Connectivity and transit
Global City in Gurugram: What is Planned
Global City is HSIIDC's roughly 1,000-acre mixed-use township in Sectors 36 to 37B of Gurugram, built along the Dwarka Expressway. Road links are the main connection today: the 29 km Dwarka Expressway is fully operational, and NH-48 runs next to the site. Indira Gandhi International Airport in Delhi is about 20 to 30 minutes away by road, while the internal transit loop and metro links are still at proposal or planning stage, and the Delhi-Gurugram-SNB RRTS was approved with construction targeted from August 2026. Status as of November 2026.

| Nearest airport | Indira Gandhi International Airport, Delhi, about 20 to 30 minutes by road. There is no airport inside the plan (as of November 2026). |
|---|---|
| Main road frontage | 8-lane Dwarka Expressway (Northern Peripheral Road) and Pataudi Road. The Dwarka Expressway was completed in full, 29 km, by NHAI in June 2025. |
| Other highways | NH-48 (Delhi-Jaipur Highway) runs adjacent to the site. KMP/Western Peripheral Expressway, 135.6 km, operational since November 2018, is an HSIIDC-linked project. |
| Internal transit loop | 6 km mass rapid transit (MRTS/LRT) loop with 6 stations inside Global City. Proposed; not yet under construction (as of November 2026). |
| Metro spur | 1.85 km spur to the Gurugram-Manesar-Panchgaon metro line at DPR stage (as of early 2026). A separate 1.8 km spur to Gurugram railway station was put on hold as of 24 February 2026. |
| Regional rapid rail (RRTS) | Delhi-Gurugram-SNB corridor: DPR approved; construction targeted from August 2026. |
| Phase 1 roads and utilities | 587 acres of trunk infrastructure, roads, drainage and utilities, about 80% complete as of late October 2026, with completion targeted for December 2026. |
How long does it take to reach IGI Airport?
Global City has no airport of its own. Passengers use Indira Gandhi International Airport in Delhi, which is about 20 to 30 minutes away by road. A 3.6 km, 8-lane shallow tunnel stretch on the Dwarka Expressway connects the corridor directly to Terminal 3, which is the basis for the short travel time quoted for the route.
Travel times vary with traffic and with the time of day, so the 20 to 30 minute range is a guide rather than a guarantee.
Expressways and highways
The Dwarka Expressway forms the core road frontage of the township. The NHAI completed the full 29 km route in June 2025, and it is described as the world's longest elevated urban road. The Global City frontage is served by its 8-lane carriageway and by Pataudi Road.
NH-48, the Delhi-Jaipur Highway, runs next to the site, and the Central Peripheral Road is also close by. Further out, the 135.6 km KMP (Western Peripheral) Expressway has been operational since the 83 km Kundli-Manesar section was opened by Prime Minister Narendra Modi on 19 November 2018.
Planned highway links (announced August 2026)
- Grade-separated interchange directly onto the Dwarka Expressway, with an underground link. Announced in August 2026; no completion date given in the reports.
- NH-48, through a new arterial road via Narsinghpur. Announced in August 2026.
- Pataudi Road and KMP Expressway connections through new arterial roads. Announced in August 2026.
The state says these links are meant to prevent congestion as the project grows toward full build-out.
Flyover to the Gurugram-Pataudi-Rewari Expressway
The National Highways Authority of India began building a 183-metre flyover in August 2026 to link the Dwarka Expressway with the Gurugram-Pataudi-Rewari Expressway, starting from Sector 37-D. The project has a target completion date of March 2027. The wider Gurugram-Pataudi-Rewari Expressway is 46 km long and costs Rs 900 crore. Work is under construction as of August 2026, and high-tension power line relocation had started.
Metro and internal transit
Global City does not yet have a metro station within the plan. Four separate transit items are in the pipeline, at different stages.
- Internal MRTS loop (proposed): a 6 km loop with 6 stations inside the township. Some plans describe it as a Light Rapid Transit system rather than a full metro, to be paired with electric buses and cycle tracks. It is proposed and not yet under construction.
- Metro spur to the Gurugram-Manesar-Panchgaon line (DPR stage): a 1.85 km spur planned to connect the township to the wider network. The Detailed Project Report was at its final state review as of early 2026.
- Sector 56 to Panchgaon (Manesar) line (planning stage): a separate 35.2 km corridor. It is the planned route nearest to Global City, and the DPR was under final state review as of early 2026.
- Millennium City Centre to Cyber City metro, with a spur to the Dwarka Expressway: approved by the Union Cabinet, covering 28.5 km with 27 stations at a total completion cost of Rs 5,452 crore. Civil work (piling and pillar casting) was actively progressing on the 15.2 km stretch from Millennium City Centre to Sector 101 as of early 2026.
The Union Cabinet approval and the Gurugram Metro Rail Limited project are the closest operating-stage metro plans to the site, but the spur to Global City itself has not yet reached construction.
Railway station access and the RRTS
There is no direct passenger rail connection to the plan itself. A 1.8 km metro spur to Gurugram railway station was decoupled from the main metro project and put on hold as a combined project as of 24 February 2026. Feeder buses and a skywalk are the interim plan for reaching the station.
The Delhi-Gurugram-SNB Regional Rapid Transit System corridor has its Detailed Project Report approved by the NCRTC board. Construction was targeted to start from August 2026. The RRTS is a regional, not local, service, so it is a longer-term option for travel toward Delhi and beyond rather than a daily link inside the township.
Freight and logistics links
The broader Delhi-Mumbai Industrial Corridor runs through the wider Gurugram region. Existing freight and container facilities nearby include the ICD Gurugram-Garhi Harsaru dry port and Gateway Rail Freight Limited. HSIIDC is also implementing the Integrated Multi-Modal Logistics Hub alongside Global City and the KMP Expressway. The freight links serve the wider region and are not part of the township's internal plan.
Phase 1 roads, utilities and water
Phase 1 covers 587 acres of core trunk infrastructure, including roads, drainage, power, water and utilities. It is built under a Rs 940 crore contract awarded in 2023, with a 350-million-litre water reservoir among its components.
- Progress: about 80% physical completion as of August 2026, and about 80% again as of late October 2026.
- Completion target: December 2026.
- Utilities: On 12 August 2026 the Chief Minister directed officers to prepare a three-month action plan to finish electricity and water supply at the site. HSIIDC has also proposed a single-window clearance system and common underground utility corridors.
Core road frontage on the Dwarka Expressway is built and open to traffic. The interior road network is part of the Phase 1 trunk works.
Dates to watch
- December 2026: target for Phase 1 trunk infrastructure completion.
- From August 2026: targeted start of construction for the Delhi-Gurugram-SNB RRTS.
- March 2027: target for the 183-metre flyover to the Gurugram-Pataudi-Rewari Expressway.
- 2035: full build-out target for the township.
Buyers should check the stage of each link on the official pages before relying on it, since the internal loop and metro spurs remain at proposal or DPR stage.
Development phases
Frequently asked questions
How far is Global City Gurugram from IGI Airport?
Global City is about 20 to 30 minutes by road from Indira Gandhi International Airport in Delhi. A 3.6 km, 8-lane shallow tunnel stretch on the Dwarka Expressway links the corridor to Terminal 3.
Is the Dwarka Expressway open to traffic?
Yes, the 29 km Dwarka Expressway is fully operational. The National Highways Authority of India completed the full route in June 2025.
Is there a metro station at Global City Gurugram?
No metro station is open at Global City as of November 2026. An internal 6 km transit loop is proposed, and a 1.85 km metro spur is at DPR stage.
Does Global City have a railway station?
Global City has no direct passenger rail link to the plan. A 1.8 km spur to Gurugram railway station was put on hold as of 24 February 2026, and feeder buses and a skywalk are the interim plan.
When will construction of the Delhi-Gurugram-SNB RRTS begin?
Construction of the Delhi-Gurugram-SNB RRTS was targeted to start from August 2026, after its Detailed Project Report was approved by the NCRTC board.
When will Phase 1 of Global City be complete?
Phase 1 trunk infrastructure, covering 587 acres, was about 80% complete as of late October 2026, with completion targeted for December 2026.
Sources
- About HSIIDC - Global City Gurugram
- Global City Gurugram | Welcome To The Future
- e-auction of mix-use land parcels in Global City, Gurugram - HSIIDC
- Cabinet approves Metro Connectivity from HUDA City Centre to Cyber City, Gurugram with Spur to Dwarka Expressway - PM India
- Gurugram Metro Rail Limited - Millennium City Corridor
- NCRTC Board approves DPR of Delhi-Gurugram-SNB RRTS Corridor
- HSIIDC's Global City project in Gurugram to get multi-highway connectivity - The Tribune
- Work starts on flyover linking expressways - The Tribune
- CM Saini sets three-month target for electricity, water supply at Gurugram Global City - ThePrint
- The long road to Gurugram's ambitious 'city within a city': What is the Global City project - ThePrint