Decision Record
YEIDA Finalises Detailed Project Report for Heritage City (Raya) — January 29, 2024
On January 29, 2024, the Yamuna Expressway Industrial Development Authority (YEIDA) finalised the Detailed Project Report for the Heritage City project in the Raya Urban Centre near Mathura, setting out a Rs 1,220-crore, three-phase build-out over 750 acres, and forwarded the report to the Uttar Pradesh government for approval before construction could begin.

| Decision date | January 29, 2024 |
|---|---|
| Deciding body | YEIDA (Yamuna Expressway Industrial Development Authority) |
| What was decided | Finalisation of the Detailed Project Report (DPR) for Heritage City |
| Land area (as decided) | 750 acres (later cited as 753/735 acres in subsequent revisions) |
| Budget (as decided) | Rs 1,220 crore |
| Phasing | Phase I by 2027; Phase II 2028–31; Phase III by 2034 |
| Location | Raya Urban Centre, near Banke Bihari Temple, Mathura, along Yamuna Expressway (near 101 km mark) |
| Next step required | Uttar Pradesh government approval before construction start |
| Consultant | CBRE South Asia Pvt Ltd (DPR preparation) |
What was decided
On January 29, the Yamuna Expressway Industrial Development Authority (YEIDA) finalised the detailed project report (DPR) to develop the heritage city project along the Yamuna Expressway, with a budget of Rs 1,220 crore allocated for its construction in three phases by 2034 near Banke Bihari Temple, Mathura. The plan covers 750 acres of land in the Raya Urban Center of Mathura.
YEIDA gave the green light to the revised DPR, and the report was sent to the Uttar Pradesh government for final approval. After approval, the committee was to determine the development approach for the project.
Operative details: phasing, budget and site
The Heritage City project was planned for development in three phases: the first phase to open by 2027, phase II across 2028-31, and phase III proposed to open by 2034. The site sits near the 101-km milestone of the Yamuna Expressway and was to be connected to the Banke Bihari temple by a 6.9 km expressway.
At the time of the DPR finalisation, the project was planned as a public-private partnership (PPP) model. Planned facilities included luxury and budget hotels, parks, convention centres, old age homes, service apartments, and a marketplace for local arts and crafts.
Two execution options placed before the Authority
The consultant proposed two development options to the Authority: under the first, the entire 750-acre parcel would be allocated to a single developer who would build the project in phases per the approved plan. Under the second option, the land would be divided among multiple companies, each responsible for specific components such as hospitality, public facilities, healthcare and recreational areas.
Practical effect of the January 2024 decision
Finalising the DPR meant the report was sent to the Uttar Pradesh government for final approval before construction could start — the DPR finalisation was an internal authority sign-off, not a construction go-ahead. No land had been acquired and no developer selected at this stage.
How the project changed after January 2024 (status as of July 2026)
The DPR and its numbers were revised multiple times after the January 2024 finalisation. The DPR was amended several times due to encroachment on land and requirements of the National Highways Authority of India (NHAI).
In November 2024, reports indicated the state government had cleared a revised DPR: officials said that with the government's approval of the Detailed Project Report on that Monday, development plans would proceed, and the CEO stated the DPR of Raya Heritage City had been approved by the government. That version covered 735 acres within the Yamuna Authority's notified area.
By mid/late-2025 the project's footprint, cost and delivery model had shifted further. One October 2025 report put the scheme at around 753 acres with a project cost of ₹7,200 crore, while a separate account from the same period cited 753 acres at an estimated cost of Rs 950 crore under a hybrid delivery model. YEIDA moved toward a hybrid model combining direct government-led development with public-private partnership (PPP) components, reversing the earlier single-developer, Film-City-style approach. Initially YEIDA had proposed executing Heritage City on the lines of the Film City project with a single private developer over a 10-year period, but the Authority later revised the concept after assessing financial risk and feasibility.
Land-acquisition activity has since begun in specific villages: acquisition efforts focused on villages including Arua Khadar, Bhim Khadar, Dangoli Khadar, Pani Village Khadar, Piproli Khadar, Jehangirpur, Begumpur Khadar and Jehangirpur Khadar, with land being purchased directly from farmers rather than through the traditional acquisition system, and an office set up in Mathura to oversee the process. A connecting expressway alignment to Vrindavan was also under review: the originally curved road alignment was straightened to avoid low-lying, flood-prone areas after waterlogging incidents during the monsoon.
What this means for investors and locals
The January 29, 2024 DPR finalisation was a planning milestone, not a construction or land-acquisition trigger. Figures quoted publicly for Heritage City — acreage (750/753/735), budget (Rs 1,220 crore / Rs 950 crore / Rs 7,200 crore) and delivery model (single developer vs PPP vs hybrid) — have all changed across successive board and consultant reviews. Anyone tracking this project should treat each figure as tied to a specific date and source, not as a fixed final plan, and should watch for confirmed UP government approval orders, board resolutions, and RERA registration (none of which were located as final, dated approvals as of the research for this record) before treating the project as construction-ready.
Development phases
Frequently asked questions
What exactly did YEIDA decide on January 29, 2024?
YEIDA finalised the Detailed Project Report for Heritage City — the technical and financial plan for the 750-acre project in Raya Urban Centre — and forwarded it to the Uttar Pradesh government for final approval before construction could begin.
Did the January 2024 decision approve construction?
No. Finalising a DPR is an internal planning sign-off. The report still needed Uttar Pradesh government approval, and further steps such as land acquisition and developer selection followed later.
What was the budget and area named in the January 2024 DPR?
The DPR set a budget of roughly Rs 1,220 crore for construction across three phases through 2034, covering 750 acres in the Raya Urban Centre near the Banke Bihari Temple in Mathura.
Have the area and cost figures changed since January 2024?
Yes. Later reports (2024–2025) cite figures ranging from 735 to 753 acres and project costs from Rs 950 crore to Rs 7,200 crore, reflecting revised DPRs, delivery-model changes, and consultant reassessments over time.
Who prepared the DPR that YEIDA finalised?
The Detailed Project Report was prepared by consultant CBRE South Asia Pvt Ltd, which has continued to revise the plan through subsequent board reviews.
Is land acquisition underway for Heritage City?
As of mid-2025 reporting, YEIDA had begun purchasing land directly from farmers in specific villages including Arua Khadar and Bhim Khadar, as part of a later phase of the project, separate from the original January 2024 DPR decision.
Sources
- 753 Acre Heritage City Project along Yamuna Expressway: Budget, Opening Date & Latest News — 99acres
- YEIDA to Develop Residential and Commercial Clusters in ₹7,200-Crore Heritage City Project at Raya — The Realty Today
- YEIDA To Build Heritage City In Mathura; New Route For Banke Bihari Temple Planned — Daily Jagran
- Heritage City — YEIDA Official Website
- New 'Heritage City' inspired by Vietnam and Korea to be developed in Gr Noida — Millennium Post
- YEIDA Initiates Land Acquisition for Heritage City Project in Mathura — OB News
- YEIDA Kicks Off Land Acquisition Process For Heritage City Project In Mathura District — News24
- Master Plan 2041 For Yamuna Expressway Areas Approved by Uttar Pradesh Government — InvestoXpert