Investment Outlook
Global City Gurugram: Real-Estate and Investment Outlook
Global City Gurugram is a roughly 1,000-acre mixed-use township that HSIIDC is developing in stages along the Dwarka Expressway; as of mid-2026 the project is still in the land-auction and core-infrastructure stage, with no completed, ready-to-register residential or commercial units of its own yet.

| Developer/authority | HSIIDC (Haryana State Industrial & Infrastructure Development Corporation), 100% state-owned |
|---|---|
| Location | Sectors 36, 36B, 37, 37A, 37B (extending toward 37D), Dwarka Expressway, Gurugram |
| Reported total area | ~1,000–1,002.36 acres (early 2023 press cited 1,080 acres before final notification) |
| Reported investment potential | ~₹1 lakh crore / ~$15 billion (projected, not committed capital) |
| Phase 1 scope | ~570–587 acres core infrastructure; ₹940 crore tender; targeted completion late 2026 |
| First plots invited for bids | 4 mixed-use parcels totaling 172.76 acres, registration closed Nov 20, 2023 |
| Land-acquisition litigation | 3 writ petitions filed in Punjab & Haryana High Court over the ~1,000-acre acquisition; auction postponed, 2 HSIIDC officials suspended |
| Re-auction after delay | 3 parcels totaling 142.52 acres put up for e-auction in 2025 |
| Construction progress | ~20% complete as of early 2026 (roads, drainage, a 350-million-litre reservoir) |
| Landmark proposal | 6.7-acre site earmarked (reported June 2026) for a proposed 620–700m tower |
Where the project actually stands
The Global City is a landmark mixed land use township project being developed by the Haryana State Industrial and Infrastructure Development Corporation Limited (HSIIDC), a 100% State owned Infrastructure Development agency of the Govt. of Haryana, in Gurugram. It is located over more than 1,000 acres of land spread across parts of Sectors 36, 36B, 37 and 37B of Gurugram.
Under the final development plan of the Gurgaon-Manesar Urban Complex, 2031, the state government gave in-principle approval to redesignate approximately 1,000 acres of Global City land as a special zone to be developed as a mixed land-use entity, with a provision of 300-floor area ratio. This is a notification and zoning decision, not evidence that all underlying land parcels are free of dispute or that construction on any given plot has actually started.
HSIIDC has separately identified a 6.7-acre plot within the project for a proposed 620–700 metre mixed-use tower that would dwarf India's tallest existing building, Mumbai's Palais Royale, which stands at 320 metres — but this remains a proposal under discussion with developers, not an approved or under-construction building.
What can — and cannot — legally be bought right now
At this stage, HSIIDC is not selling finished flats, built floors, or small retail plots directly to individual homebuyers inside the Global City footprint. What is being sold, in phases, is bulk land to developers and institutional bidders through e-auction.
- Can be bought (by qualifying bidders): Mixed land-use plots, with industrial parcels ranging from 5 to 100 acres, and larger mixed commercial-residential parcels sold through HSIIDC e-auctions.
- Cannot yet be bought (by retail individuals, directly from HSIIDC): Ready flats, independent floors, or small residential/commercial units within Global City itself — these will only exist once a developer wins a parcel, builds on it, and separately registers that specific project with Haryana RERA.
Individual developer projects within Global City require RERA Haryana registration, and buyers are advised to verify approvals at haryanarera.gov.in and check HSIIDC allotment authenticity before purchasing. Any listing describing itself as a "Global City plot" or "Global City floor" for direct retail sale before a developer has actually been allotted land, built the project, and obtained a RERA registration number should be treated as unverified marketing rather than a legal offer of sale.
How land is expected to be released
HSIIDC's release mechanism is competitive e-auction of large parcels, not a lottery or first-come booking for individuals.
In late 2023, HSIIDC invited bids for four mixed-use plots on its Global City project, with the four land parcels measuring 172.76 acres in total, to be auctioned for commercial and residential development within the roughly 1,000-acre township. These sit in Sectors 36B, 37A and 37B opposite the Dwarka Expressway, with registration closing on November 20, 2023 and the auction held on December 5.
Two of the parcels (86.05 and 23.76 acres) were structured for 65% commercial and 35% residential use, a 58.11-acre parcel for 50-50 commercial-residential use, and a 4.854-acre plot was reserved specifically for a school. Base rates on these plots ranged from roughly ₹1,21,000 to ₹1,47,500 per square metre for the larger commercial-residential parcels, against ₹56,500 per square metre for the institutional (school) plot.
Separately, HSIIDC awarded a contract worth a reported ₹940 crore for first-phase infrastructure — roads, electricity, water supply and more — covering an initial roughly 570 acres of land. More recent reporting places this first tranche at 587 acres with the same ₹940 crore order value and a completion target of December 2026, alongside a full build-out horizon stretching to 2035. As of early 2026, one account put construction progress at roughly 20% complete, covering roads, drainage and a large water reservoir, with relocation of high-tension power cables underground targeted for completion in the second half of 2026 — a step needed before vertical construction can proceed on the affected land. These later-stage figures come from industry commentary rather than an HSIIDC press release, so they should be treated as indicative rather than confirmed.
The auction that got delayed — and why it matters
The project's own history is itself a documented example of notification and title risk. After delay because of disputable land parcels, HSIIDC invited bids to auction three mixed-use sites for the Global City project in Gurugram. That e-auction, covering three parcels totaling 142.52 acres, was scheduled for May 19, with bidder registration closing May 1.
The auction had been postponed for months after HSIIDC realised — only after the chief minister had led a state delegation to the UAE to market the project — that the acquisition of the 1,000 acres set aside for Global City was being challenged in three separate writ petitions before the Punjab and Haryana High Court. The managing director suspended two HSIIDC officials, a general manager and a manager in charge of legal matters, for failing to disclose the litigation to the state government.
This is a concrete, documented instance of the kind of title/litigation risk that applies to greenfield government-led townships generally: land can be notified for a project while portions of it remain under active legal challenge, and marketing timelines (an overseas roadshow, in this case) can run ahead of legal due diligence.
Comparable precedent regions — what happened to values there
Global City Gurugram has no long value track record of its own yet, since its own land is only now being auctioned and built out. Two other Indian state-led greenfield/investment-region projects have a longer history and documented price data, and are useful (not predictive) comparisons.
GIFT City, Gandhinagar (Gujarat)
Flat rates in GIFT City, Gandhinagar changed by 6.6% in the last 1 year, 46.5% in the last 3 years, and 101.0% in the last 5 and 10 years, according to price-trend data compiled by a listings platform. A separate industry account puts residential price appreciation at approximately 94% over the past decade, with recent months seeing a 30–35% spike in certain apartment segments.
GIFT City's expansion also illustrates a land-cost dynamic relevant to any state-led township: of the original 1,065 acres of GIFT City, 741 acres was government wasteland with no special land-acquisition expense, whereas most of the land in the four villages earmarked for its expansion is privately held, making that acquisition cost likely to increase.
Dholera SIR (Gujarat)
Land rates in Dholera, Ahmedabad changed by 14.3% in the last 1 year, 45.5% in the last 3 years, and 77.8% in the last 5 and 10 years, per the same type of listings-platform price-trend data. Within the Dholera Special Investment Region, documented land pricing varies sharply by whether a village sits inside or outside the notified boundary: land inside SIR villages ranges from roughly ₹50–70 lakh per bigha on average, with Phase 1 villages touching ₹80–85 lakh, against ₹20–30 lakh per bigha for villages outside the SIR boundary.
The common thread in both precedents is that documented appreciation followed years after initial notification, tracked closely with actual infrastructure completion (metro, expressway, anchor tenants), and was uneven across zones — plots inside the formally notified, title-clear planning area behaved very differently from land just outside it.
Key risks
- Title and acquisition risk: Global City's own land acquisition has already been challenged in three separate writ petitions before the Punjab and Haryana High Court, showing that notified project land can still carry live legal disputes over portions of the parcel.
- Notification and master-plan change risk: The project's zoning basis rests on in-principle state approval to redesignate the land as a special mixed land-use zone with a 300-floor area ratio under the Gurgaon-Manesar Urban Complex plan — this kind of administrative approval can be revised, and the "Final Approved Layout Plan" for the whole 1,002-acre area has been described in industry commentary but should be checked directly against HSIIDC's own published plan before relying on any specific zoning split.
- Timeline slippage: The first public target of auctioning the first 250 acres by end of November 2023 was not met on schedule; the auction was postponed for months due to a blunder by HSIIDC over undisclosed litigation, and a subsequent, smaller 142.52-acre auction round followed in 2025 — well behind the original announced schedule. Phase 1 infrastructure completion has similarly moved between reported dates (October 2026 per one contractor statement, December 2026 per later commentary).
- RERA is project-specific, not project-wide: HSIIDC's own land allotment is not the same as a RERA registration. Individual developer projects within Global City require their own RERA Haryana registration before units in them can be legally marketed or sold to end buyers.
- Marketing ahead of delivery: Numerous third-party listing sites publish specific figures on Global City's job creation, green-space share, and amenity counts that do not trace to an identifiable HSIIDC source; such figures should be treated as promotional rather than confirmed.
Signals to watch
- Completion of Phase 1 core trunk infrastructure (roads, drainage, water reservoir) — reported targets cluster around October–December 2026.
- Completion of undergrounding of the high-tension power lines crossing the site, reported as a precondition for vertical construction on the affected parcels.
- Resolution of the pending Punjab and Haryana High Court writ petitions concerning the underlying land acquisition.
- Results (prices achieved, number of bidders) of the next HSIIDC e-auction rounds following the 172.76-acre (2023) and 142.52-acre (2025) rounds already held.
- The first Haryana RERA registration numbers issued for individual developer projects actually built on Global City land — this is the point at which retail buyers gain a legally enforceable, project-specific set of protections.
- Any formal confirmation or abandonment of the proposed 620–700 metre tower on the 6.7-acre site, and whether that proposal converts into an actual RERA-registered project.
- Progress on Metro Phase 5 connectivity to the Dwarka Expressway corridor, which several accounts link to the project's planned internal transit system.
Development phases
Frequently asked questions
Can I buy a plot or flat directly in Global City Gurugram today?
Not from HSIIDC directly as a retail buyer. HSIIDC sells large land parcels to developers and institutional bidders through e-auction; individual buyers will only be able to buy units once a developer has been allotted a parcel, built on it, and registered that specific project with Haryana RERA.
Is land inside Global City covered by RERA right now?
HSIIDC's land allotment itself is not a RERA registration. Individual developer projects within Global City require their own RERA Haryana registration before units in them can be legally sold, and this should be verified separately on the HRERA portal for each specific project.
Why was the original 2023 auction delayed?
HSIIDC discovered that the acquisition of the roughly 1,000 acres set aside for the project was being challenged in three separate writ petitions before the Punjab and Haryana High Court — after the state had already promoted the project abroad. Two officials were suspended over the disclosure failure, and the auction was pushed back.
What plots have actually been auctioned so far?
In late 2023, HSIIDC invited bids on four mixed-use parcels totaling 172.76 acres, with base rates of roughly ₹1,21,000–₹1,47,500 per square metre for the larger commercial-residential plots and ₹56,500 per square metre for a school plot. A further e-auction covering three parcels totaling 142.52 acres followed in 2025 after the litigation-related delay.
How does this compare to other Indian greenfield city projects?
GIFT City in Gandhinagar has documented flat-rate appreciation of about 46.5% over 3 years and 101% over 5–10 years, while Dholera SIR land rates have risen roughly 45.5% over 3 years and 77.8% over 5–10 years, according to listings-platform price-trend data. Both took years after initial notification for these gains to show, and appreciation was concentrated inside the formally notified planning boundary rather than spread evenly across the wider region.
Is the proposed India's-tallest tower in Global City confirmed?
As of the most recent reporting, HSIIDC has earmarked a 6.7-acre plot for a proposed 620–700 metre tower and held consultations with developers, but final specifications, developer selection, and construction approval had not been confirmed.
When is Phase 1 infrastructure expected to be ready?
Reported targets vary by source, clustering around October to December 2026, for roughly 570–587 acres of core roads, power, and water infrastructure under a tender reported at around ₹940 crore. Full build-out of the township is targeted for 2035.
Sources
- Global City Gurugram — official HSIIDC project site
- Global City Gurugram — Media/Contact
- Authorities of Gurugram Global City are Seeking Bids For Four Mixed-Use Plots — Axiom Landbase
- Three Gurugram Global City Sites Up for Auction After a Long Delay — Winworld Realty
- Tender for Gurugram Global City project awarded — Construction World
- Gurugram to get India's tallest building under Haryana's Global City plan — Business Standard
- India May Get Its Tallest Skyscraper In Gurugram's Global City Project — Swarajya
- Global City Gurugram: India's Vision of a World-Class Smart Township — Together Buying
- Global City Gurugram: Master Plan and Market Dynamics — Homwisor
- Property Rates and Price Trends in GIFT City, Gandhinagar — 99acres
- GIFT City Property Investment 2026: High ROI & Rapid Appreciation Explained
- Is GIFT City Real Estate a Good Investment in 2026? Returns, Risks & Future Growth Explained
- Is GIFT City a Good Real Estate Investment in 2026? — Vitalspace
- Land prices to go down as surrounding area of GIFT now under GUDA's jurisdiction — Gujarat Samachar
- Property Rates and Price Trends in Dholera, Ahmedabad — 99acres
- Dholera Village Wise Land Price 2026 — TP vs Non-TP Rates