Land assembly plan

LDA plans to acquire farmland at up to four times circle rate for IT City and Varun Vihar, Lucknow

The Lucknow Development Authority is preparing to assemble more land for its IT City township on Sultanpur Road and the Varun Vihar residential scheme, combining land pooling with acquisition for owners who do not opt in. As of November 2026, the plan is at the planning and land-assembly stage, with no final acquisition notification yet issued.

LDA IT City (Sultanpur Road) — LDA plans to acquire farmland at up to four times circle rate for IT City and Varun Vihar, Lucknow
LocationSultanpur Road (NH-731), Mohanlalganj tehsil, Lucknow district, Uttar Pradesh
Deciding and nodal authorityLucknow Development Authority (LDA)
Schemes coveredLDA IT City and Varun Vihar residential scheme
MethodLand pooling first, with acquisition as fallback for owners who do not come forward
Compensation for acquired land (as reported)Up to 4 times circle rate for rural land; up to 2 times circle rate for urban land
Land still needed (as stated in the report)Roughly 1,000 acres; about 100 acres of government land is counted in the mix
Total IT City scheme area (LDA, Feb 2026)Approximately 3,490 acres (about 5,625 bigha)
Status as of November 2026Planning and land-assembly stage; no final acquisition notification cited

What the LDA is proposing

The Lucknow Development Authority plans to acquire land for two residential and township schemes: the IT City project on Sultanpur Road and the Varun Vihar scheme. The approach combines land pooling with acquisition. Under pooling, landowners give up their land and receive developed plots allotted under the scheme. Owners who do not come forward for pooling may be subject to acquisition.

LDA vice-chairperson Prathamesh Kumar is quoted in the report on this approach. The stated strategy is to maximise the land secured through pooling with the consent of farmers, and to use acquisition only as a fallback.

The report puts the land need at roughly 1,000 acres for the scheme. About 100 acres of government land is counted within the overall mix, and some land has already been secured through pooling.

Compensation terms as reported

The report ties compensation for acquired land to the circle rate, the official rate that the state uses for land values. Higher multiples apply to rural plots than to urban plots.

Type of landCompensation as reported
Rural landUp to 4 times the circle rate
Urban landUp to 2 times the circle rate
Land given under poolingDeveloped plots allotted under the scheme

The report does not set out a single fixed rupee amount per acre. The actual payment for any plot depends on its circle rate and whether it is classed as rural or urban.

Where the IT City scheme already stands

The IT City project has moved through several stages since the Uttar Pradesh Cabinet first approved the Chak Gajaria farm land for an IT and multi-use precinct in April 2013. The LDA released the layout plan and master map on 28 February 2026, fixing sector boundaries, the road hierarchy and the pooling framework.

Scheme area figures in published reports vary. The LDA's own layout figure for the total IT City scheme is about 3,490 acres, while some earlier reports cite 2,660 to 2,858 acres for an older project scope.

What it means for the city

For Sultanpur Road, the plan is about bringing more land into a single planned township. The core anchor is the 100-acre HCLTech campus inside the IT City Special Economic Zone, which has been operational since 2016 and houses more than 6,500 employees in IT services and engineering roles. Land assembly for the wider scheme is intended to extend that employment base into a larger residential and commercial area.

The 11 villages in Mohanlalganj tehsil covered by the IT City scheme are Rakibabad, Sonai, Kajehra, Bhatwara, Moharikhurd, Sikandarpur Amolia, Bakkas, Pahadnagar Tikaria, Siddhpura, Parheta and Khujaili. For landowners in these villages, the choice between pooling and acquisition, and the compensation or plot allotment that follows, is the most direct effect of the plan.

For the wider city, the scheme adds housing supply and new road and utility networks along the corridor, but the timing of this supply depends on how fast the remaining land is secured.

What comes next

Buyers, owners and investors should follow LDA notifications directly for the status of any specific plot or village.

Development phases

Phase 1Notified; lottery held 10 March 2026686.66 ha (about 1,696 acres) under pooling; 549 plotsallottedPhase 2Lottery held 22 May 2026415 plots allotted; land acquisition for non-poolingowners and registry stay proposal pending

Frequently asked questions

Is the LDA acquiring land for IT City?

The LDA is preparing to acquire land for the IT City and Varun Vihar schemes. It is using land pooling first and acquisition as a fallback for owners who do not come forward. As of November 2026, no final acquisition notification has been cited.

How much compensation will farmers receive?

According to the report, compensation for acquired land can be up to 4 times the circle rate for rural land and up to 2 times the circle rate for urban land. The actual amount depends on the plot's circle rate and classification.

What do landowners get if they pool their land?

Landowners who give land under the pooling scheme receive developed plots allotted under the scheme. Plots have been allotted through lotteries held on 10 March 2026 and 22 May 2026.

How much land does the scheme need?

The report cites roughly 1,000 acres needed for the scheme. The LDA has said about 100 acres of government land is counted in the mix, and some land has already been secured through pooling.

Which villages are affected?

The IT City scheme covers 11 villages in Mohanlalganj tehsil: Rakibabad, Sonai, Kajehra, Bhatwara, Moharikhurd, Sikandarpur Amolia, Bakkas, Pahadnagar Tikaria, Siddhpura, Parheta and Khujaili.

Is the IT City project already operating?

The HCLTech campus inside the 100-acre IT/ITES Special Economic Zone has been operational since 2016. The wider township and residential development is still in the planning and land-assembly stage.

Sources