Mountain City (Jubbarhatti Township) — Land Acquisition Status

HIMUDA's Mountain City project — also called the Jathia Devi satellite township or Shimla Counter-Magnet Township — has been trying to assemble land near Jubbarhatti airport for over two decades. As of early-to-mid 2026 the state says it wants villagers' consent, but several panchayats have formally refused to give land, leaving the acquisition contested and incomplete.

Mountain City (Jubbarhatti Township) — Mountain City (Jubbarhatti Township) — Land Acquisition Status
Current land requirement (Jan 2026)~1,200 bighas, per PWD/UD Minister Vikramaditya Singh
Earlier stated requirement~2,600 bighas (Minister Vikramaditya Singh, undated Tribune report)
Land already acquired (historical)35 hectares at Jathia Devi + 250 bighas via agreement with Chanan/Majhola villagers
Planning-area villages notified (23 Jan 2024)177 revenue villages — 106 (Shimla Planning Area) + 21 (Shoghi Special Area), Shimla district; 50 (Kandaghat tehsil), Solan district
Total project cost (2023 DPR)≈ Rs 1,373–1,374 crore
HIMUDA Phase-1 approval (Feb 2026)919 residential units on 21 bighas, Rs 1,327 crore
Latest sub-project cost (Jul 2026 filing)₹568.75 crore for 20.35 hectares, EC sought
Acquisition modelConsent/agreement-based, with a compulsory fallback provision historically on the table
Key dispute (Jan 2026)Bagi/Jathiya Devi panchayat resolution rejecting acquisition, sent to Governor and CM

What this project is called

The township has gone by several names as it has moved through state and central schemes: it began as the Jathia Devi satellite/mountain township, was pitched to the Centre as a Shimla Counter-Magnet Township, and was rebranded 'Mountain City' when HIMUDA's board cleared land acquisition in October 2023 as a counter-magnet city to decongest Shimla. The Himachal Pradesh Housing and Urban Development Authority (HIMUDA) received the green light from its Board of Directors to acquire land for the establishment of new township 'Mountain City', near the Jubbarhatti airport, as a counter-magnet city to decongest Shimla city.

A two-decade history of stalled acquisition

Land assembly at this site has failed to conclude multiple times under different governments. As far back as 2007, 5,227 bighas of land had been identified by Himuda, of which barely 1,692 bighas belonged to the government while 3,018 bighas was under private ownership, with another 517 bighas set aside for IT-based industry, but nearly four years had lapsed in identifying the requisite land as it met with massive opposition from villagers.

A later attempt under the Virbhadra Singh government saw about 400 bighas acquired at Jathia Devi, about 17 km from Shimla, and experts from Singapore visited Jathia Devi and prepared a master plan, with an agreement signed with a Singapore company for the township. The previous BJP government subsequently abandoned the satellite township proposal, and the project became unviable after restrictions were imposed on construction and the number of floors that could be built within the Shimla Planning Area.

By around 2015, HIMUDA had acquired 35 hectares at Jathia Devi, 13 km from Shimla, though around 100 hectares more would have to be acquired for a full-fledged self-sustaining township. The project was revived again in 2023 under the current government as 'Mountain City'.

Acquisition model: consent first, compulsion held in reserve

The state's stated approach has shifted over time between negotiated purchase and a compulsory fallback. In one round of talks, a meeting with landowners was held to decide circle rates on the basis of the base price fixed by HIMUDA, and officials noted that if consensus could not be forged, HIMUDA had the right to acquire land under a special section. Deputy Commissioners at the time also asked HIMUDA to keep landowners fully informed to avoid disputes: officials directed that complete information about land to be acquired be given to owners so they had no doubts, which would also reduce revenue-related disputes.

More recently, the government has publicly committed to a purely consent-based model. Himachal Pradesh Public Works and Urban Development Minister Vikramaditya Singh said in January 2026 that no compulsory or forceful land acquisition would be carried out for the township, and that not even an inch of land would be taken without public consent. He said resolutions passed by village panchayats opposing forced land acquisition would be respected.

Villages covered, by district

Two distinct village counts appear in official records — one for the broader planning jurisdiction, another for the villages directly facing acquisition notices.

Compensation rates and demands

No fixed, published per-bigha or per-hectare compensation rate for the current acquisition round has been reported. What is on record instead are the negotiation terms and demands:

No official rate schedule matching this factor-2 demand has been published as of the time of writing; this page will be updated once a notified compensation rate is confirmed in reporting.

Budget

Cost estimates have varied across stages of the project:

Disputes and farmer/panchayat resistance

Opposition has intensified through late 2025 and early 2026. The Town and Country Planning Department's move to initiate the land acquisition process after years of uncertainty sparked sharp resistance from local villagers, who feared loss of land and livelihoods. A delegation of residents from Jathia Devi and adjoining villages met Urban Development and PWD Minister Vikramaditya Singh, urging him to intervene and halt the acquisition process.

At a formal public hearing, residents from nine villages registered their objections and suggestions to the acquisition, with more than 500 villagers attending and submitting written objections. Local leaders said due process had been skipped: Baghi pradhan Des Raj said people were not informed about the land acquisition earlier and a notice was issued only on December 24, with nobody told how much land was to be acquired across the eight revenue villages. The SDM assured villagers that survey shortcomings — including unrecorded water kuhls, temples and a gurdwara — would be addressed.

The dispute escalated to a formal panchayat resolution in January 2026. Amid mounting opposition to the proposed Rs 1,374-crore Jathiya Devi satellite township, Gram Panchayat Bagi formally refused to part with any land for the project, with the resolution passed by an overwhelming majority at a Gram Sabha meeting. The resolution was submitted to the Governor and Chief Minister, seeking immediate cancellation of the proposed acquisition and citing threats to livelihoods, agriculture and local infrastructure, and was passed at a special Gram Sabha attended by residents of eight villages.

Current stage (as of mid-2026)

As things stand, the project is administratively moving forward on paper while facing active local opposition on the ground:

In short: notified planning area — yes; board-level project approvals — yes, in phases; completed, uncontested land acquisition — no, not as of the latest available reports.

Development phases

Frequently asked questions

Is land acquisition for Mountain City / Jathia Devi township complete?

No. As of early-to-mid 2026, HIMUDA has only secured pockets of land from earlier rounds (around 35 hectares plus 250 bighas via village agreements); a further roughly 1,200 bighas is described as still required, and this is contested by at least one panchayat.

What is the current land acquisition model — consent or compulsory award?

The government has stated it will not use compulsory acquisition and will proceed only with landowner consent, respecting panchayat resolutions. Earlier rounds of the project, however, kept a compulsory fallback (a 'special section') available if consensus could not be reached.

How many villages are covered by the project?

The Jathia Devi Planning Area notified in January 2024 covers 177 revenue villages (106 from the former Shimla Planning Area and 21 from the Shoghi Special Area in Shimla district, plus 50 from Kandaghat tehsil in Solan district). A smaller set of nine villages — including Anji, Majhola, Chanal, Shirdu and Kyari — has been directly named in recent land acquisition notices and hearings.

What compensation rate is being offered to landowners?

No fixed, publicly notified per-bigha rate for the current round has been reported. Villagers have demanded compensation at 'factor-2' rates under the Land Acquisition, Rehabilitation and Resettlement (LARR) Act, or a complete rollback of the acquisition; the government has not confirmed a matching rate in available reporting.

What is the total budget for the Mountain City project?

The whole-project detailed project report from 2023 estimated the cost at roughly Rs 1,373–1,374 crore. A later Phase-1 residential component approved by HIMUDA in February 2026 carries its own estimated cost of Rs 1,327 crore, and a separate filing in mid-2026 lists a 20.35-hectare sub-project at ₹568.75 crore.

Which villages have opposed the acquisition?

The Bagi (also called Jathiya Devi) gram panchayat, covering villages including Chanan/Chalan, Majhola/Mashla and others, passed a formal resolution in January 2026 refusing to give land and asked the Governor and Chief Minister to cancel the acquisition. Residents of Shilibhaghi, Anji, Chanal, Panti, Danukhri, Shirdu, Kyari and Majhiyari also raised objections at a December 2025 public hearing.