New Cities India

Land acquisition

Ghaziabad Aerocity Township: Land Acquisition

GDA’s proposed Aerocity-themed township near Raj Nagar Extension is planned across 231 hectares in three villages. As of October 2026, the authority is seeking landowner consent for land pooling; no cash compensation rate has been reported for that model.

Ghaziabad Aerocity Township — Ghaziabad Aerocity Township: Land Acquisition
Proposed land area231 hectares, as reported in September 2026
Villages3: Morti, Ator and Mevla Agri, all in Ghaziabad district
Preferred land assembly modelLand pooling, subject to landowner consent
Landowner’s reported pooling share25% of developed plots corresponding to land contributed
GDA board-approved budgetAbout ₹2,813 crore for land procurement, reported May 2026
Reported cash compensation rateNo rate reported for the land-pooling proposal
Consent notice period15 days, according to September 2026 reports
Reported initial pooling consentOne landowner had submitted consent by September 19, 2026

Acquisition model and compensation

GDA’s board approved a land-procurement proposal for the township in May 2026, with land pooling identified as the preferred route. Under the reported terms, landowners who contribute land would receive 25% of developed plots; they would not receive a cash payment under that model. GDA began seeking landowner consent in September and set a 15-day period for responses.

Reports also describe direct purchase by agreement and acquisition under the Land Acquisition, Rehabilitation and Resettlement Act, 2013, as alternatives if pooling does not secure the required land. No current per-unit cash rate for direct purchase or statutory acquisition was found in the reporting reviewed. An official quoted by Hindustan Times described a hypothetical acquisition arrangement as 80% of the land cost in cash and 10% in developed plots in lieu of the remaining 20%; this was presented as a comparison with pooling, not as a published current rate for affected owners.

Villages and proposed area

The September 2026 reporting identifies three villages in Ghaziabad district: Morti, Ator and Mevla Agri. Reports describe the proposed land as approximately 231 hectares in total. The coverage reviewed does not provide a reliable village-by-village area breakdown or a separately reported count of villages by district.

Budget and reported farmer issues

In May 2026, Hindustan Times reported that GDA’s board approved about ₹2,813 crore for land procurement for the Aerocity-themed township. This is a reported approved budget, not a per-hectare compensation rate.

Farmers and landholders raised objections to the initial land identification, and an August 2026 report said GDA would conduct a further detailed survey to address objections and technical shortcomings. In September, the authority sought consent for pooling. A September 19 report said one landowner had submitted a consent letter and that GDA was seeking further consents. The reports reviewed do not establish that all affected owners consented or that the land had been fully assembled.

Current stage

As of October 2026: the project remains at the land-assembly stage. GDA has issued notices seeking consent for land pooling, and reporting records an initial consent from one landowner. The available reports do not confirm completion of pooling, payment of compensation, a concluded statutory acquisition, or commencement of township construction. GDA has said development would be phased after land is obtained; a report mentioned a possible initial phase of about 50 hectares, not a completed or formally delivered phase.

Frequently asked questions

Which villages are included in the proposed Ghaziabad Aerocity land plan?

September 2026 reports name Morti, Ator and Mevla Agri, all in Ghaziabad district.

How much land is proposed for the township?

Recent September 2026 reporting puts the identified area at about 231 hectares. The reports reviewed do not give a village-wise area split.

What compensation are landowners being offered?

Under the reported land-pooling terms, contributing landowners would receive 25% of developed plots corresponding to their contribution, rather than cash. No current cash rate was reported.

Has GDA announced a per-acre or per-hectare acquisition rate?

No current per-acre or per-hectare cash rate was found in the reporting reviewed. The reported pooling arrangement is plot-based.

What is the approved land-procurement budget?

Hindustan Times reported in May 2026 that GDA’s board approved about ₹2,813 crore for land procurement.

Has land acquisition been completed?

The latest reports reviewed describe consent-seeking and land pooling in progress, with one landowner’s consent reported in September 2026. They do not establish that land assembly is complete.

Sources

Interested in Ghaziabad Aerocity Township?

Register once — get informed when projects, plot schemes or launches open up here.