New Cities India

Board Decision

GDA Board Vets Harnandipuram Township Map (August 2024)

On August 5, 2024, the Ghaziabad Development Authority (GDA) Board vetted the map for a new township named Harnandipuram, also called Naya Ghaziabad, to be built on land acquired from farmers across eight villages near the Delhi-Meerut Road and RRTS corridor. The same meeting also cleared a revised Wave City project report and approved a plan to sell a long-stalled Indirapuram-extension land parcel as smaller plots.

Harnandipuram Township (Naya Ghaziabad) — GDA Board Vets Harnandipuram Township Map (August 2024)
Decision dateAugust 5, 2024 (Monday GDA Board meeting)
Approving bodyGhaziabad Development Authority (GDA) Board
Township area (as reported)Around 520 hectares (~1,300 acres) — media reports; some listings cite 521 hectares
BoundariesPipeline Road (north), Northern Peripheral Road (east), Morta (south); Hindon river flows through parts
Villages named for land acquisitionMathurapur, Nagla Firoz, Mohanpur, Shamsher, Champat Nagar, Bhenda Khurd, Shahpur Morta, Morta, Bhowpur (press accounts list up to 10 names, including Atour)
Estimated acquisition costAround Rs 5,000 crore, to be shared equally by the UP state government and GDA
Same-meeting decision: Wave CityRevised DPR of 3,786.8 acres cleared, enabling registries/allotments for ~12,000 people
Same-meeting decision: Indirapuram extension116 plots to be carved from a 3-lakh-sqm parcel after 26 failed auction rounds
Governing schemeCM Urban Expansion New City Promotion Scheme ('Naya Ghaziabad')

What the Board Decided

At a board meeting held on a Monday (August 5, 2024), the GDA Board vetted the township map for a new project named Harnandipuram. The map of the new township was vetted at the GDA Board's meeting, and it was described as spanning from Pipeline Road in the north of the city to Northern Peripheral Road in the east and Morti in the south, with the Hindon river flowing by certain parts of the township, according to GDA secretary Rajesh Kumar Singh.

Approval of the map by the Board was described as a step preceding formal government sign-off. If approved by the government, this would be the first township that GDA builds since Madhuban Bapudham around 15 years ago.

Area and Boundaries

Reported figures for the township's size vary slightly by source. With some parts of the township off the Hindon, 'Harnandipuram' was reported to come up on around 1,300 acres — almost the size of Indirapuram. Later coverage converted this to metric terms: the Harnandipuram township will cover an area of around 520 hectares, nearly equal to Indirapuram, stretching from Pipeline Road in the north to Northern Peripheral Road in the east and Morta in the south, with the Hindon River flowing through certain parts.

A later breakdown of the land base indicated: the project covers 520 hectares, with 462 hectares to be procured directly from farmers to speed up the land acquisition process, around 11 hectares already owned by the GDA, and the rest to be sourced from gram sabhas.

Land Acquisition Across the Named Villages

Per the brief and GDA's own statements, the township requires acquiring farmland across eight named villages — Mathurapur, Nagla Firoz, Mohanpur, Shamsher, Champat Nagar, Bhenda Khurd, Shahpur Morta, Morta and Bhowpur. Contemporary press quotes from GDA secretary Rajesh Kumar Singh listed a similar but slightly longer set of village names: 'Land will have to be acquired from farmers first. According to our plan, we have to undertake the acquisition process in villages such as Nagla Ferozepur, Mohanpur, Morta, Bhowpur, Atour, Champat Nagar, Shamsher, Bhenda Khurd, Mathurapur and Shapur Morta,' Singh said.

The estimated cost of acquisition was reported as a shared state-authority expense. The land acquisition process is likely to cost around Rs 5,000 crore, with the state government and GDA sharing the cost equally. A committee was set up to fix rates: a committee comprising GDA and district administration officials was formed to determine the market rate for land purchases, reviewing recent sale deeds and identifying encumbrance-free land to finalise rates.

Other Decisions Cleared at the Same Board Meeting

Practical Effect and Status Since the Decision

The August 5 board vetting was a preparatory step, not a final launch. Following this, on September 23, 2024, the development authority announced the future course of the project, with Phase 1 work to begin by 2025.

By late 2025/early 2026, GDA had moved into the land-acquisition and DPR stage rather than a public scheme launch. GDA appointed a professional consulting agency to prepare the Detailed Project Report and overall layout of the township, with first-phase planning work focused on nearly 100 hectares of land. Separate coverage similarly noted Phase 1 development has been linked to about 336 hectares of land, with a budget allocation of ₹400 crore from the state government for initial development and acquisition support.

As of early 2026, official brochures and confirmed plot pricing had not yet been issued; industry commentary described the project as currently in the land acquisition phase, expected to launch around late 2026 or 2027. No RERA registration number, final layout plan, or confirmed price list had been located in current reporting — investors should treat any third-party pricing or 'GDA-approved' plot claims circulating online as unverified until GDA issues an official brochure.

Frequently asked questions

What exactly did the GDA Board approve on August 5, 2024?

It vetted (reviewed and cleared) the proposed map for the Harnandipuram township, covering land near the Delhi-Meerut Road/RRTS corridor. The same meeting also cleared a revised Wave City project report and a plan to sell a stalled Indirapuram-extension land parcel as smaller plots.

Is Harnandipuram the same as 'Naya Ghaziabad'?

Yes. Harnandipuram is the name given to the township developed under the state government's 'Naya Ghaziabad' plan, which itself falls under the CM Urban Expansion New City Promotion Scheme.

How big is the township and where is it located?

Reports put the area at roughly 520 hectares (about 1,300 acres), running from Pipeline Road in the north to Northern Peripheral Road in the east and Morta in the south, with the Hindon river passing through parts of the site.

Which villages are losing land to the project?

Per the notified plan, land is being acquired across eight villages — Mathurapur, Nagla Firoz, Mohanpur, Shamsher, Champat Nagar, Bhenda Khurd, Shahpur Morta, Morta and Bhowpur — though some early press reports also named a village called Atour in this list.

Has the township actually launched or is land acquisition still ongoing?

As of the most recent reporting, GDA was still in the land-acquisition and Detailed Project Report (DPR) stage, with Phase 1 planning focused on roughly 100 hectares; no official launch brochure or confirmed plot prices had been issued yet.

What else was decided at the same board meeting?

The Board cleared a revised Wave City DPR of 3,786.8 acres (benefiting around 12,000 plot holders/investors), approved selling a 3-lakh-sqm stalled Indirapuram-extension parcel as 116 smaller plots after 26 failed auctions, and froze rates on GDA's unsold flat inventory.

Sources

Interested in Harnandipuram Township (Naya Ghaziabad)?

Register once — get informed when projects, plot schemes or launches open up here.