Global City Gurugram Phase 1 Reaches 80% Completion; HSIIDC Proposes Single-Window Clearance
A senior project officer confirmed that Global City Gurugram's first phase—covering roughly 570 to 587 acres and built under a Rs 9.4 billion contract awarded in 2023—has reached around 80 percent physical completion, with remaining work expected by December 2026. In parallel, the Haryana State Industrial and Infrastructure Development Corporation (HSIIDC) has proposed a single-window clearance system and common underground utility corridors to streamline approvals and services for the mixed-use township.

| Phase 1 Coverage | 570–587 acres of core infrastructure (roads, power, water, drainage, utilities) |
|---|---|
| Contract Value | Rs 9.4 billion (approximately Rs 940 crore), awarded 2023 |
| Physical Progress (as of Aug 2026) | Approximately 80% complete |
| Phase 1 Completion Target | December 2026 |
| Total Project Footprint | Approximately 1,000 acres across Sectors 36, 36B, 37, 37A, 37B |
| Development Authority | HSIIDC (100% state-owned corporation of Haryana) |
| Private Developer Interest | Signature Global, M3M India, DLF, Godrej Properties, Sobha (via e-auctions) |
| Investment Potential Pitch | Rs 1 trillion (full build-out) |
| Key Regulatory Innovation | Single-window clearance system for approvals and service connections (power, water) |
| Full Project Timeline | 2035 (Phase 1 by end-2026; subsequent phases through 2035) |
What Happened: The Construction Update
A senior officer confirmed that around 80 percent of the physical work on Global City Gurugram's first phase had been completed, with the remaining infrastructure work expected to be finished by December 2026. The HSIIDC awarded a contract worth around Rs 9.4 billion for first-phase infrastructure covering roughly 570–587 acres in 2023, covering foundational elements including roads, power substations, water and sewage networks, and utility corridors.
The August 2026 report from the construction trade press marked a major checkpoint in a project that was first floated in 2016, announced in 2019 and relaunched in 2023. The site was carved out of a larger 1,383.68-acre parcel acquired in 2006–07 and formally returned to HSIIDC in 2014 after earlier SEZ plans were abandoned.
Who Decided and What Authority Leads
The Haryana State Industrial and Infrastructure Development Corporation, a wholly state-owned corporation, is the nodal agency responsible for delivering core infrastructure such as roads, drainage, power and water networks, sewage systems and utility corridors before private construction begins. HSIIDC was incorporated on March 8, 1967, under the Companies Act with 100% equity held by the Government of Haryana, with its registered and corporate office in District Panchkula.
The project operates under a mixed-use, public-infrastructure-then-private-development model: HSIIDC develops trunk infrastructure through government funding and contractor tenders, then recovers costs and generates revenue by auctioning individual plots to private developers under a mixed land-use format.
The Numbers: Scale and Investment
The mixed-use township is being developed on roughly 1,000 acres in Sectors 36, 36B, 37, 37A and 37B along Dwarka Expressway. Phase 1 represents the foundational infrastructure layer: roads, power, water supply, and other infrastructure are to be built over 587 acres as part of the project's first phase by December 2026, at a cost of ₹940 crore.
On the broader scale, the project is positioned as the Central Business District of the NCR, carrying an investment potential of around Rs 1 lakh crore (roughly $15 billion) and projected to generate over five lakh jobs once fully operational. HSIIDC will operate and maintain the Global City until 2033, with maintenance charges to be recovered from allottees after that.
Developer Interest and Plot Auctions
The HSIIDC has conducted multiple e-auctions for mixed-use and institutional plots, with several established Gurugram developers—including Signature Global, M3M India, DLF, Godrej Properties and Sobha—showing interest or acquiring parcels. Plots have been offered in different sizes, with commercial parcels attracting significant interest because of the project's location along the Dwarka Expressway.
The Single-Window Clearance System: What Changes
The corporation has proposed a single-window clearance system and common underground utility corridors to reduce fragmentation in approvals and services. The state has proposed that industries and developers operating within Global City can access permissions and services such as power and water without approaching multiple departments separately. This administrative reform is intended to accelerate project delivery and reduce bureaucratic friction compared to older Gurugram areas.
The plan includes common underground utility corridors for cables and pipelines, dedicated bus corridors, an internal transit system and greater green cover, positioning it as a corrective to the congestion and infrastructure gaps that have long marked Gurugram's growth.
Infrastructure Features and Connectivity
The township will be connected to the Dwarka Expressway, NH-48 (Delhi-Jaipur Highway), Pataudi Road and the Kundli-Manesar-Palwal (KMP) Expressway, with the multi-route access intended to head off future traffic congestion as the project scales up.
The completed township will include a dedicated water treatment plant, a green lake and a link to the Dwarka Expressway, and a Namo Bharat Metro rapid rail line is planned to serve the area.
What Is Next: Timeline and Phases
Work on the first phase began last year and is targeted for completion by the end of 2026, with full build-out envisioned through 2035. Once Phase 1 infrastructure is operational, private developers will begin vertical construction of residential towers, office buildings, retail spaces, hospitals, schools, and hospitality zones across the allotted plots.
The project's full realization is scheduled across multiple phases through 2035, making Global City a 9–10 year development arc. Success hinges on infrastructure delivery on schedule, sustained developer confidence, and execution of the promised single-window clearance mechanism.
Development phases
Frequently asked questions
What is Global City Gurugram?
Global City is a mixed-use township being developed by HSIIDC on roughly 1,000 acres in Sectors 36, 36B, 37, 37A and 37B along Dwarka Expressway, positioned as the Central Business District of the NCR.
Who is developing Global City?
HSIIDC, a 100% state-owned agency of Haryana incorporated in 1967, has been at the forefront of developing industrial infrastructure in the state and is implementing Global City alongside other marquee projects like the KMP Expressway.
When will Phase 1 be completed?
Around 80 percent of the physical work has been completed, with the remaining infrastructure work expected to be completed by December 2026.
What is the single-window clearance system?
The state has proposed a single-window clearance system so that industries and developers operating within Global City can access permissions and services such as power and water without approaching multiple departments separately.
Which developers have invested in Global City plots?
Several established Gurugram developers, including Signature Global, M3M India, DLF, Godrej Properties and Sobha, have shown interest or acquired parcels.
What is the total investment potential?
The project is positioned as carrying an investment potential of around Rs 1 lakh crore (roughly $15 billion) and is projected to generate over five lakh jobs once fully operational.
Sources
- Gurugram Global City Project Nears Completion
- The Long Road to Gurugram's Ambitious 'City Within a City': What is the Global City Project
- CM Saini Sets Three-Month Target for Electricity, Water Supply at Gurugram Global City
- HSIIDC's Global City Project in Gurugram to Get Multi-Highway Connectivity
- Haryana Govt Begins Work on Global City Project Phase 1
- Global City Gurugram: Master Plan & Completion Date