New Cities India

Land Acquisition

Kopparthy Industrial Smart City: Land Acquisition, Compensation and Stage

Kopparthy Industrial Smart City, also searched as Kopparthy IMC or Kadapa Industrial City, is a National Industrial Corridor Development Corporation (NICDC) project on about 2,595.74 acres at Kopparthy and Tadigotla villages in Chinthakommadinne mandal, YSR Kadapa district, Andhra Pradesh. Most of the core site was already in state government possession, so the project has moved through land consolidation rather than a large farmer compensation drive, and no Kopparthy-specific compensation rate has been announced as of November 2026.

Kopparthy Industrial Smart City — Kopparthy Industrial Smart City: Land Acquisition, Compensation and Stage
Core site area2,595.74 acres (1,050.45 ha), proposed by the Andhra Pradesh government for Phase 1
Full node area5,760 acres identified for the Kopparthy Node (NICDC)
Land in state possessionAbout 2,400 acres, or 92% of the core site, as of 31 January 2026 (NICDC monitoring report)
Acquisition modelConsolidation of government and APIIC land; separately owned balance of 199.59 acres
Compensation rateNo Kopparthy-specific per-acre rate announced as of November 2026
Central project costRs 2,137 crore (also reported as Rs 2,136 crore), approved August 2024
Villages and mandalKopparthy and Tadigotla, Chinthakommadinne mandal, YSR Kadapa district
Current stageFoundation stone laid 16 October 2025; road link of Rs 304.44 crore approved September 2026 (as of November 2026)

How the land is being assembled

The Kopparthy site was largely government-held before the project was formally taken up. Environmental-clearance filings show that 2,396.15 acres were already in the possession of APIIC, the state industrial infrastructure agency, and the remaining 199.59 acres were separately owned.

The NICDC monitoring report dated 31 January 2026 confirms the same pattern. Around 2,400 acres, or 92% of the 2,595 acres proposed by the state, were under state possession, and a consultant for detailed master planning and preliminary engineering was appointed for the 5,760-acre Kopparthy Node.

Land has also been moved into the implementing company. An initial tranche of 878 acres was transferred to the special purpose vehicle, AP Industrial Corridor Infrastructure Development Corporation (APICDC), with the state contributing Rs 300 crore as matching equity. These figures are as of 31 October 2025, from the NICDC status update.

Under the Visakhapatnam-Chennai Industrial Corridor, the master plan was notified on 11 September 2025, with 53% of the notified land designated for industrial use.

What compensation has been paid or announced

No per-acre compensation rate has been announced for Kopparthy, and no Collector's award figure for the site has been published as of November 2026. The reported record shows government possession and allotments, not a negotiated farmer payment schedule.

For any private parcels that still need to be taken over, the national framework is the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act). Under it, owners of private land are compensated at up to four times market value in rural areas and twice market value in urban areas, including a 100% solatium. No Kopparthy-specific order applying these multipliers has been reported.

Compensation figures will be added if Collector awards or gazette notifications for Kopparthy villages are published.

Villages and mandals covered

All identified core-site land falls in a single district, YSR Kadapa, and mainly in one mandal. The core site is recorded as Kopparthy and Tadigotla villages in Chinthakommadinne mandal.

Districts covered: one (YSR Kadapa).

Budget and funding

The Union Cabinet approved Kopparthy as one of 12 new industrial nodes under the National Industrial Corridor Development Programme on 28 August 2024. The central project cost is Rs 2,137 crore, also reported as Rs 2,136 crore, and the project is expected to attract Rs 8,860 crore of investment and about 54,500 jobs.

A road connecting the Kopparthy Industrial Area with the Kadapa Bypass was approved in September 2026, with Rs 304.44 crore allocated by the Union Ministry of Road Transport and Highways.

The Rs 28,602 crore figure covers all 12 approved projects together, including Orvakal and the Nakkapalli pharma cluster, and should not be read as Kopparthy's budget alone.

Land already allotted to companies

On 10 January 2026, the state Industries and Commerce Department issued G.O. Ms. No. 16 formalising the allotment of 466.35 acres at the Kopparthy Mega Industrial Hub to Shirdi Sai Electricals Limited. The concessional land rate is Rs 8 lakh per acre. The company had asked for 540 acres, but the allotment was reduced because of site constraints. The company plans a greenfield electrical-equipment complex with a fixed capital investment of Rs 4,864 crore.

Separately, JSW Steel began construction of a Rs 16,350 crore integrated steel plant on 3 July 2026 in Jammalamadugu mandal, about 1,100 acres at Rs 5 lakh per acre. A proposed IT cluster and electronics ecosystem is planned for Kopparthy, but that plan has not been tied to a land allotment in the reporting so far.

Farmer negotiations and disputes

No separate farmer negotiation or compensation exercise specific to the Kopparthy site has been reported. Land assembly has been handled through state possession and allotments.

Elsewhere in YSR Kadapa, the Kadapa District Collector cancelled a 2007 allotment to Brahmani Industries in July 2026 and took back nearly 14,000 acres at Ambavaram in Jammalamadugu mandal. This is a separate parcel from Kopparthy, and it has been added to the district's government land bank.

Wider YSR Kadapa land bank

The state industrial infrastructure agency reports 11,528.17 acres already acquired for industrial parks and other uses across YSR Kadapa district. A further 46,104.35 acres have been identified, with requisition filed for 27,823.43 acres for the land bank. These district-wide figures cover all industrial estates in the district, not Kopparthy alone.

Current stage as of November 2026

The project has moved through the following steps:

  1. 12 August 2024: environmental clearance recorded for the 1,050.45-hectare industrial park.
  2. 28 August 2024: Union Cabinet approval under the national programme.
  3. 11 September 2025: master plan notified.
  4. 9 October 2025: engineering, procurement and construction contract awarded to a joint venture of BSR Infratech India Ltd and Star Infratech.
  5. 16 October 2025: foundation stone laid by Prime Minister Narendra Modi.
  6. 10 January 2026: allotment order for 466.35 acres to Shirdi Sai Electricals.
  7. 31 January 2026: NICDC monitoring report records about 92% of the core site in state possession.
  8. 19 September 2026: road link of Rs 304.44 crore announced.

The site is in the post-clearance phase: land is in state hands, the master plan is notified, and the main construction contracts are in place. Compensation for any remaining private parcels has not been announced.

Facts as on 31 January 2026, from NICDC

Land figures in this section are taken from the NICDC project monitoring report, and the environmental clearance figures are from the state environmental clearance record.

Frequently asked questions

How is land for Kopparthy Industrial Smart City being acquired?

Most of the land is being assembled through state and APIIC holdings rather than a fresh farmer consent drive. About 92% of the 2,595.74-acre core site was in state possession as of 31 January 2026.

What compensation is paid for land at Kopparthy Industrial Smart City?

No Kopparthy-specific per-acre compensation rate has been announced as of November 2026. Any private parcels would fall under the RFCTLARR Act, 2013, which sets compensation at up to four times market value in rural areas and twice in urban areas, plus a 100% solatium.

Which villages are covered by Kopparthy Industrial Smart City?

The core site covers Kopparthy and Tadigotla villages in Chinthakommadinne mandal, YSR Kadapa district. The related YSR Electronic Manufacturing Cluster also includes Rampathadu in Pendlimarri mandal and Ambavaram in Valluru mandal.

How much budget is allocated for Kopparthy Industrial Smart City?

The central project cost is Rs 2,137 crore, approved by the Union Cabinet in August 2024. The project is expected to attract Rs 8,860 crore of investment and about 54,500 jobs.

Is there farmer opposition to Kopparthy Industrial Smart City land?

No farmer negotiation or compensation exercise specific to the Kopparthy site has been reported. Most of the core land was already in state hands before the project was taken up.

Sources

Interested in Kopparthy Industrial Smart City?

Register once — get informed when projects, plot schemes or launches open up here.