Land assembly plan
LDA plans to acquire farmland at up to four times circle rate for IT City and Varun Vihar, Lucknow
The Lucknow Development Authority is preparing to assemble more land for its IT City township on Sultanpur Road and the Varun Vihar residential scheme, combining land pooling with acquisition for owners who do not opt in. As of November 2026, the plan is at the planning and land-assembly stage, with no final acquisition notification yet issued.

| Location | Sultanpur Road (NH-731), Mohanlalganj tehsil, Lucknow district, Uttar Pradesh |
|---|---|
| Deciding and nodal authority | Lucknow Development Authority (LDA) |
| Schemes covered | LDA IT City and Varun Vihar residential scheme |
| Method | Land pooling first, with acquisition as fallback for owners who do not come forward |
| Compensation for acquired land (as reported) | Up to 4 times circle rate for rural land; up to 2 times circle rate for urban land |
| Land still needed (as stated in the report) | Roughly 1,000 acres; about 100 acres of government land is counted in the mix |
| Total IT City scheme area (LDA, Feb 2026) | Approximately 3,490 acres (about 5,625 bigha) |
| Status as of November 2026 | Planning and land-assembly stage; no final acquisition notification cited |
What the LDA is proposing
The Lucknow Development Authority plans to acquire land for two residential and township schemes: the IT City project on Sultanpur Road and the Varun Vihar scheme. The approach combines land pooling with acquisition. Under pooling, landowners give up their land and receive developed plots allotted under the scheme. Owners who do not come forward for pooling may be subject to acquisition.
LDA vice-chairperson Prathamesh Kumar is quoted in the report on this approach. The stated strategy is to maximise the land secured through pooling with the consent of farmers, and to use acquisition only as a fallback.
The report puts the land need at roughly 1,000 acres for the scheme. About 100 acres of government land is counted within the overall mix, and some land has already been secured through pooling.
Compensation terms as reported
The report ties compensation for acquired land to the circle rate, the official rate that the state uses for land values. Higher multiples apply to rural plots than to urban plots.
| Type of land | Compensation as reported |
|---|---|
| Rural land | Up to 4 times the circle rate |
| Urban land | Up to 2 times the circle rate |
| Land given under pooling | Developed plots allotted under the scheme |
The report does not set out a single fixed rupee amount per acre. The actual payment for any plot depends on its circle rate and whether it is classed as rural or urban.
Where the IT City scheme already stands
The IT City project has moved through several stages since the Uttar Pradesh Cabinet first approved the Chak Gajaria farm land for an IT and multi-use precinct in April 2013. The LDA released the layout plan and master map on 28 February 2026, fixing sector boundaries, the road hierarchy and the pooling framework.
- Phase 1 notified area: 686.66 hectares (about 1,696 acres) under the land-pooling scheme.
- Phase 1 lottery on 10 March 2026 allotted 549 developed residential plots across Sectors 15, 16, 17, 18 and 30.
- Phase 2 lottery on 22 May 2026 allotted 415 plots.
- On 22 October 2026, the LDA announced Rs 100 crore for development of the villages covered by the IT City project.
- In early October 2026, the LDA proposed to the District Magistrate that about 300 hectares be acquired from owners who have not opted for pooling.
Scheme area figures in published reports vary. The LDA's own layout figure for the total IT City scheme is about 3,490 acres, while some earlier reports cite 2,660 to 2,858 acres for an older project scope.
What it means for the city
For Sultanpur Road, the plan is about bringing more land into a single planned township. The core anchor is the 100-acre HCLTech campus inside the IT City Special Economic Zone, which has been operational since 2016 and houses more than 6,500 employees in IT services and engineering roles. Land assembly for the wider scheme is intended to extend that employment base into a larger residential and commercial area.
The 11 villages in Mohanlalganj tehsil covered by the IT City scheme are Rakibabad, Sonai, Kajehra, Bhatwara, Moharikhurd, Sikandarpur Amolia, Bakkas, Pahadnagar Tikaria, Siddhpura, Parheta and Khujaili. For landowners in these villages, the choice between pooling and acquisition, and the compensation or plot allotment that follows, is the most direct effect of the plan.
For the wider city, the scheme adds housing supply and new road and utility networks along the corridor, but the timing of this supply depends on how fast the remaining land is secured.
What comes next
- A formal acquisition notification has not yet been cited in the report. The land-assembly process will move forward once acquisition steps are taken for owners who do not opt for pooling.
- A proposal to stay land registry (sale and purchase) transactions across the 11 villages was sent to the state government in August 2026 after the District Magistrate gave consent. It remains a proposal awaiting state notification.
- The final area and public-sale timeline for the wider township are still being firmed up.
Buyers, owners and investors should follow LDA notifications directly for the status of any specific plot or village.
Development phases
Frequently asked questions
Is the LDA acquiring land for IT City?
The LDA is preparing to acquire land for the IT City and Varun Vihar schemes. It is using land pooling first and acquisition as a fallback for owners who do not come forward. As of November 2026, no final acquisition notification has been cited.
How much compensation will farmers receive?
According to the report, compensation for acquired land can be up to 4 times the circle rate for rural land and up to 2 times the circle rate for urban land. The actual amount depends on the plot's circle rate and classification.
What do landowners get if they pool their land?
Landowners who give land under the pooling scheme receive developed plots allotted under the scheme. Plots have been allotted through lotteries held on 10 March 2026 and 22 May 2026.
How much land does the scheme need?
The report cites roughly 1,000 acres needed for the scheme. The LDA has said about 100 acres of government land is counted in the mix, and some land has already been secured through pooling.
Which villages are affected?
The IT City scheme covers 11 villages in Mohanlalganj tehsil: Rakibabad, Sonai, Kajehra, Bhatwara, Moharikhurd, Sikandarpur Amolia, Bakkas, Pahadnagar Tikaria, Siddhpura, Parheta and Khujaili.
Is the IT City project already operating?
The HCLTech campus inside the 100-acre IT/ITES Special Economic Zone has been operational since 2016. The wider township and residential development is still in the planning and land-assembly stage.
Sources
- LDA to acquire farmers' land at four times circle rate for IT City and Varun Vihar project in Lucknow
- IT City – Lucknow Development Authority (official page)
- Lucknow Development Authority (LDA) – Home and Press Release
- LDA to acquire 300 hectares for IT City, 6 October 2026 report
- UP govt plans IT city (Business Standard/PTI)
- LDA issues tender for developing IT City in Lucknow (BusinessToday)
- HCL IT City Official Website
- 549 plots allotted under land pooling policy in LDA's IT City scheme