City Growth News
Kadapa's Kopparthy Industrial Smart City Moves Toward Land, Roads and Jobs
NICDC presented Kopparthy Industrial Smart City, a 2,596-acre greenfield industrial township in Kadapa district, at the 31st CII Partnership Summit in Visakhapatnam in November 2026. Built under the Visakhapatnam-Chennai Industrial Corridor and implemented by APICDC, the township is under construction, with ₹8,860 crore investment potential and a job target of 54,500 as of November 2026.

| Location | Kopparthy and Tadigotla villages, Chintakommadinne mandal, YSR Kadapa district, Andhra Pradesh |
|---|---|
| Notified area (Phase 1) | 2,596 acres (1,050.45 hectares) |
| Project cost (trunk infrastructure) | ₹2,137 crore |
| Investment potential | ₹8,860 crore (as of November 2026) |
| Job target | 54,500 jobs |
| Physical progress | Around 12% completion (as of November 2026) |
| Implementing company | AP Industrial Corridors Infrastructure Development Corporation Ltd (APICDC), a 50:50 joint venture of the Government of India and the Government of Andhra Pradesh |
| Status | Under Construction (as of November 2026) |
What NICDC showed at the summit
NICDC, the National Industrial Corridor Development Corporation, took part in the 31st CII Partnership Summit held at Visakhapatnam on 12 and 13 November 2026. Through its pavilion, it presented three Greenfield Industrial Smart City nodes in Andhra Pradesh: Krishnapatnam, Orvakal and Kopparthy. Kopparthy is the node in Kadapa district.
For the three nodes together, the showcase cited about ₹31,360 crore of investment potential and about 2 lakh jobs. Physical progress was presented node by node: Krishnapatnam was reported above 50 per cent, Orvakal at about 30 per cent, and Kopparthy at around 12 per cent as of November 2026. The Kopparthy-specific figures of ₹8,860 crore and 54,500 jobs match the numbers on NICDC's own project page for the node.
The summit coverage is a useful snapshot of where the node stands. It is still early in construction, so the investment and job numbers describe the planned end state rather than activity already on the ground.
What changes for Kadapa: land and industry
The Kopparthy node covers 2,596 acres in the Kopparthy and Tadigotla villages. Of this, about 1,213.47 acres are saleable industrial area under the revised master plan that APICDC's board approved on 12 June 2026, along with the allotment pricing for the three nodes. The proposed allotment rate for industrial land is ₹1.25 crore per acre.
Several companies have already moved into the wider Kopparthy area. On 10 January 2026, the Andhra Pradesh Industries and Commerce Department issued G.O. Ms. No. 16, formalising the state Cabinet's approval to allot 466.35 acres at the Kopparthy Mega Industrial Hub to Shirdi Sai Electricals Limited. The company plans a greenfield electrical-equipment manufacturing complex with fixed capital investment of about ₹4,864 crore.
JSW Group's steel project in the Kadapa district is also relevant. Chief Minister N. Chandrababu Naidu and JSW Group Chairman Sajjan Jindal launched construction on 3 July 2026 at Sunnapurallapalli and Peddadanluru villages in Jammalamadugu mandal. The integrated steel plant will sit on 1,100 acres with a total investment of ₹16,350 crore across two phases. A proposed IT cluster and electronics ecosystem for Kopparthy has been announced alongside it.
Roads and logistics links
On 19 September 2026, Union Minister for Road Transport and Highways Nitin Gadkari announced the Centre's approval of a road connecting the Kopparthy Industrial Area with the Kadapa Bypass, with an allocation of ₹304.44 crore. Andhra Pradesh Deputy Chief Minister Pawan Kalyan welcomed the allocation the same day. For a township that depends on freight and workforce movement, a direct link to the bypass is among the most practical steps for the city.
A multimodal logistics park is proposed about 9 km from the Kopparthy node under the PM Gati Shakti scheme. If built, it would connect the township to rail, road and cargo handling in one location. The node sits on the Visakhapatnam-Chennai Industrial Corridor, which links Andhra Pradesh's ports and industrial zones to the wider national network.
How the node reached this stage
- 28 August 2024: The Cabinet Committee on Economic Affairs, chaired by PM Narendra Modi, approved Kopparthy as one of 12 new industrial nodes under the National Industrial Corridor Development Programme, with about 2,596 acres and a central project cost of about ₹2,137 crore.
- 12 August 2024: APIIC's environmental-clearance records show Environmental Clearance accorded for the 1,050.45-hectare (2, 595.74-acre) industrial park at Kopparthy.
- 16 October 2025: PM Narendra Modi laid the foundation stone for Kopparthy Industrial Area in Kadapa, together with the Orvakal Industrial Area in Kurnool. The two parks were presented with a combined investment of over ₹4,920 crore.
- 9 October 2025: An EPC contract was awarded to a joint venture of BSR Infratech India Ltd and Star Infratech.
- 31 October 2025: About 2,400 acres, or 92 per cent of the land proposed by the state, was under state possession, with an initial tranche of 878 acres transferred to the implementing company.
What comes next
The next phase of the Kopparthy node is physical build-out. Progress stood at around 12 per cent in November 2026, so trunk infrastructure, roads and utilities will carry the next stretch of work. The road to the Kadapa Bypass, the proposed logistics park and the planned IT and electronics cluster are the steps most likely to shape how the township develops.
For investors and local residents, the practical signals to follow are allotments under the revised master plan, the progress of the bypass road, and whether the anchor projects in the area, including the Shirdi Sai Electricals complex and the JSW steel plant, move from approval to production. The JSW steel plant has set its first-phase commercial production target for 2028–29 and its second-phase 2 MTPA capacity target for 2034.
Frequently asked questions
Where is Kopparthy Industrial Smart City located?
Kopparthy Industrial Smart City sits on 2,596 acres across Kopparthy and Tadigotla villages in Chintakommadinne mandal, YSR Kadapa district, Andhra Pradesh.
Who is developing Kopparthy IMC?
Kopparthy IMC is being developed by APICDC, the AP Industrial Corridors Infrastructure Development Corporation Ltd, a 50:50 joint venture of the Government of India and the Government of Andhra Pradesh.
How much investment and how many jobs is Kopparthy expected to bring?
Kopparthy Industrial Smart City has a projected investment potential of ₹8,860 crore and a job target of 54,500, according to NICDC's figures for the node as of November 2026.
How far along is Kadapa Industrial City?
Kadapa Industrial City, as the Kopparthy node is also searched, was at around 12 per cent physical completion as of November 2026, with the status listed as under construction.
What road links are planned for the Kopparthy node?
The Centre has approved a road connecting the Kopparthy Industrial Area with the Kadapa Bypass, with an allocation of ₹304.44 crore announced on 19 September 2026.
Sources
- Kopparthy Andhra Pradesh – NICDC project page
- Kopparthy Industrial Area – APICDC
- Environmental Clearance for Kopparthy Industrial Park – APIIC
- PM lays the foundation stone, inaugurates and dedicates development projects worth Rs 13,430 crore in Kurnool, Andhra Pradesh – PMO
- Cabinet approves 12 industrial smart cities worth Rs 28,602 cr – Business Standard
- NICDC showcases Andhra Pradesh industrial smart city nodes at CII Partnership Summit 2026 – Indian Masterminds
- Pawan Kalyan thanks Centre for Rs 304 crore Kopparthy–Kadapa Bypass road – Deccan Chronicle
- JSW Steel starts construction of ₹16,350-crore Andhra Pradesh steel project – Business Standard