Harnandipuram Scheme Advances as GDA Secures Farmers' Consent

The Ghaziabad Development Authority has executed sale deeds for about 202 hectares for the Harnandipuram (Naya Ghaziabad) township and has farmers' consent for roughly 100 more hectares. The authority says purchases now cover about 42 per cent of the proposed area, and it is buying land by mutual agreement rather than compulsory acquisition.

Harnandipuram Township (Naya Ghaziabad) — Harnandipuram Scheme Advances as GDA Secures Farmers' Consent
AuthorityGhaziabad Development Authority (GDA)
Proposed scheme area (this report)About 501 hectares; earlier reports cite about 521 hectares
Sale deeds executed in favour of GDA202.3455 hectares (about 500 acres)
Farmers' consent for further landAbout 100 hectares; sale-deed execution underway
Share of proposed area secured by sale deedsAbout 42 per cent (as reported, November 2026)
Acquisition methodMutual consent with landowners
State seed capital₹943.37 crore, approved by Government Order dated 31 July 2026
Farmer compensationFour times the circle rate for rural land, two times for urban clusters, plus 10 per cent of developed plots

What has happened

The Ghaziabad Development Authority reports that sale deeds covering about 202 hectares have been executed in its favour for the Harnandipuram scheme. Farmers have also agreed to sell roughly 100 more hectares, and the deed-execution process for that land is under way.

The authority says these purchases account for about 42 per cent of the proposed area. Once the pending deeds are completed, the land available for development will rise further, which officials say will make planning for later phases easier.

Who decided, and on what basis

The purchases follow a shift in approach. In October 2026, the Allahabad High Court directed the GDA to assemble the township land only through negotiated agreements with landowners. The authority has since said it is continuing to buy land by mutual consent rather than through compulsory acquisition.

The compensation terms were set by the GDA Board. Farmers receive four times the circle rate for rural land and two times for urban clusters, along with a 10 per cent share of developed plots under the approved package.

What this changes

Harnandipuram is planned as a township of about 501 hectares across eight villages: Mathurapur, Shamsher, Champat Nagar, Bhaneda Khurd, Nagla Firoz Mohanpur, Bhovapur, Shahpur Nij Morta and Morta. Earlier reports cited about 521 hectares for the same scheme. The site lies near Raj Nagar Extension on the northern edge of Ghaziabad, close to the Delhi-Meerut Road and the RRTS corridor.

The state government approved ₹943.37 crore in seed capital under the Chief Minister Urban Expansion / New City Promotion Scheme. The overall project cost has been reported at about ₹5,000 crore, shared equally between the state government and the GDA, although later reports give a higher overall development estimate.

Where the plan stands and what comes next

As of November 2026, the scheme is still at the land-assembly and planning stage. The GDA Board approved the layout for the first phase, an area of about 336 hectares, at its 174th meeting, reported on 24 September 2026. A RERA registration application for the first phase has been filed.

Phase 1 planning covers about 5,000 residential units across the township, with plots, group housing, commercial and recreational components in the wider plan.

Development phases

Phase 1Launch targeted October 2026About 336 hectares; layout approved by GDA Board; RERAapplication filedLater phasesDependent on further land deedsDevelopment to follow as additional land is secured bysale deed

Frequently asked questions

How much land has the Ghaziabad Development Authority secured for Harnandipuram?

Sale deeds covering about 202 hectares have been executed in favour of the GDA. Farmers have also consented to about 100 more hectares, and those deeds are in progress. The authority says this represents about 42 per cent of the proposed area.

Is the GDA using compulsory acquisition for Harnandipuram?

The GDA says it is buying land through mutual consent with farmers. This follows a directive from the Allahabad High Court in October 2026 to acquire the township land only through negotiated agreements.

What compensation are farmers receiving?

Under the approved package, farmers receive four times the circle rate for rural land and two times for urban clusters. They also receive 10 per cent of developed plots.

How big is the Harnandipuram township?

The scheme is about 501 hectares in this report, while earlier reports cited about 521 hectares. It covers eight villages near Raj Nagar Extension in Ghaziabad.

When will Harnandipuram Phase 1 launch?

Officials targeted an October 2026 launch. The RERA registration application has been filed, and the launch is tied to receiving the RERA registration number.