SPV Incorporation Record
NICDIT Zaheerabad Industrial Smart City Limited Incorporated as Project SPV
On 14 February 2025, the Ministry of Corporate Affairs registered NICDIT Zaheerabad Industrial Smart City Limited, the project company created to build the Zaheerabad Industrial Area under the Hyderabad-Nagpur Industrial Corridor, with equity split between the Centre's NICDIT (49%) and Telangana's TGIIC (51%).

| Entity incorporated | NICDIT Zaheerabad Industrial Smart City Limited |
|---|---|
| Incorporation date | 14 February 2025 |
| CIN | U42101TS2025SGC194013 |
| Registrar | RoC-Hyderabad |
| Equity split | TGIIC 51% / NICDIT 49% |
| Authorised share capital | Rs 5,00,00,000 (paid-up Rs 1,00,000) |
| Registered office | 5-9-58/B, Basheerbagh, Parishram Bhawan, Hyderabad 500004 |
| Phase I project area | 3,245 acres |
| Phase I project cost | ~Rs 2,360-2,370 crore |
What was decided
NICDIT ZAHEERABAD INDUSTRIAL SMART CITY LIMITED was registered on 14-02-2025, with Corporate Identification Number U42101TS2025SGC194013, according to Ministry of Corporate Affairs (MCA) records. It is classified as a Non-government company and is registered under the Registrar of Companies, RoC-Hyderabad. The Special Purpose Vehicle was incorporated with equity contribution from the National Industrial Corridor Development and Implementation Trust (NICDIT) and Telangana Industrial Infrastructure Corporation Limited (TGIIC) for development of the Zaheerabad Industrial Area in Telangana.
The new Zaheerabad Industrial Area (ZIA) is managed by this SPV, in which the Centre's NICDIT holds 49 per cent equity while TGIIC owns 51 per cent. The company has an authorised share capital of INR 5,00,00,000, with INR 1,00,000 paid-up capital. Its registered/corporate office is at 5-9-58/B, 6th floor, Basheerbagh, Parishram Bhawan, Hyderabad, Telangana 500004.
Which body authorised this, and when
The SPV incorporation implements a prior Central approval. The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, approved a project to establish an Industrial Smart City at Zaheerabad in Sangareddy district as part of 12 Industrial Smart Cities under the National Industrial Corridor Development Programme (NICDP), with an estimated investment of Rs 28,602 crore. The 3,245-acre industrial smart city, approved by the Centre as part of that programme, will be developed under the overall master plan of the erstwhile Zaheerabad NIMZ at a cost of Rs 2,369.82 crore, by a special purpose vehicle in which Telangana holds 51% and the Government of India the rest.
The project, first conceived as a National Investment and Manufacturing Zone, was later incorporated into the Hyderabad-Nagpur Industrial Corridor for funding under NICDIT, and the NICDIT board approved the proposal in the year preceding the SPV's registration. Company filings show the registration itself was executed via the MCA/RoC-Hyderabad process, formally creating the legal entity that now holds and deploys the equity approved at Cabinet and NICDIT-board level.
Operative details: land, cost, and boundaries
The Zaheerabad Industrial Node under the Hyderabad-Nagpur Industrial Corridor is spread across 17 villages of Nyalkal and Jharasangam mandals of Sangareddy district; the overall project area (Phase 1 and 2) measures approximately 12,500 acres, of which a Phase-I activation area of 3,245 acres is proposed under the NICDIT framework for a project cost of Rs 2,361 crore.
Phase I of the development spans 3,245 acres in Sangareddy district, with 1,900 acres earmarked for industrial use and 650 acres allocated for green zones; the remaining land supports residential, commercial, and logistics infrastructure. TGIIC holds a 51 percent equity stake worth ₹620.96 crore, while NICDIT contributes 49 percent, valued at ₹596 crore, with the balance met through SPV debt financing.
As of the most recent land-status update, 91% of the land is under state possession, with acquisition underway for the remaining 284.48 acres. The state government has already allotted large industrial plots within the project area: Vem Technologies received 511 acres, while Hyundai was allotted 408 acres.
Practical effect: what the SPV does next
The company created on 14 February 2025 is the legal and financial vehicle that will contract, borrow, and execute infrastructure works for ZIA — it does not itself decide land use or cabinet-level funding, but implements those decisions. Within months of incorporation, it began procurement activity. NICDIT Zaheerabad Industrial Smart City Ltd. invited an RFQ-cum-RFP from interested bidders for a Programme Manager for New Cities (PMNC) for infrastructure development of the Zaheerabad Industrial Area under the HNIC project. Submissions were due at the TGIIC office on or before 3:00 PM (IST), 30/06/2025.
Officials stated tenders for infrastructure work were expected to be finalized by October (2025), with project completion targeted within 18 months of commencement. Prime Minister Narendra Modi laid the foundation stone for the project, taken up at an estimated cost of Rs 2,360.54 crore, on 10 May 2026. Officials said the project has investment potential of more than Rs 10,000 crore, generating 1.74 lakh jobs by 2029.
Corporate structure at a glance
| Item | Detail |
|---|---|
| CIN | U42101TS2025SGC194013 |
| Incorporation date | 14-02-2025 per MCA records |
| Company type | Private Limited Company, limited by shares |
| RoC | RoC-Hyderabad |
| Authorised capital | Rs 5,00,00,000 |
| Paid-up capital | Rs 1,00,000 |
| Promoters/Directors | Emmadi Vishnu Vardhan Reddy, Rohit Upadhyay, Rajeev Sharma, Pradeep Kumar Agarwal, Vedulla Madhusudan, Vinod Kumar Chinta |
Development phases
Land use
Frequently asked questions
What exactly was decided on 14 February 2025?
The Ministry of Corporate Affairs registered a new company, NICDIT Zaheerabad Industrial Smart City Limited, giving legal form to the project SPV that will build the Zaheerabad Industrial Area.
Who owns the SPV, and in what proportions?
Equity is split between Telangana's TGIIC, which holds 51%, and the Centre's NICDIT, which holds 49%, matching the structure reported when the Cabinet-approved project was greenlit.
Is this the same as the Cabinet's approval of the Zaheerabad Industrial Smart City?
No. The CCEA approved the Zaheerabad project (along with 11 other industrial smart cities) at a policy level in August 2024; the February 2025 filing is the subsequent step of legally incorporating the company that implements that approval.
How large is Phase I, and what is it for?
Phase I covers 3,245 acres, with 1,900 acres for industrial use and 650 acres for green zones; the remainder supports residential, commercial and logistics infrastructure.
What has the SPV done since incorporation?
It issued an RFQ-cum-RFP inviting bids for a Programme Manager for New Cities (PMNC) to oversee infrastructure development, with submissions due by 30 June 2025, ahead of infrastructure tenders and construction.
Has construction actually started?
As of the most recent reporting, land assembly was largely complete (about 91% in state possession, with roughly 284 acres still under acquisition) and Prime Minister Modi laid the foundation stone for the project on 10 May 2026; full construction and commissioning timelines follow from there.
Sources
- NICDIT ZAHEERABAD INDUSTRIAL SMART CITY LIMITED - IndiaFilings
- Centre, Telangana partner to build Zaheerabad smart city - Manufacturing Today India
- Nicdit Zaheerabad Industrial Smart City Limited - FileSure
- Industrial Smart City To Come Up in Zaheerabad - NICDC (Deccan Chronicle repost)
- Centre Approves Industrial Smart City at Zaheerabad - Deccan Chronicle
- Zaheerabad industrial city set to get 15K cr in investments - NICDC (ToI repost)
- RfQ-cum-RfP for PMNC, Zaheerabad Industrial Area - NICDC
- Zaheerabad Smart City Project Eyes Rs 150 Bn Investment - Construction World
- Work to Begin on ₹2,369 Crore Zaheerabad Industrial Smart City Phase I - The Realty Today
- Zaheerabad: Telangana's New Smart Industrial Powerhouse - ProjX News
- Modi to Lay Foundation Stone for Zaheerabad Industrial Smart City Project on May 10 - Deccan Chronicle
- Cabinet approves 12 Industrial nodes/cities under NICDP - PIB