APCRDA's 64th Authority Meeting Clears L&T Quantum Facility Contract and Twin Quantum Valley Towers

At its 64th Authority meeting on 4 August 2026, chaired by Chief Minister N. Chandrababu Naidu, the Andhra Pradesh Capital Region Development Authority (APCRDA) approved awarding Larsen & Toubro the contract for the Rs 1,280-crore Quantum Facility Project and for construction of the two Quantum Valley towers, alongside a batch of other Amaravati infrastructure decisions.

Amaravati — APCRDA's 64th Authority Meeting Clears L&T Quantum Facility Contract and Twin Quantum Valley Towers
Meeting64th APCRDA Authority Meeting
Date4 August 2026 (announced late Tuesday)
Chaired byChief Minister N. Chandrababu Naidu
Briefed byMunicipal Administration & Urban Development Minister P. Narayana
Quantum Facility Project contractorLarsen & Toubro (L&T)
Quantum Facility Project valueRs 1,280 crore
Quantum Valley twin towers construction valueRs 1,205 crore (this meeting)
Land pooling contribution endorsed2,344 acres, Mothadaka village, Guntur district
Endowments compensation releasedRs 122 crore for 244.39 acres, Palnadu district

What was decided

The Capital Region Development Authority (CRDA) has approved several key development works to accelerate the reconstruction of Amaravati, including the quantum facility project, digital infrastructure, tourism initiatives and measures to strengthen connectivity, an official release quoting Minister Narayana said after the 64th CRDA Authority meeting. The meeting was chaired by Chief Minister N. Chandrababu Naidu, and the decisions were briefed to reporters afterward by Municipal Administration and Urban Development Minister P. Narayana.

Two contract awards to Larsen & Toubro (L&T) were the headline items: the Quantum Facility Project and the construction of the Quantum Valley towers.

Quantum Facility Project: L&T contract

The minister said Larsen & Toubro had secured the tender for the Rs 1,280-crore Quantum Facility Project, which has been approved by the authority as part of the government's efforts to develop Amaravati into a global technology hub. The award was described by the minister as one of the flagship projects for strengthening the city's position in advanced technology and innovation, part of the broader plan to build Amaravati into a global city through investment in infrastructure and technology.

Quantum Valley twin towers: construction contract

The same meeting approved awarding the contract to L&T for construction of the two 18-storey Quantum Valley towers, reported at a cost of Rs 1,205 crore.

This construction award follows on from an earlier, separate administrative approval: at APCRDA's 60th Authority meeting on 23 April 2026, the state had already granted administrative approval of Rs 1,208.41 crore for the construction of twin office towers in the Quantum Valley, designed to boost IT and commercial growth, with the towers (designated T1 and T2) described as iconic, G+43-floor towers that will provide 3.7 million sq ft of office space, aiming to create a global hub for quantum tech companies, R&D labs, and startups. That 60th-meeting decision cleared the "shell and core" works package, and the 64th-meeting decision is the follow-through contract award for actual construction. Readers should note the differing floor counts and rupee figures reported across sources (Rs 1,208.41 crore/G+43-floor at the 60th meeting versus Rs 1,205 crore/18-storey at the 64th meeting) — both figures come from official briefings but have not been fully reconciled in public reporting as of August 2026.

Other approvals at the 64th meeting

Land pooling, acquisition and compensation

The authority approved land acquisition for the Inner Ring Road and a new railway line to improve connectivity to the capital. Reports differ slightly on the acreage: one account states the authority endorsed the unanimous resolution passed by residents of Mothadaka village in Guntur district to contribute 2,344 acres under the Land Pooling Scheme, while another puts it at the allotment of 2,340 acres at Mothadaka village for the proposed Inner Ring Road and railway line.

Separately, the authority approved the release of Rs 122 crore to the Endowments Department as compensation in accordance with Supreme Court directions, for bringing 244.39 acres of Endowments Department land in Palnadu district under the Land Pooling Scheme. The authority also ratified borrowings to pay nearly Rs 300 crore in annuity to farmers who pooled their lands for the capital city project.

Context: the Amaravati Quantum Valley programme

The Quantum Facility and twin towers sit inside a wider state initiative. The Quantum Valley is a landmark initiative to establish India's first 133-qubit quantum computer, with leading companies such as IBM, TCS and L&T partnering in the project, and its foundation stone was laid by Union Minister for Science and Technology Dr. Jitendra Singh together with CM Naidu in February 2026. The Andhra Pradesh State Quantum Mission has an estimated investment target of Rs 4,000 crore over five years, with Phase I (2025–2027) focused on infrastructure, education and related capacity-building. Land allocation figures for the Quantum Valley campus itself have also varied across official statements — one account cites 54 acres of land in Amaravati, with the project's Detailed Project Report (DPR) already approved by APCRDA, while another puts the Phase I campus at 50 acres, with the Detailed Project Report already approved by APCRDA.

Practical effect

For the Quantum Valley programme, the 64th-meeting decision moves the project from planning/DPR-approval stage into contracted execution: L&T is now the awarded contractor for both the Quantum Facility building and the twin office towers, meaning construction mobilisation and timelines can begin. For Amaravati residents and land-pooling farmers, the meeting's land and compensation decisions (Mothadaka land pooling for the Inner Ring Road and railway, Rs 122 crore Endowments compensation, and ratified annuity borrowings) indicate continued expansion of the notified capital region's infrastructure footprint and financial commitments to farmers who pooled land. For prospective office tenants and IT/quantum-tech investors, the twin towers' commercial floor space (reported at 3.7 million sq ft in the April 2026 administrative approval) is the key capacity figure to track as construction proceeds. HappyNest homebuyers get near-term relief via the APRERA renewal-fee waiver rather than a change to project delivery timelines themselves.

Frequently asked questions

What exactly did APCRDA approve on 4 August 2026?

At its 64th Authority meeting, chaired by CM N. Chandrababu Naidu, APCRDA approved awarding L&T the Rs 1,280-crore Quantum Facility Project contract and the construction contract for the two Quantum Valley towers, along with a Vijayawada-Amaravati ropeway, a Krishna River bridge feasibility study, digital infrastructure tenders, HappyNest housing relief, and land pooling/compensation items.

Is the Quantum Facility Project the same as the Quantum Valley twin towers?

No. They were reported as two separate items approved at the same meeting: the Rs 1,280-crore Quantum Facility Project contract to L&T, and a separate construction contract to L&T for the twin Quantum Valley towers, reported at Rs 1,205 crore.

Why do the tower cost and floor-count figures differ between sources?

APCRDA's earlier 60th meeting (23 April 2026) had granted administrative approval of Rs 1,208.41 crore for G+43-floor twin towers (T1/T2), while coverage of the 64th meeting describes the newly awarded construction contract as being for two 18-storey towers at Rs 1,205 crore. Both figures come from official briefings, but public reporting has not fully reconciled the discrepancy as of August 2026.

What happens to land pooling farmers under this decision?

The authority endorsed Mothadaka village residents' resolution to contribute land (reported as 2,344 acres in one account and 2,340 acres in another) for the Inner Ring Road and a new railway line, and ratified borrowings of nearly Rs 300 crore in annuity payments to farmers who had pooled land for the capital city project.

What is the status of the Krishna River bridge?

It is at the feasibility/consultant-appointment stage only — the 64th meeting approved a feasibility study and a consultant to assess bridge requirements for the proposed Amaravati-Vijayawada-Guntur mega city; no construction contract has been awarded.

Does this decision affect HappyNest housing project homebuyers?

Yes — the authority revived the HappyNest project and secured an APRERA waiver of renewal fees so buyers face no extra financial burden from project delays, but this is a fee relief measure, not a new construction timeline announcement.