Land Acquisition Notice
YEIDA Notifies Acquisition of 736 Hectares in Tappal for Logistics Park
In 2023, the Yamuna Expressway Industrial Development Authority (YEIDA) issued a notification to acquire 736 hectares of land in Tappal, Aligarh district, launching the first concrete land-acquisition step for the planned Tappal-Bajna logistics park and industrial hub. A social impact assessment by Gautam Buddha University subsequently identified 888 families as affected by the move.

| Decision | Notification to acquire 736 hectares of land in Tappal |
|---|---|
| Issuing authority | Yamuna Expressway Industrial Development Authority (YEIDA) |
| Year of notification | 2023 (specific date not published in available records) |
| SIA conducted by | Gautam Buddha University, under the RFCTLARR Act, 2013 |
| Families identified as affected | 888 |
| Logistics park footprint (Master Plan 2031, Phase II) | 364 acres (~147 hectares) |
| Logistics park Phase 1 | 205 acres, including 154 acres for core logistics operations |
| Estimated project cost | ₹990–1,040 crore (land acquisition + infrastructure) |
| Tappal-Bajna Urban Centre total area | 27,438 acres (~11,100 hectares); urban centre first approved in 2017 |
| UP govt approval of Master Plan 2031 Phase II | 24 March 2025 |
What Was Decided
In 2023, YEIDA issued a notification to acquire 736 hectares and began conducting a social impact assessment (SIA). The notification covers land in Tappal, part of the wider Tappal-Bajna Urban Centre — a 27,438-acre industrial and residential township near the Noida International Airport, and represents the authority's first formal step toward assembling land for the logistics park and industrial projects planned for the area.
The Social Impact Assessment
The social impact assessment, conducted by Gautam Buddha University under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, identified impacts on 888 families, emphasizing the need for fair compensation, livelihood restoration, and preservation of social balance to mitigate displacement risks. Officials described the SIA process as one that evaluates the potential social effects on a community when land is acquired for development, will identify mitigation strategies and ensure fair compensation for affected farmers.
Scale and Boundaries of the Logistics Park
The Tappal-Bajna Urban Centre is not a new concept — it was one of the last major urban centres under Master Plan 2031, approved in 2017, alongside the Raya Urban Centre in Mathura. Within it, the logistics park is part of YEIDA's Master Plan 2031 (Phase II) and is set to occupy 364 acres within the Tappal-Bajna Urban Centre.
Development is staged: the park, which is estimated to cost around INR 1,040 crore, will be developed in three phases, with the first phase covering 205 acres, including 154 acres dedicated to logistics operations. The scheme aims to address the rising cargo demands of the National Capital Region (NCR) and surrounding areas, particularly with the nearby Noida International Airport.
The broader Phase-II master plan covering this and other Yamuna Expressway urban centres received state government sign-off on 24 March, when the Uttar Pradesh government approved the Master Plan 2031 Phase-2 for urban development in Aligarh, Mathura, Hathras, and Agra along the 165-km Yamuna Expressway.
Investment and Employment Estimates
Separate reporting on the logistics-park component describes it as developed via public-private partnership with over Rs 640 crore investment, ... projected to create around 10,000 jobs through warehouses, transport terminals, commercial zones, and supporting infrastructure. This PPP/jobs figure applies to the logistics-park scheme specifically and should not be confused with the larger land-acquisition cost estimate of ₹990–1,040 crore cited for land plus infrastructure across the wider notified area.
Broader Acquisition Targets Beyond the 736 Hectares
The 736-hectare notification is described in multiple reports as only a first tranche. YEIDA plans to acquire around 1,900 hectares (including 736 hectares already notified) to protect the area from encroachment and enable planned development. Later reporting referenced still-larger figures for the same broad Tappal-Bajna area: one account said 1,449 hectares in Tappal-Bajna (Aligarh) will also be acquired for logistics parks and industrial development, while another noted a request to the Aligarh administration requesting to initiate a social impact assessment (SIA) for over 1,600 hectares of land earmarked for logistics park and industrial development in the Tappal-Bajna Urban Centre. A separate report put the figure at 712 hectares... acquired for the Tappal-Bajna Urban Centre. These numbers appear to reflect different proposal stages and scopes reported across 2024–2025 rather than a single reconciled figure, and none supersede the confirmed 736-hectare notification of 2023.
Practical Effect: Encroachment Risk and the Registration Ban
The notification's practical effect has been complicated by unauthorized activity inside the notified footprint. YEIDA has urged the Aligarh administration to halt land registries and curb unauthorized constructions in the Tappal-Bajna area, earmarked for a logistics park and industrial projects. Officials warned that residential registrations in the area... could make evictions challenging and jeopardize the Rs 1,040-crore project.
YEIDA's CEO raised concerns about the rapid emergence of unauthorized colonies across 90 villages in the area, and a district-level survey indicated unauthorised plotting on land that falls under YEIDA's notified jurisdiction, with roads without asphalt or tar and boundary walls — wire fences and cemented markers — had come up in the area. In response, an OSD said an anti-encroachment drive will soon be conducted in the area to demolish illegal constructions. Despite this, plots continue to be sold to buyers from Delhi-NCR, with residential plots priced between Rs 15,000 and Rs 25,000 per square meter.
Development phases
Frequently asked questions
What exactly did YEIDA notify in 2023?
YEIDA issued a formal notification to acquire 736 hectares of land in Tappal, Aligarh district, and began a social impact assessment (SIA) as required for land acquisition under Indian law.
Who carried out the social impact assessment, and what did it find?
Gautam Buddha University conducted the SIA under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. It identified 888 families as affected by the proposed acquisition.
Is the 736-hectare notification the same as the full Tappal-Bajna logistics park?
No. The 736 hectares is a land-acquisition notification covering part of the wider Tappal-Bajna Urban Centre. The logistics park itself, under YEIDA's Master Plan 2031 (Phase II), is a smaller 364-acre (~147-hectare) scheme within that notified area, with its first construction phase covering 205 acres.
How much more land does YEIDA plan to acquire beyond the 736 hectares?
Various reports from 2024–2025 cite larger figures — around 1,900 hectares in Tappal overall, 1,449 hectares for Tappal-Bajna industrial/logistics use, and a separate SIA request covering more than 1,600 hectares. These appear to be overlapping or successive proposals rather than a single confirmed final figure.
Why did YEIDA ask the Aligarh administration to stop land registrations?
Because unauthorized residential plotting, informal roads and boundary markers had appeared within the notified area despite the 2023 acquisition notice, risking evictions becoming legally difficult and threatening the logistics park's industrial land-use plan.
When was the Tappal-Bajna Urban Centre itself approved?
The Tappal-Bajna Urban Centre was first approved by the Uttar Pradesh government in 2017 as part of Master Plan 2031. The related Phase-II master plan for this and other Yamuna Expressway urban centres received fresh state approval on 24 March 2025.
What is the estimated cost of the logistics park project?
Reports put the cost of land acquisition and infrastructure for the logistics park at roughly ₹990–1,040 crore, with a separate figure of over ₹640 crore cited for the PPP-developed logistics facility itself, projected to create around 10,000 jobs.
Sources
- No more land Registration: YEIDA Moves to Protect Rs 1,040-Crore Logistics Park from Encroachments
- Tappal — Grokipedia
- Noida: YEIDA to Acquire 5,000 hectare for Multiple Projects
- Unauthorised encroachments threaten YEIDA's INR 1,040 crore logistics park project in Aligarh
- YEIDA urges Aligarh administration to halt land registries
- Logistics Park at Tappal Yamuna Expressway
- YEIDA's massive land acquisition: A boost for urban development - Construction Week India
- YEIDA to acquire 5,000 hectares, plans to launch new plot schemes
- UP Govt Approves YEIDA's Phase-2 Master Plan for New Cities Along Yamuna Expressway
- UP Government Approves Master Plan 2031 Phase-2 for Yamuna Expressway Areas, YEIDA's Strategic Development Plans
- UP government approves YEIDA Master Plan 2031 Phase-2 for Agra, Mathura, Aligarh and Hathras