Land Acquisition
YEIDA Seeks Social Impact Assessment for 1,600 Hectares at Tappal-Bajna for Logistics and Industrial Development
YEIDA has sent a letter to the Aligarh administration requesting the initiation of a social impact assessment (SIA) for over 1,600 hectares of land earmarked for logistics park and industrial development in the Tappal-Bajna Urban Centre. Gautam Buddha University will conduct the assessment, and survey teams will be formed in both districts.

| Land area for SIA | Over 1,600 hectares in Tappal-Bajna, Aligarh |
|---|---|
| Purpose | Logistics park and industrial development |
| Assessment agency | Gautam Buddha University |
| Total Tappal land acquisition plan | 2,000 hectares in Tappal village |
| Prior notification | Authority issued notification to acquire 736 hectares in Tappal last year; SIA process currently underway |
| Logistics park scale | Set to be developed on 364 acres within the Tappal-Bajna Urban Centre — a 27,438-acre industrial and residential township |
| Project investment | Rs 1,040 crore estimated |
| Funding secured | YEIDA signed MoU with HUDCO and secured Rs 3,300 crore in interest-free loans from State government |
What YEIDA Decided
A letter has been sent to the Aligarh administration requesting to initiate a social impact assessment (SIA) for over 1,600 hectares of land earmarked for logistics park and industrial development in the Tappal-Bajna Urban Centre.
Gautam Buddha University will conduct the assessment, and survey teams will be formed in both districts. Surveys are scheduled to begin next week (as of late January 2025).
Background: Earlier Acquisition
Last year, the Authority issued a notification to acquire 736 hectares in Tappal, and the social impact assessment (SIA) process is currently underway. YEIDA plans to acquire 2,000 hectares of land in Aligarh's Tappal village for logistics parks and other projects outlined in its master plan.
The Multimodal Logistics Park Project
The Tappal-Bajna Urban Center in Aligarh will feature a logistics park, designed to enhance cargo handling and boost industrial growth along the Yamuna Expressway corridor.
The logistics park, part of YEIDA's Master Plan 2031 (Phase II), is set to be developed on 364 acres within the Tappal-Bajna Urban Centre — a 27,438-acre industrial and residential township near the Noida International Airport.
Phase I will cover 205 acres, with 154 acres dedicated to core logistics operations.
Purpose and Scope of SIA
The SIA, which evaluates the potential social effects on a community when land is acquired for development, will identify mitigation strategies and ensure fair compensation for affected farmers.
For the proposed 166-hectare logistics hub, a social impact assessment conducted by Gautam Buddha University under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, identified impacts on 888 families, emphasizing the need for fair compensation, livelihood restoration, and preservation of social balance to mitigate displacement risks.
Funding and Partnerships
YEIDA has also signed a memorandum of understanding (MoU) with HUDCO for funding and has secured Rs 3,300 crore in interest-free loans from the State government.
According to the MoU, YEIDA and HUDCO together will develop a habitat center on 25 acres and a convention center on 15 acres close to Noida airport. NBCC India will be the collaborative partner for these projects with HUDCO and YEIDA under the Private Public Partnership (PPP) model.
Encroachment and Land Security Challenges
YEIDA has urged the Aligarh administration to halt land registries and curb unauthorized constructions in the Tappal-Bajna area, earmarked for a logistics park and industrial projects. This step follows widespread encroachments reported within the notified area, threatening the success of the multi-modal logistics park scheme.
Residential plots are being sold to buyers from Delhi-NCR, with residential plots priced between Rs 15,000 and Rs 25,000 per square meter, and commercial plots along the Yamuna Expressway fetching higher rates.
Broader YEIDA Phase II Expansion
YEIDA Phase II will extend over 2,593 sq km, bringing major urban transformations to Mathura, Agra, Aligarh, and Hathras. Four Key Urban Centers in Phase II: Raya Urban Center (Mathura), Tappal-Bajna Urban Center (Aligarh), Agra Urban Center, Hathras Urban Center.
YEIDA will acquire land in 10 new sectors, including sectors 4A, 5, 5A, 6, 7, 8, 8D, 9, 10, and 11. A Korean city will be developed in sector 4A, covering 365 hectares, while a Japanese city will be established in sector 5A, spanning 395 hectares.
What Comes Next
Following the initiation of the SIA process (announced late January 2025), the survey teams will conduct fieldwork across Aligarh and adjacent districts. The Uttar Pradesh government approved YEIDA's Master Plan 2031 Phase-II in March 2025, designating Tappal-Bajna as an industrial township integrated with the Yamuna Expressway corridor.
The SIA findings will inform compensation frameworks and rehabilitation schemes for affected landholders, following which formal land acquisition proceedings are expected to proceed. Concurrently, YEIDA is pursuing anti-encroachment actions to protect the notified area from unauthorized residential development.
Development phases
Frequently asked questions
Why is YEIDA conducting a social impact assessment for Tappal-Bajna?
The SIA evaluates the potential social effects on a community when land is acquired for development, will identify mitigation strategies and ensure fair compensation for affected farmers.
Who will conduct the SIA and when will it be completed?
Gautam Buddha University will conduct the assessment, and survey teams will be formed in both districts. Surveys are scheduled to begin next week from late January 2025; no formal completion date has been announced.
How much land has YEIDA already notified for acquisition in Tappal?
The Authority issued a notification to acquire 736 hectares in Tappal last year, and the social impact assessment (SIA) process is currently underway.
What is the total planned logistics park footprint?
The logistics park is set to be developed on 364 acres within the Tappal-Bajna Urban Centre — a 27,438-acre industrial and residential township near the Noida International Airport. Phase I will cover 205 acres, with 154 acres dedicated to core logistics operations.
Has YEIDA secured funding for the project?
YEIDA has signed a memorandum of understanding (MoU) with HUDCO for funding and has secured Rs 3,300 crore in interest-free loans from the State government.
What challenges has the project faced?
YEIDA has urged the Aligarh administration to halt land registries and curb unauthorized constructions in the Tappal-Bajna area. This follows widespread encroachments reported within the notified area, threatening the success of the multi-modal logistics park scheme. Officials have expressed concern over residential registrations in the area, which could make evictions challenging and jeopardize the Rs 1,040-crore project.
What is the broader context of Tappal-Bajna development?
Tappal-Bajna is one of four Key Urban Centers in YEIDA Phase II; detailed project reports (DPRs) have been prepared for Raya and Tappal-Bajna Urban Centers, with developers being finalized. Tappal-Bajna Urban Centre will be developed in 11,104 hectares.
Sources
- 99acres: YEIDA to acquire 5,000 hectares, plans to launch new plot schemes
- Construction World: Uttar Pradesh Approves YEIDA Phase II Under Master Plan 2031
- Construction World: NOIDA: YEIDA to Acquire 5,000 hectare for Multiple Projects
- India Seatrade News: YEIDA moves to protect Rs 1,040 crore logistics park from encroachments
- Grokipedia: Tappal
- Maritime Gateway: YEIDA gets ready to acquire land for logistics park & heritage city
- YEIDA Official: Logistics Park
- Properties News: YEIDA Authority Inks Deal with HUDCO as Consultant