Mountain City (Jubbarhatti Township) Master Plan — HIMUDA's Counter-Magnet City for Shimla

Mountain City is HIMUDA's long-delayed counter-magnet township near Jubbarhatti Airport, on the Jathia Devi site outside Shimla — there is no single stable master plan document; instead the project has moved through several redesigns, with the latest Phase 1 approved in February 2026 covering a small fraction of the originally envisioned land.

Mountain City (Jubbarhatti Township) — Mountain City (Jubbarhatti Township) Master Plan — HIMUDA's Counter-Magnet City for Shimla
LocationJathia Devi, near Jubbarhatti Airport, ~12–15 km from Shimla
Development authorityHIMUDA (Himachal Pradesh Housing and Urban Development Authority)
Current status (Feb 2026)Phase 1 approved by HIMUDA board; not yet under construction
Land acquired to date35 hectares confirmed; further 100 hectares planned (~135 ha total)
Planning area notifiedJathia Devi Planning Area notified 23 Jan 2024, excluding 177 villages from Shimla Planning Area
Phase 1 (2026 version)919 residential units on 21 bighas; ~Rs 1,327 crore
Earlier project cost estimatesRs 1,373–1,374 crore (2023 DPR); Rs 500 crore revised Centre-funding ask (Aug 2023)
ConsultantTata Consulting Engineers Ltd (TCE)
Original scheme2017 MoU with Singapore-backed firm; scrapped August 2019 after NGT height restrictions

What kind of "master plan" actually exists

There is no single, fixed master-plan document for Mountain City that has stayed unchanged over time. The project has been re-scoped at least three times since it was first conceived, and each version has its own land figures, costs and phasing. With the National Green Tribunal restricting construction in the Greater Shimla Planning Area, HIMUDA had decided to abandon the modern township project at Jathiadevi, near Jubbarhatti airport, after signing an MoU with Singapore on February 27, 2017. The project never took off because the NGT restricted construction to two and a half floors, making it economically unviable, and the MoU was scrapped in August 2019.

The name later resurfaced under two labels for what is largely the same Jubbarhatti/Jathia Devi site: HIMUDA received approval to acquire land for the establishment of new township 'Mountain City', near the Jubbarhatti airport, as a counter-magnet city to decongest Shimla city. Government press material and the 2024–2026 board minutes refer to the same site simply as the "Jathia Devi project."

Total planned area vs. area actually committed

Figures for total land differ by report and by date, and should not be added together as if they describe one static plan:

In short: the 135-hectare figure is the land HIMUDA has acquired or is acquiring; the 21-bigha, 919-unit figure is the much smaller slice actually committed to construction as of early 2026. No published document confirms what share of the 135 hectares the current Phase 1 represents, and no overall completion year has been stated for the full township.

Timeline of the project

DateDevelopment
27 Feb 2017MoU signed with a Singapore-backed government firm to build the township.
Aug 2019MoU scrapped after NGT restricted construction heights, making the project unviable.
Jan 2022HIMUDA decided to sell plots and construct flats at the site instead of the original township model.
Jul 202335 hectares confirmed acquired; ~100 hectares more identified as needed for a self-sustaining township; DPR submitted under the Mountain Township Scheme.
Aug 2023Centre approved a revised DPR costed at Rs 500 crore, down from an initial Rs 1,300 crore estimate.
Oct 2023HIMUDA board approved land acquisition for 'Mountain City' near Jubbarhatti airport, at an estimated project cost of around Rs 1,373 crore.
19 Jan 2024A Rs 1,374 crore proposal was sent to the Union Ministry, and HIMUDA prepared to issue an RFP for acquiring 100 hectares and appointing a consultant.
23 Jan 2024The TCP Department created the Jathia Devi Planning Area by excluding 177 villages — 106 from the Shimla Planning Area, 21 from the Shoghi Special Area and 50 from Kandaghat tehsil — under Sections 66 and 13 of the Town and Country Planning Act, 1977.
Aug 2024Tata Consulting Engineers Ltd delivered a detailed presentation on the project; the government had by then acquired 35 hectares.
Feb 2026HIMUDA board approved Phase 1: 919 residential units on 21 bighas, at an estimated investment of Rs 1,327 crore.

Land use and phasing approach

No published land-use split (percentage of area for residential, commercial, industrial, green/open space) has been located for Mountain City / Jathia Devi as of this writing, so no percentage breakdown is shown on this page. What is documented is the phasing approach itself: HIMUDA plans to develop the township in a phased manner with residential, commercial and civic infrastructure, ensuring planned growth and regulated urbanisation. The Jathia Devi Planning Area notification is a zoning/jurisdiction instrument — it defines which villages fall under regulated development control — rather than a parcel-by-parcel land-use map.

Population and employment targets

No official population or employment target figure has been published for Mountain City. The closest quantified metric available is the Phase 1 housing count: HIMUDA would develop 919 residential units on 21 bighas of land in the first phase of the Jathia Devi project. Earlier coverage of the broader counter-magnet strategy for Shimla notes the underlying rationale — Shimla's population rose from 13,960 in 1901 to 169,572 in 2011 and was projected to reach 210,277 by 2022 — but this is context for why a counter-magnet township was proposed, not a stated target for Mountain City itself.

Planner / consultant

Tata Consulting Engineers Ltd (referred to in some reports simply as "Tata Consultants") prepared and submitted the master plan for the satellite township. The firm's continued role was confirmed later: Tata Consulting Engineers Ltd delivered an in-depth presentation on the Jathia Devi project to the state government in August 2024.

Where to find official plan documents

No single downloadable "master plan PDF" for Mountain City/Jathia Devi was found publicly hosted at the time of writing. The primary official channels to check are:

Readers should treat any figure on this page as provisional and check these sources directly for the latest board decisions, since the project's scope has changed multiple times since 2017.

Development phases

Original concept (superseded)2016–2019 (abandoned)1,944 bighas total per TCE master plan; Phase I tocover 250 bighas by HIMUDA plus 350 bighas transferredfromLand-acquisition milestoneby 2023–202535 hectares acquired; further 100 hectares planned(~135 ha total); Jathia Devi Planning Area notified 23JanPhase 1 (current, board-approved)approved Feb 2026; no public completion date919 residential units on 21 bighas; ~Rs 1,327 croreinvestment

Frequently asked questions

Is Mountain City the same project as the 'Jathia Devi township' or 'New Shimla'?

Yes — these are different names used over time by officials and media for the same HIMUDA counter-magnet project near Jubbarhatti Airport / Jathia Devi, outside Shimla.

Has construction actually started?

As of the most recent confirmed update, the project was at the land-acquisition and board-approval stage. In February 2026 HIMUDA's board approved a Phase 1 of 919 residential units on 21 bighas, but no construction-completion date has been published.

How much land will the township eventually cover?

This is not settled. An early Tata Consulting Engineers master plan envisioned 1,944 bighas, but the plan actually being pursued from 2023 onward is built around roughly 135 hectares of acquired/to-be-acquired land — a much smaller footprint.

What happened to the original Singapore-backed township plan?

The state signed an MoU with a Singapore government-backed firm in February 2017, but the National Green Tribunal's restriction on building heights in the Greater Shimla Planning Area made the design economically unviable, and the MoU was scrapped in August 2019.

Who is the planning consultant?

Tata Consulting Engineers Ltd (TCE) prepared the master plan/DPR and has continued to brief the state government on the project.

Is there an official land-use breakdown (residential vs commercial vs green space)?

No percentage-based land-use split has been publicly documented for this project as of this writing; only the phased development approach and unit counts for Phase 1 are confirmed.

Where can I check the latest official status?

Check HIMUDA's official website and Himachal Pradesh government press releases directly, since board approvals and cost figures for this project have changed several times since 2017.