Decision Record
SEIAA Uttar Pradesh Environmental Clearance for IMC Agra: Decision Record
The State Environment Impact Assessment Authority (SEIAA), Uttar Pradesh has granted Environmental Clearance for the Integrated Manufacturing Cluster (IMC) Agra project, a 1,058-acre industrial node on the Amritsar-Kolkata Industrial Corridor (AKIC). Government progress reports reviewed as of November 2025 record the clearance date as 10 March 2025, not the 7 November 2023 date carried in some earlier reporting — investors should treat 10 March 2025 as the verified date until an official corrigendum states otherwise.

| Deciding authority | State Environment Impact Assessment Authority (SEIAA), Uttar Pradesh |
|---|---|
| Environmental Clearance granted | 10 March 2025 (per NICDC/DPIIT progress reports, as of Nov 2025) |
| Project | Integrated Manufacturing Cluster (IMC) Agra, under AKIC |
| Implementing SPV | AKIC Integrated Manufacturing Cluster Agra-Prayagraj Ltd (incorporated 30 Jan 2025) |
| Land area | 1,058 acres along Agra's Inner Ring Road, Rahan Kalan |
| Corridor inclusion | NICDIT meeting, 14 July 2021 |
| Land availability confirmed | December 2022 (1,058 acres) |
| SHA/SSA (UPSIDA-NICDIT) executed | 8 November 2024 |
| Outstanding condition (as of Nov 2025) | Taj Trapezium Zone (TTZ) tree-felling permission pending before Supreme Court |
| Investment potential cited | ~₹3,400–3,447 crore; ~69,516 jobs potential |
What was decided
State Environment Impact Assessment Authority (SEIAA), Uttar Pradesh has granted Environmental Clearance on 10th March, 2025.
This clearance covers the project implemented through the AKIC Integrated Manufacturing Cluster Agra-Prayagraj Ltd SPV, which the SPV was incorporated 30th January, 2025. The clearance is a statutory pre-requisite under the EIA Notification, 2006 for the project to proceed to construction, and is separate from the earlier land-availability confirmation and the State Support Agreement/Shareholder Agreement steps.
Note on dates: An earlier editorial note referenced a clearance date of 7 November 2023. Live review of the recurring official monthly progress reports issued by the National Industrial Corridor Development Corporation (NICDC) and the Department for Promotion of Industry and Internal Trade (DPIIT) — checked across editions from June 2025 through November 2025 — consistently and repeatedly record the grant date as 10 March 2025, with no independent record found of a November 2023 grant for this specific project. This page uses the verified 10 March 2025 date and flags the discrepancy for transparency.
Background: how the project reached this stage
- 14 July 2021: IMC at Agra in the State of U.P was included for development under AKIC in the NICDIT meeting held on 14th July, 2021.
- December 2022: State Govt. in December 2022 has confirmed the availability of 1,058 Acre land for the project.
- 8 November 2024: Shareholder Agreement (SHA) between UPSIDA, and NICDIT for IMC Agra executed on 8th November, 2024, alongside a matching State Support Agreement between the Uttar Pradesh government, UPSIDA and NICDIT.
- 30 January 2025: The joint Agra-Prayagraj SPV, AKIC Integrated Manufacturing Cluster Agra-Prayagraj Ltd, SPV was incorporated 30th January, 2025.
- 10 March 2025: SEIAA Uttar Pradesh granted the Environmental Clearance.
The project sits within the broader Amritsar-Kolkata Industrial Corridor, which spans approximately 1,839 kilometers, this corridor links Punjab to West Bengal, covering seven Indian states and is aligned with the Eastern Dedicated Freight Corridor (EDFC), which acts as the corridor's backbone.
Operative details: area, location, connectivity
Officials describe the site as follows: the Agra IMC will be developed across 1,058 acres in Rahan Kalan, in Agra district. The cluster is strategically located across 1,058 acres along the city's Inner Ring Road, giving it road access to Delhi NCR and the Agra-Lucknow Expressway.
On distances, the project is strategically located just 25 km from the EDFC, 205 km from Delhi NCR, and 334 km from Lucknow, and separate reporting notes it is expected to benefit from the forthcoming Jewar Airport, which is 140 km away via the Yamuna Expressway.
Project metrics published by NICDC for IMC Agra list a Project Cost of ₹1,812 crore, an Investment Potential of ₹3,447 crore, and an Employment Potential of 69,516 jobs, based on a Project Area of 1,058 acres. As of late 2024 reporting, officials indicated that the land acquisition process is complete.
Practical effect: what the clearance does and does not unlock
The Environmental Clearance is one of the gating approvals a project needs before construction contracts can be tendered and works can begin on site. For IMC Agra specifically, however, the most recent NICDC/DPIIT progress reports (as of November 2025) show that on-the-ground works remain conditional on a separate approval: Approval for tree felling permission for Taj Trapezium Zone (TTZ) in Hon'ble Supreme Court underway, and EPC tender to be issued once TTZ issue is resolved.
The Taj Trapezium Zone is an eco-sensitive area of 10,400 sq km, spreads across Agra, Firozabad, Mathura, Hathras, and Etah districts in UP and Bharatpur district in Rajasthan to protect the world heritage Taj Mahal from environmental pollution. In parallel Supreme Court proceedings on TTZ tree felling generally, on 5th March 2025, the Supreme Court directed the Taj Trapezium Zone (TTZ) Authority to appoint the Forest Research Institute (FRI) to conduct a tree census in the zone, underlining that tree-felling clearances in this zone are handled separately from — and in addition to — the SEIAA environmental clearance process.
In practical terms for investors: the SEIAA clearance is a necessary and completed step, but as of November 2025 it had not by itself triggered EPC (engineering, procurement and construction) tendering for IMC Agra's trunk infrastructure, because of this outstanding TTZ condition.
Status as of the latest available reporting
As of November 2025, based on NICDC/DPIIT monthly progress reports:
- Environmental Clearance: granted (10 March 2025).
- SPV: incorporated (30 January 2025).
- SHA/SSA: executed (8 November 2024).
- Land: 1,058 acres confirmed available since December 2022; acquisition reported complete in late-2024 investor-facing reporting.
- EPC tender for trunk infrastructure: pending resolution of the TTZ tree-felling permission before the Supreme Court.
This is a notified/cleared status, not yet an operational (under-construction or completed) status.
Frequently asked questions
Which authority granted the Environmental Clearance for IMC Agra?
The State Environment Impact Assessment Authority (SEIAA), Uttar Pradesh. Government progress reports record that SEIAA, Uttar Pradesh has granted Environmental Clearance on 10th March, 2025.
Is the Environmental Clearance date 7 November 2023 or 10 March 2025?
Live review of the official, recurring NICDC/DPIIT monthly project status reports (checked across editions from mid-2025 through November 2025) consistently records the grant date as 10 March 2025. No independent corroboration of a 7 November 2023 clearance date for this project was found; that date should be treated as unverified pending an official correction.
How large is IMC Agra and where is it located?
The project covers 1,058 acres along Agra's Inner Ring Road in Rahan Kalan, Agra district, part of the Amritsar-Kolkata Industrial Corridor.
What is the implementing entity for IMC Agra?
The project is implemented through the SPV AKIC Integrated Manufacturing Cluster Agra-Prayagraj Ltd, which was incorporated 30 January 2025, jointly covering the Agra and Prayagraj clusters under the corridor programme.
Has construction started at IMC Agra?
Not as of the latest reviewed reporting (November 2025). Progress reports note that approval for tree-felling permission for the Taj Trapezium Zone (TTZ) is underway before the Supreme Court, and that the EPC tender for trunk infrastructure is to be issued once that issue is resolved.
Why does the Taj Trapezium Zone matter for this project?
IMC Agra falls within or near the Taj Trapezium Zone, a 10,400 sq km eco-sensitive area around the Taj Mahal spanning several UP and Rajasthan districts, where tree felling requires separate Supreme Court-supervised clearance in addition to the standard SEIAA Environmental Clearance.
What investment and jobs are projected for IMC Agra?
NICDC's project listing cites a project cost of ₹1,812 crore, an investment potential of ₹3,447 crore, and an employment potential of about 69,516 jobs across the 1,058-acre site.
Sources
- NICDC/DPIIT Progress Report – National Industrial Corridor Development Corporation (31.10.2025)
- NICDC/DPIIT Progress Report – National Industrial Corridor Development Corporation (30.11.2025)
- NICDC/DPIIT Progress Report – National Industrial Corridor Development Corporation (30.09.2025)
- IMC Agra Uttar Pradesh | NICDC
- PIB: NICDC & UPSIDA partner to develop key clusters in Agra and Prayagraj
- Investors Show Keen Interest On Agra Manufacturing Cluster – Bizz Buzz
- Investors show interest in Agra industrial hub – Bizz Buzz
- UP to set up integrated manufacturing clusters in Agra, Prayagraj – The Statesman
- Amritsar-Kolkata Industrial Corridor: A Game-Changer For India's Industrial Growth – NIC Blog
- Taj Trapezium Zone – Drishti IAS
- Supreme Court, Tree Felling, Taj Trapezium Zone – LiveLaw