who is implementing the project?

A special purpose vehicle, NICDIT Zaheerabad Industrial Smart City Limited, with TGIIC holding 51% equity and NICDIT 49%, plus debt financing for the balance of the project cost.

Which industries are targeted?

Automobile, electrical equipment, food processing, machinery and equipment, metals and non-metallic based industries, and transport equipment. Hyundai and VEM Technologies are among the first major allottees.

Is this a brand-new project or a revival?

It revives the Zaheerabad National Investment and Manufacturing Zone (NIMZ), originally launched in 2013 under the UPA government, now restructured and funded under the National Industrial Corridor Development and Implementation Trust (NICDIT) framework.

Sources